About this file

Site Visit Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY--PROJECT NUMBER ZHTV071983R, Replace Windows Administration Facility Building 20039, newest first.
File Type Posted
Addendum 1 Drawing.pdf PDF
Wage Decision 25Jun2010.pdf PDF
Addendum 1.pdf PDF
Amendment 2.pdf PDF
Site Visit Attendance and Rules.pdf PDF
Wage Decision June 2010.pdf PDF
Amendment 1.pdf PDF
Specifications.pdf PDF
Safety Health Plan Requirement —
Submittal Specifications.pdf PDF
ZHTV071983R Solicitation.pdf PDF
Wage.pdf PDF
Drawings.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA8601-10-B-0002

Replace Windows – South/East Side of Building 20039

Site Visit Questions

Q1. Note #10 E on our drawing mentions to re-point the brickwork on the SW Tower. The line drawing omits the SW Tower and only shows the NE Tower. Our Group was not shown the

SW Tower during the walk thru. Can we take a look at the SW Tower or can a picture be provided?

RESPONSE – This work was removed from the scope of work. No work is to occur on the SW tower. See revised sheet A-2 note 10 modified with addendum #1.

Q2. What factor is more relevant ie: AT/FP "or" Exact Match? Pertains to whether or not the previously installed windows meet current blast requirements despite past installation.

RESPONSE – The Exact Match applies to appearance only. Newly installed windows must meet AT/FP requirements in terms of performance. See revised sheet A-2 “Window Notes” modified with addendum 1.

Q3. Was load considered on Exact Match?

RESPONSE – The Exact Match applies to appearance only. Newly installed windows must meet AT/FP requirements in terms of performance. See revised sheet A-2 “Window Notes”

Q4. Requesting information on stand-off distance requirements for Administration Facility

Building 20039 window replacement. We need stand-off distance to calculate correct window configuration to meet loads imposed on window system.

RESPONSE– Use an 82 ft Stand-off distance. See revised sheet A-2 “Window Notes”

Q5. Is an Irrevocable Letter of Credit from a local bank for the contract amount enough to meet the surety requirements on this job?

RESPONSE- Must follow guidance provided in FAR 52.228-14 regarding a Letter of Credit.