C-17 BLOS MOD Scaffolding Solicitation QA revised 1.docx

DOCX document 171 KB Posted

Attached to
C-17 BLOS MOD Interior Work Stands Scaffolding Robins AFB Federal contract opportunity
Solicitation number
FA857126Q0025
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This document is a Questions and Answers (Q&A) file for a C-17 Scaffolding Solicitation. The solicitation, issued by the Department of the Air Force Materiel Command Air Force Sustainment Center under Solicitation Number FA857126Q0025, seeks the procurement of scaffolding materials and equipment for the 402d Aircraft Maintenance Group at Robins Air Force Base in Georgia. The Q&A clarifies key details about the solicitation, specifically confirming that the procurement is for scaffolding equipment only, with no equipment rental or erection/dismantle services required. The document indicates that the solicitation involves 8 sets of scaffolding, with the expectation that the total price will be the sum of the individual unit prices.

View the file

Other files for this federal contract opportunity

Other files attached to C-17 BLOS MOD Interior Work Stands Scaffolding Robins AFB, newest first.
File Type Posted
C-17 BLOS MOD Scaffolding Solicitation QA revised 2.pdf PDF
C-17 BLOS MOD Scaffolding Solicitation QA revised.docx DOCX document
C-17 BLOS MOD Scaffolding Solicitation QA.docx DOCX document
Purchase Description (PD) - Supply C-17 BLOS MOD Template - 26 Aug 25.pdf PDF
Solicitation - FA857126Q0025.pdf PDF
Layout Drawings C-17 Interior Mod Work Scaffolding.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C-17 Scaffolding Solicitation Q&A

1. Can the government confirm this solicitation is for the purchase of scaffolding equipment and no equipment rental or erection/dismantle is required?

Response: Confirmed: This effort is for scaffolding only.

2. Is this the example of 1 set of scaffolding or 8 set of scaffolding?

3. If we figure out the total price of the items (as in the material example breakdown) as X dollar, should we use unit price as X divided by 8 or X.

Response: The 8 each should add up to the total price.