ANSWERS TO CONTRACTOR QUESTIONS 26 FEB 2010.docx
DOCX document 11 KB Posted
- Solicitation number
- FA8601-10-R-0011
About this file
Answers to contractor questions 26 FEB 2010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| solicitation amendment 5.doc | DOC document | |
| Safety Health Plan Requirement.docx | DOCX document | |
| addendum.doc | DOC document | |
| ANSWERS TO CONTRACTOR QUESTIONS 3 MAR 2010.docx | DOCX document | |
| solicitation amendment 4.doc | DOC document | |
| Answers to contractor questions.docx | DOCX document | |
| solicitation amendment 3..doc | DOC document | |
| 08-0002A Renovate Facility for EOD REFLECTED CEILING PLAN.pdf | ||
| Site Visit Sign In.pdf | ||
| solicitation amendment 2.doc | DOC document | |
| solicitation amendment.doc | DOC document | |
| WD OH29.dot | DOT file | |
| SOLICIT.pdf | ||
| DRWGS.pdf | ||
| WD OH29.mht | MHT file | |
| SPECS.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESPONSES TO CONTRACTOR QUESTIONS
2/26/2010
1. Is there a proper bid form? Yes, the SF 1442 – READ SECTION L “INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS”.
2. Who is the alarm contractor? You would need to speak with APM, who is doing the sister project.
3. The sprinkler riser should be in a protected area, the garage area should be sprinklered under this phase. Who is installing the new fire alarm panel for APM? This question can be addressed after contract award with the fire safety engineer.