First_Article_Requirements.pdf

PDF 82 KB Posted

Attached to
AC-130J 105mm Ammunition Rack Production Kit Federal contract opportunity
Solicitation number
FA850919R0007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Robins Air Force Base

About this file

First Article Requirements

View the file

Other files for this federal contract opportunity

Other files attached to AC-130J 105mm Ammunition Rack Production Kit, newest first.
File Type Posted
RFP_Questions.docx DOCX document
FA8509-19-R-0007-0002.pdf PDF
FA8509-19-R-0007-0001.pdf PDF
Packaging_Requirement.pdf PDF
Section_L_-_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
Statement_of_Work_(SOW).docx DOCX document
Transportation_Requirement.doc DOC document
FA8509-19-R-0007_rev_1.pdf PDF
Contract_Data_Requirements_Listing_A001_-_A006.pdf PDF
L-XXX_COST_PROPOSAL_ADEQUACY_AND_STRUCTURE.docx DOCX document
Section_M_-_Evaluation_Factors_for_Award.pdf PDF
AC-130J_105mm_Ammunition_Rack_RFI.doc DOC document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Please wait...

If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.

You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.

For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.

Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

1. DATE

FIRST ARTICLE REQUIREMENTS

(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3) (Additional Instructions on Page 3)

2. P/R/MIPR NUMBER

3. PART NUMBER

4. NSN

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS

UNIT(S) OF LOT/ITEM

AND WILL BE:

PART OF PRODUCTION QUANTITY

IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

7. LONG LEAD TIME ITEMS

SERVE AS A MANUFACTURING

STANDARD

REQUIRED

NOT REQUIRED

WILL

WILL NOT

(See FAR 52.209-3 or -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 or -4 Alternate I)

REQUIRED

NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST/INSPECTION REQUIREMENTS

F. FIRST ARTICLE DELIVERY:

A.

CONTRACTOR TESTING

GOVERNMENT TESTING

(1) Due within calendar days from date contract.

Performance or other characteristics which the First Articles must meet

(2) Notify calendar days prior to shipment.

are

(3) Delivered to government at B.

The detailed technical requirements for First Article approval tests are contained in (Set Forth Consignee and Address) (Cite Spec and Para number) Government written notice of approval/disapproval within days after receipt of first article package.

(4) C.

TEST PLAN REQUIRED

(1) DD Form 1423 ELIN

(2) Delivery due calendar days from date of contract.

G. Estimated cost of government testing/inspection evaluation.

(3) Number of days for government approval/disapproval days.

D. Contractor's notification to ACO and (Requesting Activity) of test time and location due days prior to start of testing.

E.

TEST REPORT REQUIRED

(1) DD Form 1423 ELIN

(2) Due calendar days from date of contract.

(3) Forwarded to

(4) Government written notice of approval/disapproval due days after receipt of contractor's report.

Disapproved First Articles will be returned to the contractor/

10. DISPOSITION OF FIRST ARTICLES

will be retained by pending Approved First Articles will be forwarded to disposition instructions from the contractor On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

(insert quantity).FirstArticles will be expended intesting.

will be Residual components of dispproved FirstArticles will be retained by returned to the contractor/

a. Approved First Articles will be returned to the contractor for shipment with production item.

pending disposition instructions from the contractor.

b. Disposition of disapproved First Articles will remain the same as marked above.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Other Disposition:

V-3

PREVIOUS EDITION IS OBSOLETE

AFMC IMT 260, 20020830,

2. P/R/MIPR NUMBER

3. PART NUMBER

4. NSN

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the a.

Government, DoD, Air Force.

Offerors currently in production of the same or similar article for a received First Article approval under the existing contract.

Air Force contract and who have Government, DoD, b.

Government, DoD, Offerors who have previously furnished production quantities of the same or similar articles to the c.

Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d.

Provided not more than months have elapsed since completion of the contract.

First Article testing will not be waived.

e.

See Remarks in block 12 below.

f.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

B. CONTRACT NUMBER

C. DATE OF CONTRACT

D. SPECIFICATION NUMBER AND REVISION

A. PROCURING OFFICE

12. REMARKS

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

AND/OR APPROVING TEST (Name, Organization, Phone)

14. PR INITIATOR (Name, Organization, Phone) AFMC IMT 260, 20020830,Reverse

INSTRUCTIONS FOR COMPLETION OF FIRST ARTICLE TEST REQUIREMENTS

(AFMC Form 260)

BLOCKS 1 - 4 AND 14. WILL BE COMPLETED BY THE INITIATOR OF PURCHASE REQUEST.

BLOCKS 5 THRU 11, AND 13. WILL BE COMPLETED BY THE ENGINEER AND/OR EQUIPMENT SPECIALIST. IF LOCAL PURCHASE, INITIATOR OF PURCHASE REQUEST SHALL COMPLETE.

BLOCKS 1 THRU 4. SELF-EXPLANATORY

BLOCK 6. INDICATE WHETHER OR NOT THE FIRST ARTICLE WILL SERVE AS A MANUFACTURING STANDARD. ( FAR 9.306(h)).

BLOCK 7. SEE FAR 52.209-3 OR -4, ALTERNATE II.

BLOCK 8. SEE FAR 9.308

BLOCK 9. MUST BE CHECKED TO INDICATE WHETHER THE CONTRACTOR OR THE GOVERNMENT IS TO PERFORM TESTING. (FAR 9.306) A. THE SPECIFIC PARAGRAPH(S) OF THE SPECIFICATION MUST BE INCLUDED OR THE PARTICULAR REQUIREMENTS CITED.

B. THE SPECIFIC PARAGRAPH(S) OF THE SPECIFICATION MUST BE INCLUDED OR THE PARTICULAR REQUIREMENTS CITED.

C. THIS PARAGRAPH IS OPTIONAL AND IS REQUIRED ONLY WHEN A TEST PLAN IS REQUIRED. THE REQUIRED ENTRIES ARE SELF-EXPLANATORY.

D. THE "NUMBER OF DAYS" ENTRY SHOULD BE FAR ENOUGH IN ADVANCE OF THE TESTING TO PERMIT ANY

GOVERNMENT REPRESENTATION AT THE TESTING SITE.

F. (1). THE DELIVERY DATE MUST BE REALISTIC AND INCLUDE ADEQUATE PRODUCTION AND ADMINISTRATIVE LEAD TIMES.

(2). THIS NOTIFICATION SHOULD BE NO LESS THAN TEN DAYS.

(3). ENTER ADDRESS WHERE FIRST ARTICLE IS TO BE DELIVERED FOR TESTING.

(4). THIRTY DAYS OR LONGER NOTIFICATION MUST BE CONSIDERED WHEN GOVERNMENT TESTING REQUIRES SPECIAL FIXTURE AND/OR AIRCRAFT.

BLOCK 11. SELF-EXPLANATORY. SIMILAR ARTICLES ARE THOSE WHICH, FOR PURPOSE OF MANUFACTURE, ARE SUBSTANTIALLY THE SAME AS THE ITEM BEING PURCHASED (For example, items that differ only in size or in place of operation (i.e., left vs right side of aircraft)).

G. THIS ESTIMATE SHOULD BE AS ACCURATE AS POSSIBLE AND INCLUDE GOVERNMENT LABOR COSTS FOR TESTS;

TOOLS/TEST EQUIPMENT; GOVERNMENT TEST FACILITY USE; TDY COSTS, TRANSPORTATION OF FIRST ARTICLE TO TEST

SITE; GOVERNMENT EVALUATION OF CONTRACTOR TEST REPORT; ETC.

BLOCK 10. APPLIES TO GOVERNMENT TESTING. APPLIES TO CONTRACTOR TEST ONLY IF ITEMS ARE NOT SUBMITTED AS PRODUCTION UNITS, IN THESE CASES CITE DISPOSITION.

E. THIS PARAGRAPH IS SELF-EXPLANATORY. (NOTE: All dates must be realistic and include adequate production and administrative lead times.)

BLOCK 5. INSERT QUANTITY OF FIRST ARTICLE TO BE TESTED. INDICATE WHETHER THE FIRST ARTICLE ITEM IS PART OF OR IN ADDITION TO THE PRODUCTION QUANTITY. (Normally the First Article in "Contractor Testing" are delivered (if not destroyed) with the production items.) PER FAR 9.301 FIRST ARTICLE MEANS PREPRODUCTION MODELS/SAMPLES, INITIAL PRODUCTION SAMPLES, TEST SAMPLES, FIRST LOTS, PILOT MODELS OR PILOT LOTS.

BLOCK 12. SELF-EXPLANATORY.

BLOCK 13 AND 14. SELF-EXPLANATORY.

AFMC IMT 260, 20020830,

8.2.1.3158.1.475346.466429

partA: 1
Prdct: 0
will: 1
wilnot: 0
Reqir: 0
not: 2
B: 1
C: 0
Cntrc: 0
Govmt: 2
dsaprov: 0
retainC: 2
rtain: 2
rtrn: 0
dspo:
FIELD1:
dlvrB: DLA Central Receiving DDWG ER. Special Handling, First Article Unit. 455 Byron St, Robins AFB GA 31098

Mark For:First Article, Do Not Post

insertA: 0
prchs: 0
firstB: 1
other: 0
approv: 0
test: 0
Testc: 0
show date as yyyymmdd (e.g. 20000101): 2019-04-03
MIPR: 19-32450
PART: 3C4823-30
NSN: NSL
Use numbers only: 1
item: EA
dueD: 180
performA: Dimensions, NDI, Composition, Hardness, Finish
notify: 30
detail: drawing 3C4823 and subsequent drawings.
daysE: 120
elin:
dlvr:
approvA:
cost: 37996.00
aco:
dueC:
elinB:
DueE:
DueF:
FirstA: supply
retainB: WR-ALC
insert: 1
rtainA: WR-ALC
AFb: 1
dodC: 1
govtC: 0
dodB: 1
govtB: 0
DODa: 1
AFa: 1
govA: 0
AFc: 1
offer: 1
offerA: 1
Offrs: 1
mon: 1
testB: 0
See: 0
months: 48
procr: AFLCMC/WIUAA
NUMBER:
show date as yyyymmdd (e.g. 20000101):
spec:
REMARKS:
cog: Randall S. Cliett, AFLCMC/WIUEB, 478-327-3680
PR:
MIPR_2: 19-32450
PART_2: 3C4823-30
NSN_2: NSL

File details come from the government source that posted it.