This is a Questions and Answers document for a federal contract opportunity titled "Q/A Facility 30011 Signage Update Effort." The solicitation seeks signage design and installation services for a facility, with quotes due by December 4, 2026 at 4:00 pm EST. Quotes must be submitted electronically via email to the Contract Specialist (christopher.hall.113@us.af.mil) and Contracting Officer (jessica.stamper.2@us.af.mil). The prime offeror must qualify as a small business under NAICS 339950 and may use a sign manufacturer and local installer without separate nonmanufacturer-rule or subcontracting-percentage requirements. The work is not subject to prevailing wage requirements or construction wage determinations.
Respondents must provide renderings and a price breakdown with their quotes. The signage must match or equal the 2/90 Sign Systems in terms of slide-insert function, finishes, and ADA/Braille compliance; additive-manufactured solutions are acceptable if they include changeable insert tiles. CMMC Level 1 certification is required prior to contract award but need not be completed at quote submission. A site visit will occur post-award, and the signage schedule will be distributed post-award. Proposed signage remains subject to DFARS 252.225-7001 (Buy American and Balance of Payments Program). Background checks are required for anyone accessing the base, with visitors needing REAL ID-compliant identification and enrollment in the Defense Biometric Identification System (DBIDS). The work is being performed for the U.S. Air Force at Wright-Patterson Air Force Base (WPAFB).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch 3 Clin Structure.pdf | ||
| Solicitation Amendment FA860127Q00180001 SF 30.pdf | ||
| Quest_Answ.pdf | ||
| Quest_Answ.pdf | ||
| Quest_Answ.docx | DOCX document | |
| SOW - F30011 Facility Signage Update -rv1 .pdf | ||
| Solicitation FA8601Q0018.pdf | ||
| Atch 5 Required Info.pdf | ||
| Atch 3 Clin Structure.pdf | ||
| Atch 4 Project Finishes List.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q/A Facility 30011 Signage Update Effort
Question 1 - Bid Submission Method: Please confirm whether bids should be submitted electronically through SAM.gov or via email to you.
Answer: Instructions for quote submissions can be found in paragraph 5. Quotes Due Date.
Quotes must be submitted electronically to the Contract Specialist via e-mail at christopher.hall.113@us.af.mil and Contracting Officer at jessica.stamper.2@us.af.mil. Quotes must conform to the requirements of this solicitation and be received no later than 4 December 2026 at 4:00 pm EST.
Question 2 - Prevailing Wages: Is this project subject to prevailing wage requirements?
Answer: NO, this is not prevailing wages.
Question 3 - Background Checks: Are background checks required for subcontractors on this project?
Answer: Yes, a basic background check for anyone coming on base.
Information required to submit a visitor Pass Request
1. Visitor’s first and last name exactly as it appears on their driver’s license
2. Visitor’s driver’s license or state ID number and state of issuance OR visitor’s US passport number
3. Areas visitor must access (Area A, Area B, or Base wide)
4. Days and times visitors require access.
Please ensure:
1. Your visitor has a current, valid state or federally issued REAL ID-compliant ID or bring one of the following in addition to their ID: U.S. Passport/U.S. Passport Card, U.S. Social Security Card, Original or Certified Birth Certificate, or Veterans Health ID Card (VHIC). Failure to have a REAL ID-compliant ID or additional necessary documents listed above will result in the individual being denied access.
2. Your visitor is a US citizen. For non-US citizens, contact the Foreign Disclosure Office at 937-904-2535
3. Visitors must report to Pass and Registration to pick up passes.
For informational purposes only: To gain unescorted access to a DOD installation, all individuals must establish identity, fitness, and purpose.
1. Identity: Established through valid, current federal or state REAL ID-compliant ID (and other additional ID if necessary).
2. Fitness: Established through a background check. An individual is typically fit if they have no outstanding warrants, terrorism connections, convictions for disqualifying offenses, or other disqualifying conditions. Visitors not meeting WPAFB BDP fitness standards will be denied.
3. Purpose: The person’s acceptable reason for seeking base access, such as a meeting, appointment, or facilities use.
Enrollment: All visitor passes are processed and printed using the Defense Biometric Identification System (DBIDS). DBIDS is a Department of Defense (DoD) approved Physical Access Control system used on WPAFB that assists the entry controller. All persons requiring access to WPAFB will register in DBIDS. Enrollment requires visitor to provide their social security number as well as biometrics (photo and fingerprints). All personally identifiable information is protected pursuant to the Privacy Act of 1974 as well as DOD/USAF privacy programs. Visitor’s refusing to enroll will not receive unescorted WPAFB access.
Question 4 - Please provide the sign schedule/quantities by sign type (room ID, directional, regulatory/ADA) or confirm that quantities are to be determined during a site visit.
Answer: Signage Schedule will be distributed post award.
Question 5 - Please confirm that an equal modular sign system is acceptable if it matches the 2/90 Sign Systems slide-insert function, finishes and ADA/braille compliance.
Answer: Yes, an equal modular sigh system is acceptable if it matches 2/90 sign/system insert function, finishes and ADA / Braille compliance.
Question 6 - Does the Government require the existing signs to be returned/stored, or is disposal by the contractor acceptable?
Answer: Read the SOW Section 7.2.
Question 7 - Our approach would be to manufacture the signage using durable polymer materials while maintaining the required dimensions, colors, finishes, removable inserts, tactile lettering, Grade 2 Braille, and applicable accessibility standards.
We understand that the solicitation specifies the 2/90 system “or equal,” and we would appreciate clarification on whether an additive-manufactured solution could qualify, provided we demonstrate equivalent functionality, appearance, durability, and compliance.
If acceptable for consideration, we could provide material specifications, drawings, and physical samples for evaluation.
Answer: Acceptable if the insert changeable tile is provided as well per the SOW.
Question 8 - Please confirm the CMMC level and assessment status required at quotation versus award, and any subcontractor requirements. The notice refers to Level 1, while SOW section 1.0 refers to Level 1 until November 9 and Level 2 afterward for CAD release. Can the work be quoted and performed using the public package and authorized field verification without receiving controlled CAD files?
Answer: CMMC Level 1 certification is requirement prior to contract award. It does not have to be complete upon submission of the quote, but if that contractor is later selected for award and does not have CMMC Level 1 complete, they will no longer be considered for award. Level 2 CMMC will not be required for this acquisition.
Question 9 - Is a site visit mandatory? The SOW says one may be scheduled within one week of posting if requested. Please confirm whether a public visit date is available and the deadline to request attendance.
Answer: Site visit will occur post contract award.
Question 10 - Does the current public package contain all bid-stage sign text, finish/color choices and placement information, or may any items be finalized after award?
Answer: Finishes will remain as noted in SOW.
Question 11 - Are the renderings and that price breakdown due with the quote, or after award?
Answer: Yes, the renderings and price breakdown due with the quote.
Question 12 - Please confirm the controlling material-origin/nonmanufacturer and subcontracting requirements for a small-business prime using a sign manufacturer and local installer, and any applicable installation wage determination or bonding requirements.
Answer: The prime offeror must qualify as a small business under NAICS 339950.
The prime may use a sign manufacturer and local installer; the solicitation does not impose a separate nonmanufacturer-rule or subcontracting-percentage requirement.
Proposed signage remains subject to DFARS 252.225-7001, Buy American and Balance of Payments Program. Offerors must comply with the applicable domestic/qualifying-country source requirements and identify any foreign end products as required by the solicitation’s Buy American certifications.
The solicitation does not currently include an installation wage determination, construction wage clause, or bonding requirement. Any additional labor or bonding requirements would be provided by formal solicitation amendment.