Question-Answer.pdf
PDF 58 KB Posted
- Attached to
- HARM Engineering Services Federal contract opportunity
- Solicitation number
- FA8520-23-R0004
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8520-23-R-0004-0001.pdf | ||
| Solicitation - FA852023R0004 - Questions with Answers.pdf | ||
| HARM Evaluation Spreadsheet - 13 Jun 2023.xlsx | XLSX spreadsheet | |
| DD-Form-254.pdf | ||
| FA8520-23-R-0004.pdf | ||
| FD2060-23-30022 CDRL_A003.pdf | ||
| Continuation Sheet DD254.pdf | ||
| FD2060-23-30022 CDRL_A002.pdf | ||
| PWS.pdf | ||
| FD2060-23-30022 CDRL_A001.pdf | ||
| FD2060-23-30022 CDRL_A004.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question:
The DD254 has Block 1B marked Top Secret. It's our assumption that all Classified work will be completed at a USG on-site facility. If this is an accurate assumption, then request 1b needs to be unchecked. Conversely, if any Classified work is to be done at a contractor location, sub or prime, then safeguarding needs to be checked and the address listed in block 8 of the DD254. Block 11a would then be unchecked and 11b or 11c would be checked. Can you clarify the DD254 requirements?
Answer:
If all work will be on base then 1 b will be None and 11a is checked.
Adjust 1b and 11a/b/c as appropriate based on the PWS.