20160615_Site_Visit_QandA_FA8201-16-R-0006.pdf
PDF 183 KB Posted
- Attached to
- Roofing Repair IDIQ Federal contract opportunity
- Solicitation number
- FA8201-16-R-0006
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 20160630_Solicitation_Q-A.pdf | ||
| FA8201-16-R-0006_Amendment_0002.pdf | ||
| FA8201-16-R-0006_Amendment_0001.pdf | ||
| 04_Attachment_-_Statement_of_Work_(SOW)_-_Basic_April_26_2016.pdf | ||
| 02_Attachment_-_UT104_22_April_2016.pdf | ||
| 03_Attachment_-_UT110_22_April_2016.pdf | ||
| 06_Attachment_-_General_Requirements_April_26_2016.pdf | ||
| 01_Attachment_-_UT102_22_April_2016.pdf | ||
| 07_Attachment_-_SOW_-_Seed_Project_April_26_2016.pdf | ||
| Attachment_08_-_Total_Evaluation_Price_-_TEP.xlsx | XLSX spreadsheet | |
| FA8201-16-R-0006.pdf | ||
| 05_Attachment_05_-_LINE_ITEM_DESCRIPTIONS.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SITE VISIT Q&A
FA8201-16-R-0006, ROOFING IDIQ
15 June 2016, 9:30 AM MDT
Met at Hill Aerospace Museum parking lot. Nine interested parties were present. Site visit location was Seed Project work site, Bldg 2403.
1. Q: Who are the asbestos abatement companies?
A: Environmental Abatement and Eagle Abatement. Contact information is in the basic
SOW.
2. Q: Do we replace/repair duct work present on the roof?
A: No.
3. Q: Is there a curb requirement? Will we need to raise equipment present on roof (i.e.
ducts)?
A: Curb requirement is 8 inches. Will only raise equipment when it is possible. For example, fixed ducts will not be lifted, but fans will be.
4. Q: Is contractor responsible for re-certifying the lightning protection system?
A: Yes, reference the Seed Project SOW for additional information.
5. Q: Can interested parties submit alternative adhesives?
A: Interested parties may submit alternative adhesives and they will be considered;
however, no guarantee can be made alternative adhesives will be found to be technically acceptable. Review Sections L, M, and the base/seed SOWs for more information.
6. Q: Does Perlight need to be removed?
A: Not necessarily, this is up to the contractor.
7. Q: What is the material on the inside ceiling?
A: Tectum panels
8. Q: How many tectum panels are damaged and need to be replaced?
A: Approximately a dozen.