This document is a set of Questions and Answers related to Solicitation FA853824Q0005 for the repair of the C-5 Tension Regulator. The solicitation is a Competitive, Total Small Business Set-Aside and requires offerors to be registered in the Joint Certification Program and approved to view Export Control in order to access the technical data package.

The key details are:

  • This is an LPTA (Lowest Price, Technically Acceptable) procurement, where price and source qualification documents will be evaluated concurrently.
  • Offerors deemed technically acceptable, even if not the lowest price, will be qualified/approved for future related solicitations.
  • Drawings are available in the data package, which can be accessed by registered and approved offerors via DoD Safe.
  • Responses are due by 5:00 PM EST on July 13, 2024.
  • The contracting agency is the Department of the Air Force Materiel Command Air Force Sustainment Center.

View the file

Other files for this federal contract opportunity

Other files attached to C-5 Tension Regulator, Repair, newest first.
File Type Posted
FA853824Q0005_AMEND-04.pdf PDF
RESOLICIT_AMEND-03 _ FA853824Q0005-0003.pdf PDF
AMEND-02 _ FA853824Q0005-0002.pdf PDF
AMEND-01 _ FA853824Q0005-0001 _ RFQ with Attachments.pdf PDF
SQS _ Added Separately for Convenience.pdf PDF
AMEND-01 _ FA853824Q0005-0001 _ Amended Attachments.pdf PDF
FA853824Q0005 _ RFQ with Attachments.pdf PDF
FA853824Q0005 _ Attachments.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8538-24-Q-0005

Questions & Answers

As of August 2, 2024:

1. Question:

If we understand the SQS requirements, we have to be an approved source before the award. Is this correct?

Answer:

No. The source approval documents will be submitted at the same time as the quote/proposal, and both will be evaluated at the same time.

- This is an LPTA - Lowest Price, Technically Acceptable o The Price and SQS requirement documents will be evaluated at the same time o The Lowest Price submission will be awarded, if also Technically Acceptable o If Technically Acceptable though not Lowest Price: The Offeror will be deemed a qualified/approved source for future solicitations related to this NSN, and solicitations for similar NSNs/Part Numbers

2. Question [Comment]:

There was an issue getting to the drawing

Answer:

Drawings are within the Data Package. To access the data package, Offerors must be registered with JCP, and a request sent to the Buyer and PCO for access to the data package – which will be sent via DoD Safe

- Full instructions and web links are found within the Solicitation’s front pages and Section L and M, within the Clauses and Provisions.