SLEP_Production_Questions_from_Industry_2.pdf

PDF 99 KB Posted

Attached to
F-16 Service Life Extension Program (SLEP) Production Federal contract opportunity
Solicitation number
FA8232-18-R-0001
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Q/A Updated Doc

View the file

Other files for this federal contract opportunity

Other files attached to F-16 Service Life Extension Program (SLEP) Production, newest first.
File Type Posted
SLEP_Pricing_Attachment_version_4.xlsx XLSX spreadsheet
SLEP_Pricing_Attachment_version_3.xlsx XLSX spreadsheet
PPI_Attachment.accdb.docx DOCX document
Section_M_F_16_SLEP_Mod_Kit_v2.pdf PDF
SOW_F_16_SLEP_Mod_Kit_v2.pdf PDF
Section_L_F_16_SLEP_Mod_Kit_v2.pdf PDF
SLEP_Pricing_Attachment_version_2.xlsx XLSX spreadsheet
Government_Furnished_Equipment_List_v2.pdf PDF
SLEP_Kit_Estimated_Quantities.xlsx XLSX spreadsheet
MK5420C_Attachment_A.PDF PDF
Solicitation_Traceability_Matrix.xlsx XLSX spreadsheet
SLEP_Production_Questions_from_Industry_1.docx DOCX document
MK5420D_Attachment_A.PDF PDF
SLEP_Pricing_Attachment.xlsx XLSX spreadsheet
Government_Furnished_Equipment_List_EDA.PDF PDF
FA823218R0001.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions after 12/04/2017

Q: Could you provide a yearly kit quantity buy estimate after the first year? It is hard to acquire supplier quantity breaks without an estimate. We also need this information to properly estimate labor per year.

A: Attached…the estimated amounts are estimates for planning purpose only and are in no way to be considered a guarantee. Orders will be placed on the IDIQ as quantities are required and funded.

Q: When will the PPI tool be on the FBO site?

A: Attached

Q: On the Option tab, the Unit Price for Option Period 1 (FY23) is set to equal the Unit Price for Basic ordering Period 2 (FY19). Should it be set to equal Basic Ordering Period 6 (FY23)?

A: Attached update pricing sheet v2

Q: On the Option tab, there is an extra row (row 197) between CLINs 1012 and 1013, which shifts the Formula set for the Option Period 1 (FY23) prices down by 1 cell. For example, Option tab row 200 is set to equal Basic tab row 200, but it should be set to equal Basic tab row 199 since there’s an extra row on the Option tab.

A: Attached update pricing sheet v2

Updated:

Updates were made to the document dates and GFM portions of these documents. The Government will be providing 5 rolled plates of AlLi.

Section_L_F_16_SLEP_Mod_Kit_v2 Section_M_F_16_SLEP_Mod_Kit_v2 Government_Furnished_Equipment_List_v2 SOW_F_16_SLEP_Mod_Kit_v2

All future updated documents will contain a change page to specify the area that was changed.