Questions_and_Answers_-_10_Jun_2014.pdf

PDF 98 KB Posted

Attached to
Hill AFB Basewide Fencing IDIQ Federal contract opportunity
Solicitation number
FA8201-14-R-0009
Issued by
Department of the Air Force Materiel Command Ogden Air Logistics Complex

View the file

Other files for this federal contract opportunity

Other files attached to Hill AFB Basewide Fencing IDIQ, newest first.
File Type Posted
Amendment_0005.pdf PDF
Fencing_Solicitation_-_FA8201-14-R-0009.doc.pdf PDF
Revised_Copy_of_Schedule_B_FY14-FY18.xlsx XLSX spreadsheet
FA8201-14-R-0009-02.doc DOC document
Schedule_B.xls XLS spreadsheet
FA8201-14-R-0009-0001.doc DOC document
SOW_Seed_Task.docx DOCX document
Schedule_B.xls XLS spreadsheet
UFGS_31_00_00_Earthwork.pdf PDF
UFGS_31_10_00_Clearing_for_Civil_Works.pdf PDF
UFGS_01_20_00.00_20_Price_and_Payment_Procedures.pdf PDF
UFGS_32_31_13.53_High-Security_Chain_Link_Fences_and_Gates.pdf PDF
UFGS_32-12-16HMA.pdf PDF
UFGS_12_93_00_Site_Furnishings_-_Bollards _Wood_Fence.pdf PDF
UFGS_01_11_00_Summary_of_Work.pdf PDF
Basic_SOW_23_Jul.pdf PDF
BASE_FACILITY_DESIGN_STANDARD.pdf PDF
ufc_1_300_02.pdf PDF
UFGS_01_62_35_Recycled_-_Recovered_Materials.pdf PDF
UFGS_32_31_13_Chain_Link_Fences_and_Gates.pdf PDF
UFGS_32_16_13_Concrete_Sidewalks _Curb _Gutter.pdf PDF
UFGS_28_20_01.00_10_Electronic_Security_System_-_Vindicator.pdf PDF
UFGS_32-13-13.06PCC.pdf PDF
UFGS_02_41_00_Demolition_and_Deconstruction.pdf PDF
Fencing_Solicitation_-_FA8201-14-R-0009.pdf PDF
MIL_HDBK_1013_10.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10 Jun 2014

Questions and Answers

Question: Line item T. We need a height to give accurate cost.

Answer: this should be line item R and has no height, just the depth stated in the specifications and required digging including hand digging around utilities and buildings. Fence height for each project is in fence line items, line items T through Y.

Question: Line item U. Need height.

Answer: this should be line item S and has no height, just the depth stated in the specifications depth and required saw cutting of concrete.

Question: Line items AI. - BG. We need heights, all we have is widths.

Answer: these should be line items AG through AZ and have standard height of 7 feet tall.

Question: The primary solicitation Section II 2.11.12 VPL Gates references "300" CHAINLINK style. What is this?

Answer: I need to research this and get back to you.

. Line Item B.S. "3 Point Latching System" What is this?

Answer: this should be line item BG, and is a gate with 3 latches lower, middle, upper evenly spaced to help keep gate from being bent to gain access.

An alternate method for making gates more secure may be approved: please submit documentation for technical approval.

. Line item B.V. references "Drawing 1" can't locate drawing 1?

Answer: this should be line item BJ and drawing is attached. If not legible, this can be printed in the CE office and picked up by applicant.

. Seed Project calls to remove 7' of fence and 3' personnel gate, is it the intent to have the gap left from removing the gate in filled with fence?

Answer: Yes, there will be about 3.5' gap in fence line after removing gate and this needs to be filled in with a 7' tall fence. Then remove fence to create opening for new gate to be installed. Additional fence may need to be removed and replaced around the opening for the new gate location over the steam vault.