Q and A FA852422Q0002.pdf
PDF 244 KB Posted
- Solicitation number
- FA8524-22-Q-0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA852422Q0002_______0001.pdf | ||
| PWS_FA852422Q0002_Rev1.pdf | ||
| FA852422Q0002.pdf | ||
| CAVAF_Reporting_Requirements_Jan2021.pdf | ||
| CAVAF_DD_FORM_2875.pdf | ||
| GFPFA852422Q0002_7.pdf | ||
| Draft_ FA852422Q0002.pdf | ||
| CDRLS_FA852422Q0002.pdf | ||
| PWS_FA852422Q0002.pdf | ||
| TRNSPDATA_REPORT.pdf | ||
| PKGRQMT_REPORT.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8524-22-Q-0002 1
FA8524-22-Q-0002
Questions & Answers
05 April 5, 2022
1. Question: Will all 43 assets (DC Generators) be shipped at one time?
Answer: Yes the Government will ship all at one time (on split shipments of 5 ea.). However, the Government would be o.k. with an incremental delivery if the contractor wants to work them in that manner.