APPENDIX C – REQUIRED REPORTS/FORMS
Provide the reports/forms as indicated below to the Contracting Officer. All reports, submittals, logs, and information provided to the Government shall be electronic and compatible with Microsoft Office such as Excel, Word, and others. “Compatible” means the document can be opened using the appropriate Microsoft Office component without any discernible effect on the text (e.g., loss of data) or the formatting of the document:
| Item No. |
| Description |
| Due Date |
| PWS Reference |
| 1. |
| Integrated Weed Management Plan |
| Post Award Orientation Conference |
| 1.1.8 |
| 2. |
| AF FORM 483 - Certificate of Competency |
| Upon Contract Award |
| 1.2.3.1 |
| 3. |
| Composting Operations Report |
| Quarterly |
| 1.8.9 |
| 4. |
| Contractor Quality Control Plan |
| Post Award Orientation Conference |
| 2.1 |
| 5. |
| AF FORM 3952 – Chemical /Hazardous Material Authorization |
| As Needed |
| 4.4.1 |
| 6. |
| Material Data Safety Sheets (MSDS) |
| As Needed |
| 4.4.2 |
| 7. |
| Pesticide Reports |
| Monthly |
| 4.4.2.2 |
| 8. |
| Final Hazardous Material Report |
| Contract Completion |
| 4.4.5 |
| 9. |
| AFMC FORM 496 – Application for AFMC Identification Card |
| As Needed |
| 4.8.2 |
| 10. |
| AF FORM 2586 – Unescorted Entry Authorization Certificate |
| As Needed |
| 4.8.3 |
| 11. |
| Contractor Work Schedules |
| Post Award Orientation Conference |
| 4.18 |
| 12. |
| Accident Investigation Reports |
| As Needed |
| 4.14 |
| 13. |
| Contractor Health and Safety Plan |
| Post Award Orientation Conference |
| 4.14.1 |
APPENDIX C