Q&A_-_16_Oct_19.docx

DOCX document 12 KB Posted

Attached to
ATSSI II Services Federal contract opportunity
Solicitation number
FA8224-19-RFI-ATSSI(II)
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

About this file

This document provides information regarding a follow-on Automated Test System Sustainment Initiative (ATSSI II) contract opportunity. The Department of the Air Force Materiel Command Air Force Sustainment Center is seeking potential sources to support a follow-on contract for its ATSSI program at Hill Air Force Base. Under ATSSI II, the contractor shall serve as a complete automated test system integrator and support design, manufacturing, validation, delivery, installation, documentation updates, software, hardware, OEM coordination, and other requirements. A draft performance work statement and additional information will be posted at a later date, with responses to capability questions due by the specified individuals. The anticipated period of performance is a 5-year IDIQ contract, with the RFP estimated for release in Spring 2020. The incumbent contractor is CACI, Inc. under the previous ATSSI I contract.

View the file

Other files for this federal contract opportunity

Other files attached to ATSSI II Services, newest first.
File Type Posted
Industry Day Attendees List.pdf PDF
Industry Day Sign-In Sheet - 30 Oct 19_Redacted.pdf PDF
ATSSI_II_Industry_Day_QandAs.pdf PDF
ATSSI_II_Industry_Day_Charts_Final.ppt PPT presentation
Industry_Day_Itinerary_Final.doc DOC document
South_Gate_to_Bldg_849.pptx PPTX presentation
ATSSI_2_Draft_PWS_Rev_11Sep19.docx DOCX document
ATSSI_II_Sources_Sought__RFI_Questions.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATSSI II - Q&A

October 16, 2019

Q1: Does contracting have a set-aside and contract vehicle in mind?

A1: All though we are still in the market research phase for this follow-on contract, we do not anticipate this effort to be set-aside.

Q2: Additionally, is there a rough timeline for when an RFP would be realsed (if any)?

A2: We anticipate a 5 year IDIQ and currently are estimating RFP release in the Spring of 2020.

Q3: Is there an incumbent?

A3: ATSSI I was awarded to CACI, Inc.