Requirements Document dated 26 December 2017
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q&A_27_December_2017.docx | DOCX document | |
| FAQ_26_December_2017.docx | DOCX document | |
| PWS_revised_1_year.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REVISED 26 Dec 17
REQUIREMENTS DOCUMENT
IN SUPPORT OF
FIRE SUPPRESSION SYSTEM SERVICES
FOR
AEROSPACE SYSTEMS DIRECTORATE
AIR FORCE RESEARCH LABORATORY
WRIGHT PATTERSON AFB, OH
The Aerospace Systems Directorate, Air Force Research Laboratory, is seeking a contract for normal maintenance services, yearly inspections, testing, upgrades, modifications, and emergency maintenance for three (3) high pressure carbon dioxide fire suppression systems and nine (9) low pressure carbon dioxide systems installed between 1940 and 2008 and one (1) Aqueous Fire Fighting Foam (AFFF) system. The Contractor shall furnish all equipment, labor, and materials, and shall perform all operations necessary to complete the work.
Estimated Annual Requirements:
| Description |
| Annual Quantity |
| Low pressure CO2 system inspection |
| 9 EA |
| High pressure CO2 system inspection |
| 3 EA |
| AFFF inspection |
| 1 EA |
| Emergency Call |
| 1 EA (20 hours) |
| Backup battery replacement |
| 4 EA (2 calls) |
| Main tank top off |
| 17,000 lb (2 calls) |
| Main tank refrigeration inspection |
| 1 EA |
| Main tank refrigeration service |
| 1 EA |
| Upgrade low pressure CO2 panel |
| 1 EA |
| Install isolation valve |
| 1 EA |
Minimum Requirements:
1. CONTRACTOR QUALIFICATIONS
Contractor shall have a license from the Ohio state fire marshal’s office.
2. ISOLATION VALVES
Isolation valve shall be installed per PWS Para. 15b in Bldg 18C, Rm B003 (Battery Vault). The main header for this valve is 1 ½ inch diameter.
3. UPGRADE SPECIFICATIONS
Equipment replaced or modified in PWS Para. 15b shall be compatible with the equipment listed below.
FLOOD
30 SECOND DELAY
LOW PRESSURE
| LOCATION |
| PANEL |
TYPE
| SPURT |
| MANUAL |
DUMP
AUTOMATIC
DUMP
| INPUTS |
| OUTPUTS |
| Bldg 18C, Battery vault B003 |
| Chemetron Micro 1 EV |
| X |
| X |
| · Heat detector |
· Manual switch
· Bldg alarm
· HVAC shutdown
· Annunciators
· Trouble
Phoenix Rig No Delay
HIGH PRESSURE
Bldg 490
RC-152
Gemini Kidde-Fenwal
WK-265134-000
| X |
| X |
| · UV/IR Detector |
· Manual Switch
· Annunciators