Price_Evaluation_Tool_ATTACK.pdf
PDF 58 KB Posted
- Attached to
- A-10 Thunderbolt Advanced-Wing Continuation Kitting (ATTACK) Federal contract opportunity
- Solicitation number
- FA8202-18-R-1001
About this file
This document contains a price evaluation tool for a federal contract opportunity to provide an A-10 Thunderbolt Advanced-Wing Continuation Kitting program. The price evaluation tool outlines unit pricing over a seven year period for quantities ranging from 1-50 units per year, with prices decreasing as quantities increase. It also includes estimated costs for a first article, three low rate initial production units, and five kits to be priced for the contract period. Based on an estimated maximum of 112 production units over seven years, the total estimated contract value is provided as $4,653,000. The related federal contract opportunity is a pre-solicitation notice posted by the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base to obtain an A-10 Thunderbolt Advanced-Wing Continuation Kitting program.
Price evaluation tool
View the file
Other files for this federal contract opportunity
Show all 50
A-10 Thunderbolt Advanced-Wing Continuation Kitting (ATTACK) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Evaluation Tool
QTY Range Unit Price
Basic YEAR I
1-5 $40.00
6-10 $38.00
11-15 $36.00
16-20 $34.00
21-25 $32.00
26-30 $30.00
31-35 $28.00
36-50 $26.00
Sub Total $264.00
Sub Total Divided by 8 = Avg Unit Cost Year 1 8 $33.00
Basic YEAR II
1-5 $42.00
6-10 $40.00
11-15 $38.00
16-20 $36.00
21-25 $34.00
26-30 $32.00
31-35 $30.00
36-50 $28.00
Sub Total $280.00
Sub Total Divided by 8 = Avg Unit Cost Year 2 8 $35.00
Basic YEAR III
1-5 $44.00
6-10 $42.00
11-15 $40.00
16-20 $38.00
21-25 $36.00
26-30 $34.00
31-35 $32.00
36-50 $30.00
Sub Total $296.00
Sub Total Divided by 8 = Avg Unit Cost Year 3 8 $37.00
Full Rate Production Units
1386553897C Draft
Basic YEAR IV
1-5 $46.00
6-10 $44.00
11-15 $42.00
16-20 $40.00
21-25 $38.00
26-30 $36.00
31-35 $34.00
36-50 $32.00
Sub Total $312.00
Sub Total Divided by 8 = Avg Unit Cost Year 4 8 $39.00
Basic YEAR V
1-5 $48.00
6-10 $46.00
11-15 $44.00
16-20 $42.00
21-25 $40.00
26-30 $38.00
31-35 $36.00
36-50 $34.00
Sub Total $328.00
Sub Total Divided by 8 = Avg Unit Cost Year 5 8 $41.00
Basic YEAR VI
1-5 $50.00
6-10 $48.00
11-15 $46.00
16-20 $44.00
21-25 $42.00
26-30 $40.00
31-35 $38.00
36-50 $36.00
Sub Total $344.00
Sub Total Divided by 8 = Avg Unit Cost Year 5 8 $43.00
Basic YEAR VII
1-5 $52.00
6-10 $50.00
11-15 $48.00
16-20 $46.00
21-25 $44.00
26-30 $42.00
31-35 $40.00
36-50 $38.00
Sub Total $360.00
Sub Total Divided by 8 = Avg Unit Cost Year 5 8 $45.00
YR I + YR II + YR III + YR IV + YR V + YR VI + YR
VII divided by 7 = Avg Unit Price for the 7 year ordering period $39.00
Maximum # of Production Units = units (This is the total # of units to be ordered over the 7 year ordering period not to include the F/A or 3
LRIP) 112 4,368.00$
Avg Unit Price x Maximum # of Units + F/A +
LRIP Units + Kits = Estimated Contract Value $4,653.00
First Article Cost for Example 1 $100.00
LRIP 1 Cost for Example 1 $50.00
LRIP 2 Cost for Example 1 $45.00
LRIP 3 Cost for Example 1 $40.00
Kits A - E to be priced assuming Kits can be ordered anytime within the ordering period of the contract:
Kit A 3 $10.00
Kit B 3 $10.00
Kit C 3 $10.00
Kit D 3 $10.00
Kit E 3 $10.00
*Numbers used in this example are not reflective of actual costs anticipated by the
Government
First Article and Low Rate Initial Production Units
KITS
File details come from the government source that posted it. Updated .