General Decision Number - 22 JULY 11.docx

DOCX document 92 KB Posted

Attached to
Renovate/Construct Aero Evacuation Squadron Facility, Building 4004 Federal contract opportunity
Solicitation number
FA8601-11-B-0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

Wage Determination OH2 - 22 July 2011

View the file

Other files for this federal contract opportunity

Other files attached to Renovate/Construct Aero Evacuation Squadron Facility, Building 4004, newest first.
File Type Posted
RFI Responses4.pdf PDF
RFI Responses3.pdf PDF
RFI Responses2.pdf PDF
RFI Responses.pdf PDF
General Decision Number - OH29 - 12 AUG 2011.pdf PDF
FA8601-11-B-0007 - Amendment 2.pdf PDF
FA8601-11-B-0007 - Site Visit SIgn-In Sheet.pdf PDF
FA8601-11-B-0007 - Amendment 1.pdf PDF
General Decision Number - OH29 - 22 JULY 2011.docx DOCX document
100 AERO EVAC SPECIFICATIONS VOL 2 OF 2.pdf PDF
FA8601-11-B-0007.pdf PDF
100 AERO EVAC SPECIFICATIONS VOL 1 OF 2.pdf PDF
100 DRAWINGS 28 FEB 2011.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: OH100002 07/22/2011 OH2

Superseded General Decision Number: OH20080002

State: Ohio

Construction Types: Heavy and Highway

Counties: Ohio Statewide.

Heavy and Highway Construction Projects

Modification Number Publication Date 0 03/12/2010 1 03/19/2010 2 04/09/2010 3 04/16/2010 4 04/23/2010 5 04/30/2010 6 05/07/2010 7 05/21/2010 8 06/04/2010 9 06/25/2010 10 07/02/2010 11 07/09/2010 12 07/23/2010 13 07/30/2010 14 08/13/2010 15 08/27/2010 16 09/03/2010 17 09/10/2010 18 10/01/2010 19 10/29/2010 20 12/03/2010 21 12/10/2010 22 12/17/2010 23 12/24/2010 24 12/31/2010 25 01/14/2011 26 01/21/2011 27 01/28/2011 28 02/04/2011 29 03/25/2011 30 04/08/2011 31 04/29/2011 32 05/06/2011 33 05/20/2011 34 05/27/2011 35 06/03/2011 36 06/10/2011 37 06/17/2011 38 07/01/2011 39 07/08/2011 40 07/22/2011

BRKY0007-003 06/01/2011

LAWRENCE

Rates Fringes

Bricklayer, Stonemason...........$ 28.29 16.80

BROH0001-001 07/01/2010

DEFIANCE, FULTON (Excluding Fulton, Amboy & Swan Creek Townships), HENRY (Excluding Monroe, Bartlow, Liberty, Washington, Richfield, Marion, Damascus & Townships & that part of Harrison Township outside corporate limits of city of Napoleon), PAULDING, PUTNAM and WILLIAMS COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 29.30 11.81

BROH0001-004 06/01/2010

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 25.77 10.03

BROH0003-002 07/01/2010

FULTON (Townships of Amboy, Swan Creek & Fulton), HENRY (Townships of Washington, Damascus, Richfield, Bartlow, Liberty, Harrison, Monroe, & Marion), LUCAS and WOOD (Townships of Perrysburg, Ross, Lake, Troy, Freedom, Montgomery, Webster, Center, Portage, Middleton, Plain, Liberty, Henry, Washington, Weston, Milton, Jackson & Grand Rapids) COUNTIES

Bricklayer, Stonemason...........$ 28.10 15.41

BROH0005-003 05/01/2011

CUYAHOGA, LORAIN & MEDINA (Hinckley, Granger, Brunswick, Liverpool, Montville, York, Homer, Harrisville, Chatham, Litchfield & Spencer Townships and the city of Medina)

BRICKLAYER

BRICKLAYERS; CAULKERS;

CLEANERS; POINTERS; &

STONEMASONS.................$ 31.25 11.78

SANDBLASTERS................$ 31.75 11.78

SEWER BRICKLAYERS & STACK

BUILDERS....................$ 31.75 11.78

SEWER BRICKLAYERS; STACK

BUILDERS; & SWING SCAFFOLDS.$ 30.91 11.78

SWING SCAFFOLDS.............$ 32.00 11.78

BROH0006-005 05/01/2010

CARROLL, COLUMBIANA (Knox, Butler, West & Hanover Townships), STARK & TUSCARAWAS

Bricklayer, Stonemason...........$ 25.95 10.58

BROH0007-005 06/01/2010

PORTAGE & SUMMIT

Rates Fringes

BRICKLAYER.......................$ 28.08 12.32

BROH0007-010 05/01/2010

PORTAGE & SUMMIT

Rates Fringes

MASON - STONE....................$ 28.52 8.45

BROH0008-001 06/01/2011

COLUMBIANA (Salem, Perry, Fairfield, Center, Elk Run, Middleton, & Unity Townships and the city of New Waterford), MAHONING & TRUMBULL

BRICKLAYER.......................$ 25.55 15.34

* BROH0009-002 07/01/2011

BELMONT & MONROE COUNTIES and the Townships of Warren & Mt.

Pleasant and the Village of Dillonvale in JEFFERSON COUNTY

Bricklayer, Stonemason...........$ 24.72 15.61 Refractory.......................$ 29.44 15.61

* BROH0010-002 07/01/2011

COLUMBIANA (St. Clair, Madison, Wayne, Franklin, Washington, Yellow Creek & Liverpool Townships) & JEFFERSON (Brush Creek & Saline Townships)

Bricklayer, Stonemason...........$ 25.82 14.09

BROH0014-002 07/01/2005

HARRISON & JEFFERSON (Except Mt. Pleasant, Warren, Brush Creek, Saline & Salineville Townships & the Village of Dillonvale)

Bricklayer, Stonemason...........$ 24.01 8.85

BROH0016-002 05/01/2011

ASHTABULA, GEAUGA, and LAKE COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 29.18 12.54

BROH0018-002 11/01/2010

BROWN, BUTLER, CLERMONT, HAMILTON, PREBLE (Gasper, Dixon, Israel, Lanier, Somers & Gratis Townships) & WARREN COUNTIES:

Bricklayer, Stonemason...........$ 26.44 10.01

BROH0022-004 06/30/2010

CHAMPAIGN, CLARK, CLINTON, DARKE, GREENE, HIGHLAND, LOGAN,

MIAMI, MONTGOMERY, PREBLE (Jackson, Monroe, Harrison, Twin, Jefferson & Washington Townships) and SHELBY COUNTIES

Bricklayer, Stonemason...........$ 25.07 10.16

BROH0032-001 06/01/2011

GALLIA & MEIGS

Rates Fringes

Bricklayer, Stonemason...........$ 30.72 12.23

BROH0035-002 07/01/2010

ALLEN, AUGLAIZE, MERCER and VAN WERT COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 24.67 11.57

BROH0039-002 06/01/2011

ADAMS & SCIOTO

Rates Fringes

Bricklayer, Stonemason...........$ 29.17 14.62

BROH0040-003 06/01/2010

ASHLAND, CRAWFORD, HARDIN, HOLMES, MARION, MORROW, RICHLAND,

WAYNE and WYANDOT (Except Crawford, Ridge, Richland & Tymochtee Townships) COUNTIES

Bricklayer, Stonemason...........$ 26.30 15.44

FOOTNOTE: Layout Man and Sawman rate: $1.00 per hour above journeyman rate.

Free standing stack work ground level to top of stack;

Sandblasting and laying of carbon masonry material in swing stage and/or scaffold; Ramming and spading of plastics and gunniting: $1.50 per hour above journeyman rate.

"Hot" work: $2.50 above journeyman rate.

BROH0044-002 06/01/2011

Rates Fringes

Bricklayer, Stonemason

COSHOCTON, FAIRFIELD,

GUERNSEY, HOCKING, KNOX,

KICKING, MORGAN,

MUSKINGUM, NOBLE (Beaver, Buffalo, Seneca & Wayne Townships) & PERRY

COUNTIES:...................$ 25.50 11.45

* BROH0045-002 06/01/2011

FAYETTE, JACKSON, PIKE, ROSS and VINTON COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 29.20 11.63

BROH0046-002 06/01/2010

ERIE, HANCOCK, HURON, OTTAWA, SANDUSKY, SENECA, WOOD (Perry & Bloom Townships) and WYANDOT (Tymochtee, Crawford, Ridge & Richland Townships) COUNTIES & the Islands of Lake Erie north of Sandusky

Bricklayer, Stonemason...........$ 27.03 15.09

FOOTNOTE: Layout Man and Sawman rate: $1.00 per hour above journeyman rate.

Free standing stack work ground level to top of stack;

Sandblasting and laying of carbon masonry material in swing stage and/or scaffold; Ramming and spading of plastics and gunniting: $1.50 per hour above journeyman rate.

"Hot" work: $2.50 above journeyman rate.

BROH0052-001 06/01/2011

ATHENS COUNTY

Rates Fringes

Bricklayer, Stonemason...........$ 26.60 12.75

BROH0052-003 06/01/2011

NOBLE (Brookfield, Noble, Center, Sharon, Olive, Enoch, Stock, Jackson, Jefferson & Elk Townships) and WASHINGTON COUNTIES

Bricklayer, Stonemason...........$ 26.60 12.75

BROH0055-003 06/01/2010

DELAWARE, FRANKLIN, MADISON, PICKAWAY and UNION COUNTIES

Rates Fringes

Bricklayer, Stonemason...........$ 27.21 12.49

CARP0003-004 05/01/2009

MAHONING & TRUMBULL

Rates Fringes

CARPENTER........................$ 24.12 12.15

CARP0069-003 05/01/2009

CARROLL, STARK, TUSCARAWAS & WAYNE

Rates Fringes

CARPENTER........................$ 24.29 10.72

CARP0069-006 05/01/2009

COSHOCTON, HOLMES, KNOX & MORROW

Rates Fringes

CARPENTER........................$ 22.95 10.10

CARP0171-002 05/01/2009

BELMONT, COLUMBIANA, HARRISON, JEFFERSON & MONROE

Rates Fringes

CARPENTER........................$ 24.12 12.39

CARP0200-002 05/01/2011

ADAMS, ATHENS, DELAWARE, FAIRFIELD, FAYETTE, FRANKLIN, GALLIA,

GUERNSEY, HIGHLAND, HOCKING, JACKSON, LAWRENCE, LICKING,

MADISON, MARION, MEIGS, MORGAN, MUSKINGUM, NOBLE, PERRY,

PICKAWAY, PIKE, ROSS, SCIOTO, UNION, VINTON and WASHINGTON

COUNTIES

CARPENTER........................$ 27.17 11.30

Diver............................$ 39.41 10.40

PILEDRIVERMAN....................$ 27.17 11.30

CARP0248-005 07/01/2008

LUCAS & WOOD

Rates Fringes

CARPENTER........................$ 27.27 14.58

CARP0248-008 07/01/2008

Rates Fringes

CARPENTER

DEFIANCE, FULTON, HANCOCK,

HENRY, PAULDING & WILLIAMS

COUNTIES....................$ 23.71 13.28

CARP0254-002 05/01/2009

ASHTABULA, CUYAHOGA, GEAUGA & LAKE

Rates Fringes

CARPENTER........................$ 29.96 11.41

CARP0372-002 07/01/2008

ALLEN, AUGLAIZE, HARDIN, MERCER, PUTNAM & VAN WERT

Rates Fringes

CARPENTER........................$ 23.18 13.28

CARP0639-003 05/01/2010

MEDINA, PORTAGE & SUMMIT

Rates Fringes

CARPENTER........................$ 28.57 11.84

CARP0735-002 05/01/2009

ASHLAND, ERIE, HURON, LORAIN & RICHLAND

Rates Fringes

CARPENTER........................$ 23.58 10.34

CARP1311-001 05/01/2011

BROWN, BUTLER, CHAMPAIGN, CLARK, CLERMONT, CLINTON, DARKE,

GREENE, HAMILTON, LOGAN, MIAMI, MONTGOMERY, PREBLE, SHELBY &

WARREN

Carpenter & Piledrivermen........$ 25.74 12.96 Diver............................$ 40.58 9.69

CARP1393-002 07/01/2008

CRAWFORD, DEFIANCE, FULTON, HANCOCK, HENRY, LUCAS, OTTAWA,

PAULDING, SANDUSKY, SENECA, WILLIAMS & WOOD

Piledrivermen & Diver's Tender...$ 27.30 16.05

DIVERS - $250.00 per day

CARP1393-003 07/01/2008

ALLEN, AUGLAIZE, HARDIN, MERCER, PUTNAM, VAN WERT & WYANDOT

Rates Fringes

Piledrivermen & Diver's Tender...$ 25.15 15.92

DIVERS - $250.00 per day

CARP1871-006 05/01/2009

BELMONT, HARRISON, & MONROE

Rates Fringes

Diver, Wet.......................$ 44.19 12.14 Piledrivermen; Diver, Dry........$ 29.46 12.14

CARP1871-008 05/01/2009

ASHLAND, ASHTABULA, CUYAHOGA, ERIE, GEAUGA, HURON, LAKE,

LORAIN, MEDINA, PORTAGE, RICHLAND & SUMMIT

Diver, Wet.......................$ 42.69 12.91 Piledrivermen; Diver, Dry........$ 28.46 12.91

CARP1871-014 05/01/2009

CARROLL, STARK, TUSCARAWAS & WAYNE

Rates Fringes

Diver, Wet.......................$ 35.64 11.73 Piledrivermen; Diver, Dry........$ 23.76 11.73

CARP1871-015 05/01/2009

COSHOCTON, HOLMES, KNOX & MORROW

Rates Fringes

Diver, Wet.......................$ 34.29 10.88 Piledrivermen; Diver, Dry........$ 22.86 10.88

CARP1871-017 05/01/2009

MAHONING & TRUMBULL

Rates Fringes

Diver, Wet.......................$ 37.31 12.38 Piledrivermen; Diver, Dry........$ 24.87 12.38

CARP2235-012 01/01/2010

COLUMBIANA & JEFFERSON

Rates Fringes

PILEDRIVERMAN....................$ 29.95 12.25

CARP2239-001 07/01/2008

CRAWFORD, OTTAWA, SANDUSKY, SENECA & WYANDOT

Rates Fringes

CARPENTER........................$ 23.71 13.28

ELEC0008-002 04/27/2009

DEFIANCE, FULTON, HANCOCK, HENRY, LUCAS, OTTAWA, PAULDING,

PUTNAM, SANDUSKY, SENECA, WILLIAMS & WOOD

CABLE SPLICER....................$ 35.70 17.06

ELECTRICIAN......................$ 34.00 16.98

ELEC0032-003 06/01/2011

ALLEN, AUGLAIZE, HARDIN, LOGAN, MERCER, SHELBY, VAN WERT &

WYANDOT (Crawford, Jackson, Marseilles, Mifflin, Ridgeland, Ridge & Salem Townships)

ELECTRICIAN......................$ 27.10 12.35

ELEC0032-004 06/01/1998

ALLEN, HARDIN, VAN WERT & WYANDOT (Crawford, Jackson, Marseilles, Mifflin, Richland, Ridge & Salem Townships)

Line Construction Equipment Operator..........$ 20.27 4.12+a Groundman Truck Driver......$ 14.43 3.63+a Lineman.....................$ 22.52 4.31+a

FOOTNOTE: a. Half day's Paid Holiday: The last 4 hours of the workday prior to Christmas or New Year's Day

ELEC0038-002 04/25/2011

CUYAHOGA, GEAUGA (Bainbridge, Chester & Russell Townships) & LORAIN (Columbia Township)

ELECTRICIAN

Excluding Sound & Communications Work.........$ 35.48 18.78

ELEC0038-008 05/01/2006

CUYAHOGA, GEAUGA (Bainbridge, Chester & Russell Townships) & LORAIN (Columbia Township)

Sound & Communication Technician Communications Technician...$ 21.20 8.12+a+b Installer Technician........$ 20.45 8.04+a+b

FOOTNOTES;

a. 6 Paid Holidays: New Year's Day; Memorial Day; July 4th;

Labor Day; Thanksgiving Day; & Christmas Day

b. 1 week's paid vacation for 1 year's service; 2 weeks' paid vacation for 2 or more years' service

ELEC0064-003 12/01/2010

COLUMBIANA (Butler, Fairfield, Perry, Salem & Unity Townships) MAHONING (Austintown, Beaver, Berlin, Boardman, Canfield, Ellsworth, Coitsville, Goshen, Green, Jackson, Poland, Springfield & Youngstown Townships), & TRUMBULL (Hubbard & Liberty Townships)

ELECTRICIAN......................$ 30.27 12.42

ELEC0071-001 12/29/2008

ASHLAND, CHAMPAIGN, CLARK, COSHOCTON, CRAWFORD, DELAWARE,

FAIRFIELD, FAYETTE, FRANKLIN, GUERNSEY, HIGHLAND, HOCKING,

JACKSON (Coal, Jackson, Liberty, Milton, Washington & Wellston Townships), KNOX, LICKING, MADISON, MARION, MONROE, MORGAN, MORROW, MUSKINGUM, NOBLE, PERRY, PICKAWAY, PIKE (Beaver, Benton, Jackson, Mifflin, Pebble, Peepee, Perry & Seal Townships), RICHLAND, ROSS, TUSCARAWAS (Auburn, Bucks, Clay, Jefferson, Oxford, Perry, Salem, Rush, Washington & York Townships), UNION, VINTON (Clinton, Eagle, Elk, Harrison, Jackson, Richland & Swan Townships), and WASHINGTON COUNTIES

Equipment Operators.........$ 27.45 10.51 Groundmen...................$ 19.83 8.92 Linemen & Cable Splicers....$ 30.50 11.15

ELEC0071-004 12/29/2008

AUGLAIZE, CLINTON, DARKE, GREENE, LOGAN, MERCER, MIAMI,

MONTGOMERY, PREBLE, and SHELBY COUNTIES

Equipment Operator..........$ 27.45 10.51 Groundman...................$ 19.83 8.92 Lineman & Cable Splicers....$ 30.50 11.15

ELEC0071-005 12/28/2009

ASHTABULA, CUYAHOGA, GEAUGA, LAKE & LORAIN

Rates Fringes

LINE CONSTRUCTION: Equipment Operator DOT/Traffic Signal & Highway Lighting Projects...$ 28.39 11.49 Municipal Power/Transit Projects....................$ 33.33 12.67 LINE CONSTRUCTION: Groundman DOT/Traffic Signal & Highway Lighting Projects...$ 22.09 10.00 Municipal Power/Transit Projects....................$ 25.92 10.91

LINE CONSTRUCTION:

Linemen/Cable Splicer DOT/Traffic Signal & Highway Lighting Projects...$ 31.55 12.24 Municipal Power/Transit Projects....................$ 37.03 13.54

ELEC0071-008 12/29/2008

COLUMBIANA, MAHONING, and TRUMBULL COUNTIES

Rates Fringes

Line Construction Equipment Operator..........$ 27.45 10.51 Groundman...................$ 19.83 8.92 Lineman & Cable Splicers....$ 30.50 11.15

ELEC0071-010 12/29/2008

BELMONT, CARROLL, HARRISON, HOLMES, JEFFERSON, MEDINA, PORTAGE,

STARK, SUMMIT, and WAYNE COUNTIES

Equipment Operator..........$ 27.45 10.51 Groundman...................$ 19.83 8.92 Lineman & Cable Splicers....$ 30.50 11.15

ELEC0071-013 12/29/2008

BROWN, BUTLER, CLERMONT, HAMILTON, and WARREN COUNTIES

Rates Fringes

Line Construction Equipment Operator..........$ 27.45 10.51 Groundman...................$ 19.83 8.92 Lineman & Cable Splicers....$ 30.50 11.15

ELEC0082-002 11/29/2010

CLINTON, DARKE, GREENE, MIAMI, MONTGOMERY, PREBLE & WARREN

(Wayne, Clear Creek & Franklin Townships)

ELECTRICIAN......................$ 27.30 14.93

ELEC0082-006 05/24/2004

CLINTON, DARKE, GREENE, MIAMI, MONTGOMERY, PREBLE & WARREN

(Wayne, Clear Creek & Franklin Townships)

Sound & Communication Technician Cable Puller................$ 9.14 4.91 Installer/Technician........$ 18.28 6.32

ELEC0129-003 03/01/2010

LORAIN (Except Columbia Township) & MEDINA (Litchfield & Liverpool Townships)

ELECTRICIAN......................$ 31.00 13.80

ELEC0129-004 03/01/2010

ERIE & HURON (Lyme, Ridgefield, Norwalk, Townsend, Wakeman, Sherman, Peru, Bronson, Hartland, Clarksfield, Norwich, Greenfield, Fairfield, Fitchville & New London Townships)

ELECTRICIAN......................$ 31.00 13.80

ELEC0141-003 08/30/2010

BELMONT COUNTY

Rates Fringes

CABLE SPLICER....................$ 28.16 19.80

ELECTRICIAN......................$ 27.91 19.80

ELEC0212-003 01/01/2006

BROWN, CLERMONT & HAMILTON

Rates Fringes

Sound & Communication Technician.......................$ 20.45 6.95

ELEC0212-005 05/31/2010

BROWN, CLERMONT, and HAMILTON COUNTIES

Rates Fringes

ELECTRICIAN......................$ 26.11 14.34

ELEC0245-003 08/30/2009

DEFIANCE, FULTON, HANCOCK, HENRY, HURON, LUCAS, OTTAWA,

PAULDING, PUTNAM, SANDUSKY, SENECA, WILLIAMS, and WOOD COUNTIES

Cable Splicer...............$ 35.85 20.25%+4.80+a Groundman/Truck Driver......$ 14.50 20.25%+4.80+a Heli-arc Welding............$ 31.47 20.25%+4.80+a Lineman.....................$ 33.15 20.25%+4.80+a Operator - Class 1..........$ 26.52 20.25%+4.80+a Operator - Class 2..........$ 23.21 20.25%+4.80+a Traffic Signal & Lighting Technician..................$ 29.84 20.25%+4.80+a

FOOTNOTE: a. 6 Observed Holidays: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; & Christmas Day. Employees who work on a holiday shall be paid at a rate of double their applicable classified straight-time rates for the work performed on such holiday.

ELEC0246-006 11/01/2009

CARROLL (South of Fox, Harrison, Rose & Washington Townships), COLUMBIANA (South of Butler, Fairfield, Knox, Salem & Unity Townships), HARRISON, and JEFFERSON COUNTIES

ELECTRICIAN......................$ 33.00 22.77+a

FOOTNOTE: a. 1 1/2 Paid Holidays: The last scheduled workday prior to Christmas & 4 hours on Good Friday.

ELEC0306-005 05/31/2010

MEDINA (Brunswick, Chatham, Granger, Guilford, Harrisville, Hinckley, Homer, Lafayette, Medina, Montville, Sharon, Spencer, Wadsworth, Westfield & York Townships), PORTAGE (Atwater, Aurora, Brimfield, Deerfield, Franklin, Mantua, Randolph, Ravenna, Rootstown, Shalersville, Streetsboro & Suffield Townships), SUMMIT & WAYNE (Baughman, Canaan, Chester, Chippewa, Congress, Green, Milton, & Wayne Townships)

CABLE SPLICER....................$ 36.39 5%+11.76

ELECTRICIAN......................$ 33.69 5%+11.76

ELEC0317-002 06/01/2010

GALLIA & LAWRENCE

Rates Fringes

CABLE SPLICER....................$ 32.68 18.13

ELECTRICIAN......................$ 31.87 19.46

ELEC0317-008 06/01/1998

ADAMS, ATHENS, GALLIA, JACKSON (Bloomfield, Franklin, Hamilton, Lick, Jefferson, Scioto & Madison Townships), LAWRENCE, MEIGS, PIKE (Camp Creek, Marion, Newton, Scioto, Sunfish & Union Townships), SCIOTO & VINTON (Brown, Knox, Madison, Vinton & Wilkesville Townships)

Cable Splicers..............$ 23.66 8.48 Equipment Operators.........$ 17.14 8.25 Groundmen...................$ 13.92 8.14 Linemen.....................$ 21.42 8.40

ELEC0540-003 06/05/1997

TUSCARAWAS COUNTY (North of Auburn, Clay, Rush & York Townships)

Rates Fringes

Line Construction Groundman; & Truck Driver...$ 14.65 8.18 Line Equipment Operator.....$ 19.02 8.69 Lineman; & Cable Splicer....$ 21.86 9.01

ELEC0540-005 12/27/2010

CARROLL (Northern half, including Fox, Harrison, Rose & Washington Townhships), COLUMBIANA (Knox Township), HOLMES, MAHONING (Smith Township), STARK, TUSCARAWAS (North of Auburn, Clay, Rush & York Townships), and WAYNE (South of Baughman, Chester, Green & Wayne Townships) COUNTIES

ELECTRICIAN......................$ 27.52 18.40

ELEC0573-003 11/29/2010

ASHTABULA (Colebrook, Wayne, Williamsfield, Orwell & Windsor Townships), GEAUGA (Auburn, Middlefield, Parkman & Troy Townships), MAHONING (Milton Township), PORTAGE (Charlestown, Edinburg, Freedom, Hiram, Nelson, Palmyra, Paris & Windham Townships), and TRUMBULL (Except Liberty & Hubbard Townships)

ELECTRICIAN......................$ 29.15 14.59

ELEC0575-001 05/31/2010

ADAMS, FAYETTE, HIGHLAND, HOCKING, JACKSON (Bloomfield, Franklin, Hamilton, Jefferson, Lick, Madison, Scioto, Coal, Jackson, Liberty, Milton & Washington Townships), PICKAWAY (Deer Creek, Perry, Pickaway, Salt Creek & Wayne Townships), PIKE (Beaver, Benton, Jackson, Mifflin, Pebble, PeePee, Perry, Seal, Camp Creek, Newton, Scioto, Sunfish, Union & Marion Townships), ROSS, SCIOTO & VINTON (Clinton, Eagle, Elk, Harrison, Jackson, Richland & Swan Townships)

ELECTRICIAN......................$ 30.69 12.48

ELEC0648-001 09/06/2010

BUTLER and WARREN COUNTIES (Deerfield, Hamilton, Harlan, Massie, Salem, Turtle Creek, Union & Washington Townships)

CABLE SPLICER....................$ 29.17 12.69

ELECTRICIAN......................$ 28.67 12.69

ELEC0673-004 01/03/2011

ASHTABULA (Excluding Orwell, Colebrook, Williamsfield, Wayne & Windsor Townships), GEAUGA (Burton, Chardon, Claridon, Hambden, Huntsburg, Montville, Munson, Newbury & Thompson Townships) and

LAKE COUNTIES

CABLE SPLICER....................$ 32.19 16.18

ELECTRICIAN......................$ 31.94 16.17

ELEC0683-002 05/30/2011

CHAMPAIGN, CLARK, DELAWARE, FAIRFIELD, FRANKLIN, MADISON,

PICKAWAY (Circleville, Darby, Harrison, Jackson, Madison, Monroe, Muhlenberg, Scioto, Walnut & Washington Townships), and

UNION COUNTIES

CABLE SPLICER....................$ 30.70 13.99

ELECTRICIAN......................$ 30.10 13.97

ELEC0688-003 01/05/2011

ASHLAND, CRAWFORD, HURON (Richmond, New Haven, Ripley & Greenwich Townships), KNOX (Liberty, Clinton, Union, Howard, Monroe, Middleberry, Morris, Wayne, Berlin, Pike, Brown & Jefferson Townships), MARION, MORROW, RICHLAND and WYANDOT (Sycamore, Crane, Eden, Pitt, Antrim & Tymochtee Townships)

ELECTRICIAN......................$ 26.25 14.30

ELEC0867-001 06/01/1998

ERIE

Rates Fringes

Line Construction Lineman; Cable Splicer; & Equipment Operator..........$ 20.75 4.09 Truck Driver (Winch) Groundman; & Groundman......$ 13.49 3.87

ELEC0972-002 06/01/2011

ATHENS, MEIGS, MONROE, MORGAN, NOBLE, VINTON (Brown, Knox, Madison, Vinton & Wilkesville Townships), and WASHINGTON

COUNITES

CABLE SPLICER....................$ 31.59 20.11

ELECTRICIAN......................$ 31.34 20.10

ELEC1105-001 05/30/2010

COSHOCTON, GUERNSEY, KNOX (Jackson, Clay, Morgan, Miller, Milford, Hilliar, Butler, Harrison, Pleasant & College Townships), LICKING, MUSKINGUM, PERRY, and TUSCARAWAS (Auburn, York, Clay, Jefferson, Rush, Oxford, Washington, Salem, Perry & Bucks Townships) COUNTIES

ELECTRICIAN......................$ 27.19 13.49

ENGI0018-003 05/04/2011

ASHTABULA, CUYAHOGA, ERIE, GEAUGA, LAKE, LORAIN, MEDINA,

PORTAGE, and SUMMIT COUNTIES

OPERATOR: Power Equipment

GROUP 1.....................$ 31.48 12.80

GROUP 2.....................$ 31.38 12.80

GROUP 3.....................$ 30.34 12.80

GROUP 4.....................$ 29.12 12.80

GROUP 5.....................$ 23.83 12.80

GROUP 6.....................$ 31.73 12.80

GROUP 7.....................$ 31.98 12.80

OPERATING ENGINEER CLASSIFICATIONS

GROUP 1 - Air Compressor on Steel Erection; Barrier Moving Machine; Boiler Operator on Compressor or Generator when mounted on a Rig; Cableway; Combination Concrete Mixer & Tower; Concrete Plant (over 4 yd. Capacity); Concrete Pump;

Crane (All Types, Including Boom Truck, Cherry Picker);

Crane-Compact, Track or Rubber over 4,000 lbs. capacity;

Cranes-Self Erecting, Stationary, Track or Truck (All Configurations); Derrick; Dragline; Dredge (Dipper, Clam or Suction); Elevating Grader or Euclid Loader; Floating Equipment (All Types); Gradall; Helicopter Crew (Operator-Hoist or Winch); Hoe (all types); Hoisting Engine on Shaft or Tunnel Work; Hydraulic Gantry (Lifting System);

Industrial-Type Tractor; Jet Engine Dryer (D8 or D9) Diesel Tractor; Locomotive (Standard Gauge); Maintenance Operator Class A; Mixer, Paving (Single or Double Drum); Mucking Machine; Multiple Scraper; Piledriving Machine (All Types);

Power Shovel; Prentice Loader; Quad 9 (Double Pusher); Rail Tamper (with auto lifting & aligning device); Refrigerating Machine (Freezer Operation); Rotary Drill, on Caisson work;

Rough Terrain Fork Lift with Winch/Hoist; Side-Boom;

Slip-Form Paver; Tower Derrick; Tree Shredder; Trench Machine (Over 24" wide); Truck Mounted Concrete Pump; Tug Boat; Tunnel Machine and/or Mining Machine; Wheel Excavator; and Asphalt Plant Engineer (Cleveland District Only).

GROUP 2 - Asphalt Paver; Automatic Subgrader Machine, Self-Propelled (CMI Type); Bobcat Type and/or Skid Steer Loader with Hoe Attachment Greater than 7,000 lbs.; Boring Machine More than 48"; Bulldozer; Endloader; Horizontal Directional Drill (Over 50,000 ft lbs thrust); Hydro Milling Machine; Kolman-type Loader (production type-Dirt);

Lead Greaseman; Lighting & Traffic Signal Installation Equipment (includes all groups or classifications);

Material Transfer Equipment (Shuttle Buggy) Asphalt;

Pettibone-Rail Equipment; Power Grader; Power Scraper; Push Cat; Rotomill (all), Grinders & Planers of All types;

Trench Machine (24" wide & under); Vermeer type Concrete Saw; and Maintenance Operators (Portage and Summit Counties Only).

GROUP 3 - A-Frame; Air Compressor on Tunnel Work (low pressure); Asphalt Plant Engineer (Portage and Summit Counties Only); Bobcat-type and/or Skid Steer Loader with or without Attachments; Highway Drills (all types);

Locomotive (narrow gauge); Material Hoist/Elevator; Mixer, Concrete (more than one bag capacity); Mixer, one bag capacity (Side Loader); Power Boiler (Over 15 lbs.

Pressure) Pump Operator installing & operating Well Points;

Pump (4" & over discharge); Roller, Asphalt; Rotovator (lime soil stabilizer); Switch & Tie Tampers (without lifting & aligning device); Utility Operator (Small equipment); Welding Machines; and Railroad Tie Inserter/Remover; Articulating/straight bed end dumps if assigned (minus $4.00 per hour.

GROUP 4 - Backfiller; Ballast Re-locator; Bars, Joint & Mesh Installing Machine; Batch Plant; Boring Machine Operator (48" or less); Bull Floats; Burlap & Curing Machine;

Concrete Plant (capacity 4 yd. & under); Concrete Saw (Multiple); Conveyor (Highway); Crusher; Deckhand;

Farm-type Tractor with attachments (highway); Finishing Machine; Fireperson, Floating Equipment (all types);

Forklift; Form Trencher; Hydro Hammer expect masonary;

Hydro Seeder; Pavement Breaker; Plant Mixer; Post Driver;

Post Hole Digger (Power Auger); Power Brush Burner; Power Form Handling Equipment; Road Widening Trencher; Roller (Brick, Grade & Macadam); Self-Propelled Power Spreader;

Self-Propelled Power Subgrader; Steam Fireperson; Tractor (Pulling Sheepfoot, Roller or Grader); and Vibratory Compactor with Integral Power.

GROUP 5 - Compressor (Portable, Sewer, Heavy & Highway); Drum Fireperson (Asphalt Plant); Generator; Masonry Fork Lift;

Inboard-Outboard Motor Boat Launch; Oil Heater (asphalt plant); Oiler/Helper; Power Driven Heater; Power Sweeper & Scrubber; Pump (under 4" discharge); Signalperson; Tire Repairperson; VAC/ALLS; Cranes - Compact, track or rubber under 4,000 pound capacity; fueling and greasing; and Chainmen.

GROUP 6 - Master Mechanic & Boom from 150 to 180.

GROUP 7 - Boom from 180 and over.

ENGI0018-004 05/04/2011

ADAMS, ALLEN, ASHLAND, ATHENS, AUGLAIZE, BELMONT, BROWN,

BUTLER, CARROLL, CHAMPAIGN, CLARK, CLERMONT, CLINTON,

COSHOCTON, CRAWFORD, DARKE, DEFIANCE, DELAWARE, FAIRFIELD,

FAYETTE, FRANKLIN, FULTON, GALLIA, GREENE, GUERNSEY, HAMILTON,

HANCOCK, HARDIN, HARRISON, HENRY, HIGHLAND, HOCKING, HOLMES,

HURON, JACKSON, JEFFERSON, KNOX, LAWRENCE, LICKING, LOGAN,

LUCAS, MADISON, MARION, MEIGS, MERCER, MIAMI, MONROE,

MONTGOMERY, MORGAN, MORROW, MUSKINGUM, NOBLE, OTTAWA, PAULDING,

PERRY, PICKAWAY, PIKE, PREBLE, PUTNAM, RICHLAND, ROSS,

SANDUSKY, SCIOTO, SENECA, SHELBY, STARK, TUSCARAWAS, UNION, VAN

WERT, VINTON, WARREN, WASHINGTON, WAYNE, WILLIAMS, WOOD, and

YANDOT COUNTIES

OPERATOR: Power Equipment

GROUP 1.....................$ 29.99 12.80

GROUP 2.....................$ 29.87 12.80

GROUP 3.....................$ 28.83 12.80

GROUP 4.....................$ 27.65 12.80

GROUP 5.....................$ 22.19 12.80

GROUP 6.....................$ 30.24 12.80

GROUP 7.....................$ 30.49 12.80

OPERATING ENGINEER CLASSIFICATIONS

GROUP 1 - Air Compressor on Steel Erection; Barrier Moving Machine; Boiler Operator on Compressor or Generator when mounted on a Rig; Cableway; Combination Concrete Mixer & Tower; Concrete Plant (over 4 yd. Capacity); Concrete Pump;

Crane (All Types, Including Boom Truck, Cherry Picker);

Crane-Compact, Track or Rubber over 4,000 lbs. capacity;

Cranes-Self Erecting, Stationary, Track or Truck (All Configurations); Derrick; Dragline; Dredge (Dipper, Clam or Suction); Elevating Grader or Euclid Loader; Floating Equipment (All Types); Gradall; Helicopter Crew (Operator-Hoist or Winch); Hoe (all types); Hoisting Engine on Shaft or Tunnel Work; Hydraulic Gantry (Lifting System); Industrial-Type Tractor; Jet Engine Dryer (D8 or D9) Diesel Tractor; Locomotive (Standard Gauge);

Maintenance Operator Class A; Mixer, Paving (Single or Double Drum); Mucking Machine; Multiple Scraper;

Piledriving Machine (All Types); Power Shovel; Prentice Loader; Quad 9 (Double Pusher); Rail Tamper (with auto lifting & aligning device); Refrigerating Machine (Freezer Operation); Rotary Drill, on Caisson work; Rough Terrain Fork Lift with Winch/Hoist; Side-Boom; Slip-Form Paver;

Tower Derrick; Tree Shredder; Trench Machine (Over 24" wide); Truck Mounted Concrete Pump; Tug Boat; Tunnel Machine and/or Mining Machine; and Wheel Excavator.

GROUP 2 - Asphalt Paver; Automatic Subgrader Machine, Self-Propelled (CMI Type); Bobcat Type and/or Skid Steer Loader with Hoe Attachment Greater than 7,000 lbs.; Boring Machine More than 48"; Bulldozer; Endloader; Hydro Milling Machine; Horizontal Directional Drill (over 50,000 ft. lbs.

thrust);Kolman-type Loader (production type-Dirt); Lead Greaseman; Lighting & Traffic Signal Installation Equipment (includes all groups or classifications); Material Transfer Equipment (Shuttle Buggy) Asphalt; Pettibone-Rail Equipment; Power Grader; Power Scraper; Push Cat; Rotomill (all), Grinders & Planers of All types; Trench Machine (24" wide & under); and Vermeer type Concrete Saw.

GROUP 3 - A-Frame; Air Compressor on Tunnel Work (low pressure); Asphalt Plant Engineer; Bobcat-type and/or Skid Steer Loader with or without Attachments; Highway Drills (all types); Locomotive (narrow gauge); Material Hoist/Elevator; Mixer, Concrete (more than one bag capacity); Mixer, one bag capacity (Side Loader); Power Boiler (Over 15 lbs. Pressure) Pump Operator installing & operating Well Points; Pump (4" & over discharge); Railroad Tie Inserter/Remover; Roller, Asphalt; Rotovator (lime soil stabilizer); Switch & Tie Tampers (without lifting & aligning device); Utility Operator (Small equipment); and Welding Machines; Artiaculating/straight bed end dumps if assigned (minus $4.00 per hour.

GROUP 4 - Backfiller; Ballast Re-locator; Bars, Joint & Mesh Installing Machine; Batch Plant; Boring Machine Operator (48" or less); Bull Floats; Burlap & Curing Machine;

Concrete Plant (capacity 4 yd. & under); Concrete Saw (Multiple); Conveyor (Highway); Crusher; Deckhand;

Farm-type Tractor with attachments (highway); Finishing Machine; Fireperson, Floating Equipment (all types); Fork Lift; Form Trencher; Hydro Hammer expect masonary; Hydro Seeder; Pavement Breaker; Plant Mixer; Post Driver; Post Hole Digger (Power Auger); Power Brush Burner; Power Form Handling Equipment; Road Widening Trencher; Roller (Brick, Grade & Macadam); Self-Propelled Power Spreader;

Self-Propelled Power Subgrader; Steam Fireperson; Tractor (Pulling Sheepfoot, Roller or Grader); and Vibratory Compactor with Integral Power.

GROUP 5 - Compressor (Portable, Sewer, Heavy & Highway); Drum Fireperson (Asphalt Plant); Generator; Masonary Forklift;

Inboard-Outboard Motor Boat Launch; Oil Heater (asphalt plant); Oiler/Helper; Power Driven Heater; Power Sweeper & Scrubber; Pump (under 4" discharge); Signalperson; Tire Repairperson; VAC/ALLS; Cranes - Compact, track or rubber under 4,000 pound capacity; fueling and greasing; and Chainmen.

GROUP 6 - Master Mechanic & Boom from 150 to 180.

GROUP 7 - Boom from 180 and over.

ENGI0066-023 06/01/2011

COLUMBIANA, MAHONING & TRUMBULL COUNTIES

Rates Fringes

OPERATOR: Power Equipment

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 1 - A & B.............$ 35.93 15.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 2 - A & B.............$ 35.60 15.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 3 - A & B.............$ 32.27 15.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 4 - A & B.............$ 28.49 15.51

ASBESTOS; HAZARDOUS/TOXIC

WASTE PROJECTS

GROUP 5 - A & B.............$ 25.09 15.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 1 - C & D.............$ 32.93 15.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 2 - C & D.............$ 32.64 15.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 3 - C & D.............$ 29.58 15.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 4 - C & D.............$ 26.11 15.51

HAZARDOUS/TOXIC WASTE

PROJECTS

GROUP 5 - C & D.............$ 23.00 15.51

ALL OTHER WORK

GROUP 1.....................$ 29.94 15.51

ALL OTHER WORK

GROUP 2.....................$ 29.67 15.51

ALL OTHER WORK

GROUP 3.....................$ 26.89 15.51

ALL OTHER WORK

GROUP 4.....................$ 23.74 15.51

ALL OTHER WORK

GROUP 5.....................$ 20.91 15.51

GROUP 1 - Rig, Pile Driver or Caisson Type; & Rig, Pile Hydraulic Unit Attached

GROUP 2 - Asphalt Heater Planer; Backfiller with Drag Attachment; Backhoe; Backhoe with Shear attached; Backhoe-Rear Pivotal Swing; Batch Plant-Central Mix Concrete; Batch Plant, Portable concrete; Berm Builder-Automatic; Boat Derrick; Boat-Tug;

Boring Machine Attached to Tractor; Bullclam; Bulldozer;

C.M.I. Road Builder & Similar Type; Cable Placer & Layer;

Carrier-Straddle; Carryall-Scraper or Scoop; Chicago Boom;

Compactor with Blade Attached; Concrete Saw (Vermeer or similar type); Concrete Spreader Finisher; Combination, Bidwell Machine; Crane; Crane-Electric Overhead;

Crane-Rough Terrain; Crane-Side Boom; Crane-Truck;

Crane-Tower; Derrick-Boom; Derrick-Car; Digger-Wheel (Not trencher or road widener); Double Nine; Drag Line; Dredge;

Drill-Kenny or Similar Type; Easy Pour Median Barrier Machine (or similar type); Electromatic; Frankie Pile;

Gradall; Grader; Gurry; Self-Propelled; Heavy Equipment Robotics Operator/Mechanic; Hoist-Monorail;

Hoist-Stationary & Mobile Tractor; Hoist, 2 or 3 drum;

Horizontal Directional Drill Operator; Jackall; Jumbo Machine; Kocal & Kuhlman; Land-Seagoing Vehicle; Loader, Elevating; Loader, Front End; Loader, Skid Steer;

Locomotive; Mechanic/Welder; Metro Chip Harvester with Boom; Mucking Machine; Paver-Asphalt Finishing Machine;

Paver-Road Concrete; Paver-Slip Form (C.M.I. or similar);

Place Crete Machine with Boom; Post Driver (Carrier mounted); Power Driven Hydraulic Pump & Jack (When used in Slip Form or Lift Slab Construction); Pump Crete Machine;

Regulator-Ballast; Hydraulic Power Unit not attached to Rig for Pile Drillings; Rigs-Drilling; Roto Mill or similar Full Lane (8' Wide & Over); Roto Mill or similar type (Under 8'); Shovel; Slip Form Curb Machine; Speedwing;

Spikemaster; Stonecrusher; Tie Puller & Loader; Tie Tamper;

Tractor-Double Boom; Tractor with Attachments; Truck-Boom;

Truck-Tire; Trench Machine; Tunnel Machine (Mark 21 Java or similar); & Whirley (or similar type)

GROUP 3 - Asphalt Plant; Bending Machine (Pipeline or similar type); Boring machine, Motor Driven; Chip Harvester without Boom; Cleaning Machine, Pipeline Type; Coating Machine, Pipeline Type; Compactor; Concrete Belt Placer;

Concrete Finisher; Concrete Planer or Asphalt; Concrete Spreader; Elevator; Fork Lift (Home building only); Fork lift & Lulls; Fork Lift Walk Behind (Hoisting over 1 buck high); Form Line Machine; Grease Truck operator; Grout Pump; Gunnite Machine; Horizontal Directional Drill Locator; Single Drum Hoist with or without Tower; Huck Bolting Machine; Hydraulic Scaffold (Hoisting building materials); Paving Breaker (Self-propelled or Ridden);

Pipe Dream; Pot Fireperson (Power Agitated); Refrigeration Plant; Road Widener; Roller; Sasgen Derrick; Seeding Machine; Soil Stabilizer (Pump type); Spray Cure Machine, Self-Propelled; Straw Blower Machine; Sub-Grader; Tube Finisher or Broom C.M.I. or similar type; & Tugger Hoist

GROUP 4 - Air Curtain Destructor & Similar Type; Batch Plant-Job Related; Boiler Operator; Compressor; Conveyor;

Curb Builder, self-propelled; Drill Wagon; Generator Set;

Generator-Steam; Heater-Portable Power; Hydraulic Manipulator Crane; Jack-Hydraulic Power driven;

Jack-Hydraulic (Railroad); Ladavator; Minor Machine Operator; Mixer-Concrete; Mulching Machine; Pin Puller;

Power Broom; Pulverizer; Pump; Road Finishing Machine (Pull Type); Saw-Concrete-Self-Propelled (Highway Work); Signal Person; Spray Cure Machine-Motor Powered; Stump Cutter;

Tractor; Trencher Form; Water Blaster; Steam Jenny;

Syphon; Vibrator-Gasoline; & Welding Machine

GROUP 5 - Brakeperson; Fireperson; & Oiler

IRON0017-002 05/01/2011

ASHTABULA (North of Route 6, starting at the Geauga County Line, proceeding east to State Route 45), CUYAHOGA, ERIE (Eastern 2/3), GEAUGA, HURON (East of a line drawn from the north border through Monroeville & Willard), LAKE, LORAIN, MEDINA (North of Old Rte. #224), PORTAGE (West of a line from Middlefield to Shalersville to Deerfield), and SUMMIT (North of Old Rte. #224, including city limits of Barberton) COUNTIES

IRONWORKER

Ornamental, Reinforcing, & Structural..................$ 30.40 17.90

IRON0017-010 05/01/2011

ASHTABULA (Eastern part from Lake Erie on the north to route #322 on the south to include Conneaut, Kingsville, Sheffield, Denmark, Dorset, Cherry Valley, Wayne, Monroe, Pierpont, Richmond, Andover & Williamsfield Townships)

Structural, including metal building erection.....$ 28.35 17.83 Structural,iexcluding metal building erection & Reinforcing.................$ 30.40 17.90

IRON0044-002 06/01/2009

CLINTON (South of a line drawn from Blanchester to Lynchburg), HAMILTON, HIGHLAND (Excluding eastern one-fifth & portion of county inside lines drawn from Marshall to Lynchburg from the northern county line through E. Monroe to Marshall) & WARREN (South of a line drawn from Blanchester through Morrow to the west county line)

Fence Erector...............$ 23.55 16.72 Ornamental; Structural......$ 26.17 16.72

IRON0055-003 07/01/2010

CRAWFORD (Area Between lines drawn from where Hwy #598 & #30 meet through N. Liberty to the northern border & from said Hwy junction point due west to the border), DEFIANCE (S. of a line drawn from where Rte. #66 meets the northern line through Independence to the eastern county border), ERIE (Western 1/3), FULTON, HANCOCK, HARDIN (North of a line drawn from Maysville to a point 4 miles south of the northern line on the eastern line), HENRY, HURON (West of a line drawn from the northern border through Monroeville & Willard), LUCAS, OTTAWA, PUTNAM (East of a line drawn from the northern border down through Miller City to where #696 meets the southern border), SANDUSKY, SENECA, WILLIAMS (East of a line drawn from Pioneer through Stryker to the southern border), WOOD & WYANDOT (North of Rte.

#30)

Fence Erector...............$ 19.10 17.66 Flat Road Mesh..............$ 20.75 18.00 Tunnels & Caissons Under Pressure....................$ 28.50 18.00 All Other Work..............$ 28.00 18.69

IRON0147-002 06/01/2010

ALLEN (Northern half), DEFIANCE (Northern part, excluding south of a line drawn from where Rte. #66 meets the northern line through Independence to the eastern county border), MERCER (Northern half), PAULDING, PUTNAM (Western part, excluding east of a line drawn from the northern border down through Miller City to where #696 meets the southern border), VAN WERT, and WILLIAMS (Western part, excluding east of a line drawn from Pioneer through Stryker to the southern border) COUNTIES

IRONWORKER.......................$ 24.47 17.57

IRON0172-002 06/01/2010

CHAMPAIGN (Eastern one-third), CLARK (Eastern one-fourth), COSHOCTON (West of a line beginning at the northwestern county line going through Walhonding & Tunnel Hill to the southern county line), CRAWFORD (South of Rte. #30), DELAWARE, FAIRFIELD, FAYETTE, FRANKLIN, HARDIN (Excluding a line drawn from Roundhead to Maysville), HIGHLAND (Eastern one-fifth), HOCKING, JACKSON (Northern half), KNOX, LICKING, LOGAN (Eastern one-third), MADISON, MARION, MORROW, MUSKINGUM (West of a line starting at Adams Mill going to Adamsville & going from Adamsville through Blue Rock to the southern border), PERRY, PICKAWAY, PIKE (Northern half), ROSS, UNION, VINTON and WYANDOT (South of Rte. #30) COUNTIES

IRONWORKER.......................$ 26.52 16.48

IRON0207-004 06/01/2011

ASHTABULA (Southern part starting at the Geauga County line), COLUMBIANA (E. of a line from Damascus to Highlandtown), MAHONING (N. of Old Route #224), PORTAGE (E. of a line from Middlefield to Shalersville to Deerfield) & TRUMBULL

Layout; Sheeter.............$ 28.06 18.46 Ornamental; Reinforcing;

Structural..................$ 27.06 18.46

IRON0290-002 10/01/2010

ALLEN (Southern half), AUGLAIZE, BUTLER (North of a line drawn from east to the west county line going through Oxford, Darrtown & Woodsdale), CHAMPAIGN (Excluding east of a line drawn from Catawla to the point where #68 intersects the northern county line), CLARK (Western two-thirds), CLINTON (Excluding south of a line drawn from Blanchester to Lynchburg), DARKE, GREENE, HIGHLAND (Inside lines drawn from Marshall to Lynchburg & from the northern county line through East Monroe to Marshall), LOGAN (West of a line drawn from West Liberty to where the northern county line meets the western county line of Hardin), MERCER (Southern half), MIAMI, MONTGOMERY, PREBLE, SHELBY & WARREN (Excluding south of a line drawn from Blanchester through Morrow to the western county line) COUNTIES

Beyond 25 mile radius of L.U. #290 Office, Dayton....$ 25.78 17.55 Within 25 mile radius of L.U. #290 Office, Dayton....$ 25.63 17.55

* IRON0372-002 06/26/2011

ADAMS (Western Part), BROWN, BUTLER (Southern Part), CLERMONT, CLINTON (South of a line drawn from Blanchester to Lynchburg), HAMILTON, HIGHLAND (Excluding eastern one-fifth & portion of county inside lines drawn from Marshall to Lynchburg from the northern county line through E. Monroe to Marshall) and WARREN (South of a line drawn from Blanchester through Morrow to the west county line) COUNTIES

IRONWORKER, REINFORCING

Beyond 30-mile radius of Hamilton County Courthouse..$ 26.75 17.40 Up to & including 30-mile radius of Hamilton County Courthouse..................$ 26.50 17.40

IRON0549-003 12/01/2009

BELMONT, GUERNSEY, HARRISON, JEFFERSON, MONROE & MUSKINGUM

(Excluding portion west of a line starting at Adams Mill going to Adamsville and going from Adamsville through Blue Rock to the south border)

IRONWORKER.......................$ 29.75 15.69

IRON0550-004 05/01/2011

ASHLAND, CARROLL, COLUMBIANA (W. of a line from Damascus to Highlandtown), COSHOCTON (E. of a line beginning at NW Co. line going through Walhonding & Tunnel Hill to the South Co. line), HOLMES, HURON (S. of Old Rte. #224), MAHONING (S. of Old Rte.

#224), MEDINA (S. of Old Rte. #224), PORTAGE (S. of Old Rte.

#224), RICHLAND, STARK, SUMMIT (S. of Old Rte. #224, Excluding city limits of Barberton), TUSCARAWAS, & WAYNE

Ironworkers:Structural, Ornamental and Reinforcing.......$ 24.38 16.73

IRON0769-004 06/01/2011

ADAMS (Eastern Half), GALLIA, JACKSON (Southern Half), LAWRENCE

& SCIOTO

ZONE 1......................$ 30.96 18.07

ZONE 2......................$ 31.36 18.07

ZONE 3......................$ 32.96 18.07

ZONE 1 - Up to 10 mile radius of Union Hall, Ashland, Ky., 1643 Greenup Ave.

ZONE 2 - 10 to 50 mile radius of Union Hall, Ashland, Ky., 1643 Greenup Ave.

ZONE 3 - 50 mile radius & over of Union Hall, Ashland, Ky., 1643 Greenup Ave.

IRON0787-003 06/01/2010

ATHENS, MEIGS, MORGAN, NOBLE, and WASHINGTON COUNTIES

Rates Fringes

IRONWORKER.......................$ 29.67 17.05

LABO0265-008 05/01/2011

Rates Fringes

LABORER

ASHTABULA, ERIE, HURON,

LORAIN, LUCAS, MAHONING,

MEDINA, OTTAWA, PORTAGE,

SANDUSKY, STARK, SUMMIT,

TRUMBULL & WOOD COUNTIES

GROUP 1....................$ 26.25 8.75

GROUP 2....................$ 26.42 8.75

GROUP 3....................$ 26.75 8.75

GROUP 4....................$ 27.20 8.75

CUYAHOGA AND GEAUGA

COUNTIES ONLY: SEWAGE

PLANTS, WASTE PLANTS,

WATER TREATMENT

FACILITIES, PUMPING

STATIONS, & ETHANOL PLANTS

CONSTRUCTION................$ 28.86 8.75

CUYAHOGA, GEAUGA & LAKE

COUNTIES

GROUP 1....................$ 27.48 8.75

GROUP 2....................$ 27.65 8.75

GROUP 3....................$ 27.98 8.75

GROUP 4....................$ 28.43 8.75

REMAINING COUNTIES OF OHIO

GROUP 1....................$ 25.82 8.75

GROUP 2....................$ 25.99 8.75

GROUP 3....................$ 26.32 8.75

GROUP 4....................$ 26.77 8.75

LABORER CLASSIFICATIONS

GROUP 1 - Asphalt Laborer; Carpenter Tender; Concrete Curing Applicator; Dump Man (Batch Truck); Guardrail and Fence Installer; Joint Setter; Laborer (Construction); Landscape Laborer; Highway Lighting Worker; Signalization Worker;

Mesh Handlers & Placer; Right-of-way Laborer; Riprap Laborer & Grouter; Scaffold Erector; Seal Coating; Surface Treatment or Road Mix Laborer; Sign Installer; Slurry Seal;

Utility Man; Bridge Man; Handyman; Waterproofing Laborer;

Flagperson; Hazardous Waste (level D); Diver Tender; Zone Person & Traffic Control

GROUP 2 - Asphalt Raker; Concrete Puddler; Kettle Man Pipeline); Machine Driven Tools (Gas, Electric, Air); Mason Tender; Brick Paver; Mortar Mixer; Power Buggy or Power Wheelbarrow; Sheeting & Shoring Man; Surface Grinder Man;

Plastic Fusing Machine Operator; Pug Mill Operator; & Vacuum Devices (wet or dry); Rodding Machine Operator;

Diver; Screwman or Paver; Screed Person; Water Blast, Hand Held Wand; Pumps 4" & Under (Gas, Air or Electric) & Hazardous Waste (level C); Air Track and Wagon Drill;

Bottom Person; Cofferdam (below 25 ft. deep); Concrete Saw Person; Cutting with Burning Torch; Form Setter; Hand Spiker (Railroad); Pipelayer; Tunnel Laborer (without air) & Caisson; Underground Person (working in Sewer and Waterline, Cleaning, Repairing & Reconditioning);

Sandblaster Nozzle Person; & Hazardous Waste (level B)

GROUP 3 - Blaster; Mucker; Powder Person; Top Lander;

Wrencher (Mechanical Joints & Utility Pipeline); Yarner;

Hazardous Waste (level A); Concrete Specialist; Concrete Crew in Tunnels (With Air-pressurized - $1.00 premium);

Curb Setter & Cutter; Grade Checker; Utility Pipeline Tapper; Waterline; and Caulker

GROUP 4 - Miner (With Air-pressurized - $1.00 premium); & Gunite Nozzle Person

TUNNEL LABORER WITH AIR-PRESSURIZED ADD $1.00 TO BASE RATE

SIGNAL PERSON WILL RECEIVE THE RATE EQUAL TO THE RATE PAID

THE LABORER CLASSIFICATION FOR WHICH HE OR SHE IS SIGNALING.

PAIN0006-002 05/01/2008

ASHTABULA, CUYAHOGA, GEAUGA, LAKE, LORAIN, PORTAGE (N. of the East-West Turnpike) & SUMMIT (N. of the East-West Turnpike)

PAINTER

COMMERCIAL NEW WORK;

REMODELING; & RENOVATIONS

GROUP 1....................$ 26.59 10.17

GROUP 2....................$ 26.99 10.17

GROUP 3....................$ 27.29 10.17

GROUP 4....................$ 28.29 10.17

COMMERCIAL REPAINT

GROUP 1....................$ 25.09 10.17

GROUP 2....................$ 25.49 10.17

GROUP 3....................$ 25.79 10.17

PAINTER CLASSIFICATIONS - COMMERCIAL NEW WORK; REMODELING; &

RENOVATIONS

GROUP 1 - Brush; & Roller

GROUP 2 - Sandblasting & Buffing

GROUP 3 - Spray Painting; Closed Steel Above 55 feet; Bridges & Open Structural Steel; Tanks - Water Towers; Bridge Painters; Bridge Riggers; Containment Builders

GROUP 4 - Bridge Blaster

PAINTER CLASSIFICATIONS - COMMERCIAL REPAINT

GROUP 1 - Brush; & Roller

GROUP 2 - Sandblasting & Buffing

GROUP 3 - Spray Painting

PAIN0007-002 07/01/2010

FULTON, HENRY, LUCAS, OTTAWA (Excluding Allen, Bay, Bono, Catawba Island, Clay Center, Curtice, Danbury, Eagle Beach, Elliston, Elmore, Erie, Fishback, Gem Beach & Genova) & WOOD

NEW COMMERCIAL WORK

GROUP 1....................$ 22.77 14.31

GROUP 2....................$ 23.02 14.31

GROUP 3....................$ 23.27 14.31

GROUP 4....................$ 23.37 14.31

GROUP 5....................$ 23.40 14.31

GROUP 6....................$ 23.52 14.31

GROUP 7....................$ 23.77 14.31

GROUP 8....................$ 24.52 14.31

GROUP 9....................$ 24.81 13.22

REPAINT IS 90% OF JR

PAINTER CLASSIFICATIONS

GROUP 1 - Brush; Spray & Sandblasting Pot Tender

GROUP 2 - Refineries & Refinery Tanks; Surfaces 30 ft. or over where material is applied to or labor performed on above ground level (exterior), floor level (interior)

GROUP 3 - Swing Stage & Chair

GROUP 4 - Lead Abatement

GROUP 5 - All Methods of Spray

GROUP 6 - Solvent-Based Catalized Epoxy Materials of 2 or More Component Materials, to include Solvent-Based Conversion Varnish (excluding water based)

GROUP 7 - Spray Solvent Based Material; Sand & Abrasive Blasting

GROUP 8 - Towers; Tanks; Bridges; Stacks Over 30 Feet

GROUP 9 - Epoxy Spray (excluding water based)

PAIN0012-008 06/01/2010

BUTLER COUNTY

Rates Fringes

PAINTER

GROUP 1.....................$ 20.27 8.10

GROUP 2.....................$ 22.85 8.10

GROUP 3.....................$ 23.25 8.10

GROUP 4.....................$ 23.60 8.10

GROUP 5.....................$ 23.85 8.10

PAINTER CLASSIFICATIONS

GROUP 1: Bridge Equipment Tender; Bridge/Containment Builder

GROUP 2: Brush & Roller

GROUP 3: Spray

GROUP 4: Sandblasting; & Waterblasting

GROUP 5: Elevated Tanks; Steeplejack Work; Bridge; & Lead Abatement

PAIN0012-010 06/01/2010

BROWN, CLERMONT, CLINTON, HAMILTON & WARREN

Rates Fringes

PAINTER

HEAVY & HIGHWAY BRIDGES-

GUARDRAILS-LIGHTPOLES-

STRIPING

Bridge Equipment Tender and Containment Builder....$ 20.27 8.10 Bridges when highest point of clearance is 60 feet or more; & Lead Abatement Projects.........$ 23.85 8.10 Brush & Roller.............$ 22.85 8.10 Sandblasting & Hopper Tender; Water Blasting.....$ 23.60 8.10 Spray......................$ 23.35 8.10

PAIN0012-014 11/01/2010

DELAWARE, FAIRFIELD, FAYETTE, FRANKLIN, MADISON, PICKAWAY, ROSS

& UNION

Bridges.....................$ 33.35 9.37 Brush; Roller...............$ 23.87 9.37 Sandblasting;

Steamcleaning;

Waterblasting (3500 PSI or Over)& Hazardous Work.......$ 24.57 9.37 Spray.......................$ 24.37 9.37 Stacks; Tanks; & Towers.....$ 27.38 9.37 Structural Steel & Swing Stage.......................$ 24.17 9.37

PAIN0093-001 12/01/2010

ATHENS, GUERNSEY, HOCKING, MONROE, MORGAN, NOBLE and

WASHINGTON COUNTIES

Bridges; Locks; Dams;

Tension Towers; & Energized Substations.......$ 28.03 13.11 Power Generating Facilities.$ 24.88 13.11

PAIN0249-002 05/01/2010

CLARK, DARKE, GREENE, MIAMI, MONTGOMERY & PREBLE

Rates Fringes

PAINTER

GROUP 1 - Brush & Roller....$ 22.29 8.60 GROUP 2 - Swing, Scaffold Bridges; Structural Steel;

Open Acid Tank; High Tension Electrical Equipment; & Hot Pipes......$ 22.70 8.60 GROUP 3 - Spray;

Sandblast; Steamclean;

Lead Abatement..............$ 23.04 8.60 GROUP 4 - Steeplejack Work..$ 23.24 8.60 GROUP 5 - Coal Tar..........$ 23.79 8.60 GROUP 6 - Bridge Equipment Tender & or Containment Builder.....................$ 25.88 860 GROUP 7 - Tanks, Stacks & Towers......................$ 26.28 8.60 GROUP 8 - Bridge Blaster, Rigger......................$ 32.25 8.60

PAIN0356-002 09/01/2009

KNOX, LICKING, MUSKINGUM, and PERRY

Rates Fringes

PAINTER

Bridge Equipment Tenders and Containment Builders....$ 27.93 7.25 Bridges; Blasters;

andRiggers..................$ 34.60 7.25 Brush and Roller............$ 20.93 7.25 Sandblasting; Steam Cleaning; Waterblasting;

and Hazardous Work..........$ 25.82 7.25 Spray.......................$ 21.40 7.25 Structural Steel and Swing Stage.......................$ 25.42 7.25 Tanks; Stacks; and Towers...$ 28.63 7.25

PAIN0438-002 12/01/2010

BELMONT, HARRISON and JEFFERSON COUNTIES

Rates Fringes

PAINTER

Bridges, Locks, Dams, Tension Towers & Energized Substations.................$ 28.33 11.40 Power Generating Facilities.$ 25.18 11.40

PAIN0476-001 06/01/2010

COLUMBIANA, MAHONING, and TRUMBULL COUNITES

Rates Fringes

PAINTER

GROUP 1.....................$ 23.20 9.60

GROUP 2.....................$ 23.40 9.60

GROUP 3.....................$ 23.41 9.60

GROUP 4.....................$ 23.85 9.60

GROUP 5.....................$ 23.85 9.60

GROUP 6.....................$ 24.10 9.60

GROUP 7.....................$ 24.28 9.60

PAINTER CLASSIFICATIONS:

GROUP 1:…