Section M - Evaluation Factors for Award
SECTION M
TYQ-23A Contractor Logistics Support
EVALUATION FACTORS FOR AWARD USING LOWEST PRICE TECHNICALLY
ACCEPTABLE (LPTA) PROCEDURES
1.0 SOURCE SELECTION
1.1 Basis for Contract Award
This acquisition will utilize Lowest Price Technically Acceptable (LPTA) source selection procedures in accordance with FAR 15.101-2. Technical tradeoffs will not be made and no additional credit will be given for exceeding acceptability. Award will be made to the technically acceptable Offeror with the lowest evaluated cost or price, which is deemed responsible in accordance with the Federal Acquisition Regulation and whose proposal conforms to the solicitation requirements. The solicitation requirements include all stated terms, conditions, representations, certifications, and all other information required by Section L of this solicitation.
The Government reserves the right to award without discussions. Therefore, each initial offer should contain the Offeror’s best terms from a price and technical standpoint. However, the
Government reserves the right to conduct discussions if determined necessary by the Source
Selection Authority (SSA).
1.2 Number of Contracts to be Awarded
The Government intends to award one (1) contract for this effort. However, the Government reserves the right not to award a contract at all, depending on the quality of the proposals and prices submitted and the availability of funds.
1.3 Correction Potential of Proposals
The Government may consider, throughout the evaluation, the "correction potential" of any deficiency or ambiguity. The judgment of such "correction potential" is within the sole discretion of the Government. If an aspect of an Offeror's proposal not meeting the Government's requirements is not considered correctable, the Offeror may be eliminated from the competitive range.
1.4 Competitive Advantage from Use of GFP
The Government will eliminate any competitive advantage resulting from an Offeror’s proposed use of Government- Furnished Property (GFP). All offerors will have the opportunity to review the same list of current GFP. This list will be the only GFP used during the evaluation.
1.5 Evaluation Methodology
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/15.htm#P25_3805
The two lowest priced offers will be evaluated for technical acceptability. If one of the offerors is found unacceptable the next lowest priced offer will be evaluated to establish competition. The
Government may continue to evaluate additional Offerors at their sole discretion. Higher priced
Offerors may not be evaluated.
The Government technical evaluation team will evaluate the technical volume on a pass/fail basis, assigning ratings of Acceptable or Unacceptable. Only those Offerors determined to be technically acceptable will be considered for award. The Government will evaluate proposals for price reasonableness, balance, realism (where identified) and total evaluated price (TEP).
Discussions may be held if determined to be in the best interest of the Government. Award will be made to the lowest evaluated priced proposal that is found to be technically acceptable.
2.0 Evaluation Factors and Sub-Factors
2.1. List Factors and Sub factors
The Government will evaluate for the following factors and sub factors described below:
Factor 1: Mission Capability
Sub factor 1: Technical Capabilities
Sub factor 2: Organization and Staff Management
Sub factor 3: Transition Plan
Sub factor 4: Technical Refresh
Sub factor 5: Program Protection
Factor 2: Cost and Price
Each sub factor within the Mission Capability factor will receive one of the technical ratings described below. Sub factor ratings shall not be rolled up into an overall rating for the Mission
Capability factor. An “Unacceptable” sub factor assessment will render the offer not awardable.
The following technical rating definitions will be used in the assessment of mission capability:
Rating Description
Acceptable Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.
Volume I – Executive Summary
If a subcontractor is being used, provide the same information for all subcontractors and certify that 50% of the effort will be accomplished using Prime Contractor employees.
Volume II - Technical
Factor 1: Mission Capability
Sub factor 1: Technical Capabilities
The Offeror’s technical approach successfully demonstrates the ability to meet the full range of requirements IAW PWS paragraph 4.1 – 4.2 & 4.9.5. The proposal demonstrates that the offeror is able to provide the skills and experience required to perform IAW PWS paragraph 4.1 – 4.2 &
4.9.5.
Facilities and Equipment: Proposed facilities, equipment, and/or any specialized facilities/equipment (such as test capabilities, access to unique interfaces (hardware and software), test stations, unique support equipment and/or mock-ups) demonstrate adequacy in meeting the full range of PWS requirements IAW PWS paragraph 4.1 – 4.2 & 4.9.5. Ability to track provided GFP/E in IAW PWS paragraph 2.
Sub factor 2: Organization and Staffing Management
The Offeror’s proposed management structure and plan for coordinating activities among the team members will be evaluated for the ability to accomplish tasks with minimal Government intervention while maintaining effective communication between the Government and the
Offeror.
The Offeror outlined processes for internal team communication and monitoring team performance, and accomplishing tasks in a timely manner. The organizational approach demonstrates clear lines of communication with a delegated authority identified, which allow for timely accomplishment of tasks and submission of deliverables, and prompt resolution of task issues and discrepancies (IAW PWS paragraph 4.3).
The Offeror’s proposal demonstrates an effective strategy to acquire expertise and methods to retain, maintain and train personnel. Having an established retention plan which addresses methods for assuring personnel remain versed on current and evolving technologies (IAW PWS section 4.3).
Sub factor 3: Transition Plan
The Transition Plan demonstrates, with rational, the methodology that will be utilized to meet all activities 60 days after contract award IAW PWS paragraph 4.13. Contractor acknowledges they shall provide necessary assistance in transferring all GFP/E/M at the end of the contract IAW
PWS paragraph 4.13.
Sub factor 4: Technical Refresh Plan
The Technical Refresh Plan demonstrates, with rational, the strategy associated with executing all activities IAW PWS paragraph 4.12.
Sub factor 5: Program Protection
This PP/SSE sub factor is acceptable when all of the following have been met by the offeror:
The offeror provides a comprehensive and executable Cybersecurity Strategy (to include Trusted
Systems and Networks per DODI 5200.44) that identifies strategy to obtain Cybersecurity and
Resiliency, documented in the Security Plan, Architecture, Security Assessment Plan and the
System Specification.
The offeror provides a Cyber Resiliency approach that describes the features incorporated into their design that ensures the system remains fully mission capable in a contested environment as documented in the PWS.
Integrated Master Plan (IMP): The offeror provides a comprehensive and executable IMP/
Integrated Program Management Report (IPMR) that fully documents the key events that will lead to successfully meeting the PP/SSE requirements in the PWS.
The offeror provides an anti-tamper plan that meets the requirements of DODI 5200.39 and
5200.47.
Information Protection compliance to the DD Form 254, Security Classification Guide.
Design Approach: The offeror provides a comprehensive and executable design approach that fully ensures that all PP/SSE requirements in the PWS are met.
Volume III – Price
General Instruction on Evaluating TEP.
All modifications and the first page of the RFP are signed and dated by an authorized representative of the company. All fill-ins are complete.
The TEP calculation for this acquisition will be established by adding together the fully loaded
CONUS labor rates in Section J Attached titled Contractor Labor Rate Matrix. The government will apply the pre-determined notional data for every year including the outlying years. When submitting the rates the Offeror shall assume these rates will be applied as pre-priced rates on the
IDIQ.
Refer to the [Instructions] tab when completing Section J attachment titled Contractor Labor
Rate Matrix. All offerors will be evaluated on the same basis and the Government will apply the offeror’s proposed amounts to the applicable multipliers in calculating the TEP. Details of this method and Government developed notional hours/quantities/labor mix will not be revealed to the offeror, but the method will be applied consistently and equally to each offer. All offers will be evaluated on the same basis.
2.3 Factor 2 – Price
The Government will evaluate the Offeror’s Price Volume for price reasonableness, balance, affordability, and realism (where identified). A Total Evaluated Price (TEP) will be evaluated and used for award purposes. Compliance with these requirements is mandatory and failure to comply may result in rejection of the offerors proposal. Offers shall be sufficiently detailed to demonstrate their acceptability in all of the above criteria. The burden of proof for credibility of proposed costs and prices rests with the offeror.
Evaluation Techniques and Methods– When responding to the Section J attachment Contractor
Labor Rate Matrix, all fill ins and labors hours must be completed. Any zeroed out columns will result in a non-responsive proposal. Do not add labor categories or change worksheet columns or rows. If practicable the Offeror may fill in their version on the corresponding labor categories for clarification during evaluation. The government will take one composite NTE rate per labor category per year and will apply to all members of the offeror's team (including the prime offeror, inter-divisions, and all subcontractors). No additional labor rate categories will be evaluated for award. This table shall be contractually binding for all fully burdened labor rates for all future contract actions and modifications affecting these items. Any deviations or modifications to this table will solely be at the government's discretion.
The TEP will consist of the Contractor’s firm-fixed and cost plus fixed fee fully-loaded labor hour rates submitted in the matrix, with profit/fee separately added (as appropriate) and multiplied by the government pre-determined generated notional data for all years including the outlaying year (FY27). Details of this method and Government developed notional hours/quantities/labor mix will not be revealed to the offeror, but the method will be applied consistently and equally to each offer. All offers will be evaluated on the same basis.
Once an Offeror’s price has been determined based on the CONUS rates submitted, section B will be filled out per CLIN, for all years by the United States Government. The total evaluated price will be calculated by adding the total amount of all total all CLIN totals for all years. Note:
This will include the CLINs for all years, including the option CLIN 0012 and outlying year
(FY27). The government will exclude CLIN X006, X007, and X008 from the TEP for evaluation purposes only.
Price Reasonableness – The Offeror’s price proposal will be evaluated for reasonableness using one or more of the techniques defined in FAR 15.404-1 (Proposal Analysis Techniques).
Generally, adequate price competition will satisfy the criteria of price reasonableness. The proposed rates in the Contract Labor Rate Matrix will be compared with the Independent
Government Cost Estimate (IGCE).
Travel and other direct costs shall be under a Cost Reimbursable – No Fee CLIN. The
Government will establish a ceiling price for this CLIN and shall verify that all travel is billed in accordance with Uniformed Travel Determination (UTD)/Civilian Travel Determination (CTD) -revised JTR 2017.
The total evaluated price will be calculated by adding the total amount of all fixed price contract line item numbers (CLINs). Note: This will include the labor CLINs for all years.
Balance – The Government will analyze proposals to determine whether they are unbalanced with respect to unit prices and variable quantity matrix factors in accordance with FAR 15.404-1.
An offer may be rejected if the CO determines that the lack of balance poses an unacceptable risk to the Government.
Realism – The Government will evaluate the realism of each offeror’s proposed costs for all Cost
Plus Fixed Fee (CPFF). All CPFF labor rates will be identical to FFP rates less profit/fee. The
Government expects this to satisfy the requirement for Realism. However if the Government determines it necessary, the Government will direct the Offeror to submit further Cost or Pricing
Data to support its rates after initial proposal submission.
Total Evaluated Price (TEP) – The Offeror’s Price proposal will be evaluated on the rates proposed in the Contract Labor Rate Matrix and based on a pre-determined notional data. The
TEP will utilize the Offeror’s labor rates proposed in the Contractor Labor Rate Matrix and multiplied by the corresponding notional data that was pre-determined by the Government. The notional hours/quantities/labor mix will not be disclosed to Offerors. For ease in numbering the below CLINs ‘X’ represents ‘0’ through ‘1’ as applicable for the base and all applicable option periods. It will be calculated as follows:
The Firm Fixed Price (FFP) CLINs (X001, X003, X005, X009) by utilizing proposed rates plus proposed profit multiplied by Government-determined notional data for all years of the contract.
The Cost Plus Fixed Fee CLIN (X002, X004, X010, X011,) by utilizing proposed rates plus proposed fee multiplied by Government-determined notional data for all years of the contract.
The Cost Reimbursable No Fee (CRNF) CLIN (X006, X007,) will not be included in the TEP. A cost shall be proposed within section B of the solicitation, but for purposes of the evaluation, the cost will be normalized to zero.
All Not Separately Priced (NSP) CLINs (X008,) are assumed to be included in the costs for other line items and so will not be separately included in the TEP.
Approval of Accounting System – As portions of this contract are other-than fixed price, the
Government will evaluate whether the offeror has a Government approved accounting system.
Failure to possess or obtain Government approval of the accounting system may result in disqualification from award. If the offeror does not currently have Government approval of its accounting system, it may be subject to a Pre-Award Accounting System Audit.
3.0 Source Selection Discussions
It is the Government’s intent to award without discussions; therefore, it is imperative that
Offerors submit their best terms initially. However, if, during the evaluation period, it is determined to be in the best interest of the Government to hold discussions, the Government will make a competitive range determination, and Offeror responses to Evaluation Notices (ENs) and the Final Proposal Revision (FPR) will be considered in making the source selection decision.
4.0 Solicitation Requirements, Terms and Conditions
In addition to meeting the identified factors and sub-factors, in order for Offerors to be rated acceptable they are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements specifically stated in Section L and
Section M to be eligible for contract award. Failure to comply with the terms and conditions of the complete solicitation may result in the Offeror being rated unacceptable and removed from consideration for award. Any exceptions to the solicitation’s terms and conditions must be fully explained and justified by the Offeror.