Question_Set_2_and_Responses.pdf
PDF 79 KB Posted
- Attached to
- Storage Aids System at Eglin AFB, Florida
- Solicitation number
- FA8604-19-R-8115
View the file
Other files
| File | Type | Posted |
|---|---|---|
| All_Questions_with_Responses.pdf | ||
| Amendment_2.pdf | ||
| Question_Set_3_and_Responses.pdf | ||
| First_Question_Set_and_Answers.pdf | ||
| FA8604-19-R-8115_Amendment_1.pdf | ||
| LEG803-01_R1.dwg | DWG drawing | |
| Proposal_Checklist.Pricing_Summary_Sheet.docx | DOCX document | |
| FA8604-19-R-8115.pdf | ||
| LEG803-01.dwg | DWG drawing |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I have a couple questions for this project at Eglin AFB – 96TH LRS.
In regards to the Tire Carousels, can you answer the following questions:
• What is the smallest size tire?
A. 10”
• What is the largest size tire?
A. 45”
• What % of the total is each? (ie: 75% small/25% large) or quantities A: There are approximately 420 tires total at present.
Percentage of tires Less than 28” diameter – 50% 28” dia. – 32” dia. – 25% 32” dia. - 45” dia. – 20% Larger than 45” – 5% (to be stored in tire pallet rack next to carousel units)
• What is the clear ceiling height?
A. 22’-6” to joists, lights in the area are at 20’.
In regards to fire suppression and electrical hook-ups I just wanted to clarify the requirements:
• Are you asking us to run all electrical to the units we are installing or will the base run the necessary electrical to the locations and we do the hook up?
A. Contractor is responsible for running all wiring per specifications.
• Are we responsible for adding fire suppression to the mezzanine?
A. Yes