ATT8_240052_Submittal Register.xlsx

XLSX spreadsheet 53 KB Posted

Attached to
WWYK240052 Renovate Hallway, 1AB1-103C, 1AB1-108B, B3001
Solicitation number
FA813726R0049
Issued by

About this file

This is a Submittal Register that documents all required construction submittals for the hallway renovation project WWYK240052 at Tinker Air Force Base, Building B3001. The register lists 168 line items organized by specification section and submittal type, including preconstruction submittals, product data, shop drawings, test reports, certificates, manufacturer's instructions, operation and maintenance data, and closeout submittals. Key preconstruction submittals include health and safety plans, construction phasing plans, environmental compliance documentation (Storm Water Pollution Prevention Plan, environmental management awareness training), hazardous materials authorizations, and asbestos/lead abatement procedures with detailed attachments for different abatement methods. The register specifies numerous product data and shop drawings for building components including steel frames, doors, hardware, glazing, gypsum board, acoustical ceilings, resilient flooring, paints, signage, sprinkler systems, diffusers, exit signs, and luminaires.

Extensive HVAC-related submittals are required, encompassing NADCA system cleaning supervision qualifications, heat trace system installation drawings and testing, equipment isolation testing, TAB (Testing, Adjusting, and Balancing) procedures and certifications, DDC controls design and testing, gas piping systems, boiler systems, water chillers, steam systems, ductwork, and refrigeration components. Electrical submittals include panelboards, receptacles, circuit breakers, lightning protection systems, and fire alarm system documentation with designer and installer qualifications. The register indicates Government (G) review authority for approximately 70% of submittals, with several items requiring contractor action codes and tracking approval timelines. Operation and maintenance manuals, as-built drawings, training documentation, and waste disposal records are identified as closeout requirements, with specific formatting requirements including electronic and hard copy delivery of certain documents.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal Register_General Requ

TITLE:WWYK240052SUBMITTAL REGISTER
JOB NAME:Renovate Hallway, 1AB1 103C - 1AB1 - 108B
LOCATION:
CONTRACT NO:
CONTRACTOR:
CONTRACTOR SCHEDULE DATESCONTRACTOR ACTIONAPPROVING AUTHORITY
(a)(b)(c)(d)(e)(f)(g)(h)(i)(j)(k)(l)(m)(n)(o)(p)(q)(r)
LineActivity #Transmittal #Specification SectionSD #Submittal DescriptionItem SubmittedParagraph #Classification: GOVT or A/E ReviewerSubmitApproval Needed ByMaterial Needed ByAction CodeDate Of ActionDate FWD to APPR / Auth Date RCD From CONTRDate FWD To Other RevwrDate RCD From Other ReviewerAction CodeDate Of ActionMailed To CONTR/ Date RCD From APPR AuthorityRemarks
100 70 0001Preconstruction SubmittalsEntry Access List1.6G
200 70 0001Preconstruction SubmittalsKey Issue Receipt1.3.12.1
300 70 0006Test ReportsPre-Construction Testing Record1.3.11G
500 70 0007CertificatesWelding, Cutting and Brazing Permit1.4G
500 70 0007CertificatesFramed Instructions1.8
600 70 0011Closeout SubmittalsKey Return Receipt1.3.12.1
700 71 0001Preconstruction SubmittalsHealth and Safety Plan1.3G
800 71 0001Preconstruction SubmittalsInternal Combustion Engines Plan1.3.5G
900 71 0001Preconstruction SubmittalsEntry Authority List1.5.2
1000 71 0001Preconstruction SubmittalsVehicle Entry Authority List1.5.2G
1100 71 0001Preconstruction SubmittalsEquipment and Material Storage1.5G
1200 71 0001Preconstruction SubmittalsContractor Offices and Plants1.5G
1300 71 0001Preconstruction SubmittalsDesignated Waste and Disposal Areas1.5G
1400 71 0001Preconstruction SubmittalsConstruction Phasing Plan1.5G
1500 71 0001Preconstruction SubmittalsAirfield Construction Waiver1.5GMust be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.
1600 71 0001Preconstruction SubmittalsFAA Form 7460-11.5.3G
1700 71 0007CertificatesSafety Meetings1.3
1800 71 0007CertificatesFOD Awareness and Prevention Training1.4
1900 72 0001Preconstruction SubmittalsRestoration Plan1.3.2G
2000 72 0001Preconstruction SubmittalsStorm Water Pollution Prevention Plan1.3.3.2G
2100 72 0001Preconstruction SubmittalsWater System Construction Permit1.3.3.6G
2200 72 0001Preconstruction SubmittalsAF Form 3952 Chemical/Hazardous Material Request/Authorization1.4G
2300 72 0001Preconstruction SubmittalsSpray Painting Plan1.9G
2400 72 0001Preconstruction SubmittalsEnvironmental Management System Awareness Training1.1
2500 72 0003Product DataNew Boiler Information Form1.3.8.2G
2600 72 0003Product DataAffirmative Procurement Documentation or Green Statement1.3.10GProvide only one. Reference specification for additional information
2700 72 0006Test ReportsAF Form 487 Generator Operating Log (Inspection and Testing)1.3.8.1G
2800 72 0007CerificatesFire Ant Federal Compliance Agreement or state phyto-sanitary certificate1.3.4.1
2900 72 0007CerificatesMonthly Hazardous Material Usage Report1.4GProvide 1st week of each month during construction
3000 72 0007CerificatesRefrigerant Technical Certifications1.5G
3100 72 0007CerificatesRefrigerant Installation1.5G
3200 72 0008Manufacturer's InstructionsSafety Data Sheets/Material Safety Data Sheets1.4
3300 72 0011Closeout SubmittalsNotice of Termination
(ODEQ Form 640-572)1.3.3.2G
3400 72 00 - Attch 201Preconstruction SubmittalsDocumentation of Training/ ExperienceC.2

C.13 35 00 72 00 - Attch 2 01 Preconstruction Submittals Employee Physicals C.2 C.13

3600 72 00 - Attch 201Preconstruction SubmittalsRegulatory Agency NotificationC.3
3700 72 00 - Attch 201Preconstruction SubmittalsSecurity DocumentationC.4
3800 72 00 - Attch 201Preconstruction SubmittalsCommunicationsC.5
3900 72 00 - Attch 201Preconstruction SubmittalsStep-by-Step Abatement ProceduresC.6G
4000 72 00 - Attch 201Preconstruction SubmittalsGlovebag ProceduresC.7G
4100 72 00 - Attch 201Preconstruction SubmittalsNegative Pressure Enclosure Construction ProceduresC.8G
4200 72 00 - Attch 201Preconstruction SubmittalsRespirator Protection ProgramC.9
4300 72 00 - Attch 201Preconstruction SubmittalsEncapsulation ProceduresC.11G
4400 72 00 - Attch 201Preconstruction SubmittalsLandfill QualificationsC.14
4500 72 00 - Attch 201Preconstruction SubmittalsWork ScheduleC.16
4600 72 00 - Attch 201Preconstruction SubmittalsEmergency Plans and Fire Prevention PlansC.17G
4700 72 00 - Attch 201Preconstruction SubmittalsWritten Hazardous Communication ProgramC.18
4800 72 00 - Attch 201Preconstruction SubmittalsRental EquipmentC.19
4900 72 00 - Attch 207CerificatesManufacturer’s CertificationsC.10
5000 72 00 - Attch 207CerificatesLaboratory and Monitoring Qualifications/CertificationsC.12
5100 72 00 - Attch 207CerificatesAsbestos Waste Transporter Certification of InsuranceC.13
5200 72 00 - Attch 208Manufacturer's InstructionsSafety Data Sheets/Material Safety Data SheetsC.15
5300 72 00 - Attch 211Closeout SubmittalsWaste Disposal ReceiptM.1(1)G
5400 72 00 - Attch 211Closeout SubmittalsAir Sampling ResultsM.1(2)G
5500 72 00 - Attch 301Preconstruction SubmittalsDocumentation of Training/ ExperienceC.1
5600 72 00 - Attch 301Preconstruction SubmittalsEmployee PhysicalsC.2
5700 72 00 - Attch 301Preconstruction SubmittalsSecurity DocumentationC.3
5800 72 00 - Attch 301Preconstruction SubmittalsStep-by-Step Abatement Procedures PlanC.4G
5900 72 00 - Attch 301Preconstruction SubmittalsFull Containment Construction Procedures/DrawingsC.5G
6000 72 00 - Attch 301Preconstruction SubmittalsRespirator Protection ProgramC.6
6100 72 00 - Attch 301Preconstruction SubmittalsWork ScheduleC.11G
6200 72 00 - Attch 303Product DataMaterials ListC.10
6300 72 00 - Attch 307CerificatesManufacturer’s CertificationsC.7
6400 72 00 - Attch 307CerificatesLaboratory and Monitoring QualificationsC.8
6500 72 00 - Attch 307CerificatesLead Based Paint Waste Transporter’s QualificationsC.9
6600 72 00 - Attch 311Closeout SubmittalsWaste Disposal ReceiptM.1.1G
6700 72 00 - Attch 311Closeout SubmittalsAir Sampling ResultsM.1.2G
6800 72 00 - Attch 311Closeout SubmittalsVerification of Decontamination of Rental EquipmentM.1.3
6900 72 00 - Attch 3a01Preconstruction SubmittalsRemoval ProceduresB.1G
7000 72 00 - Attch 3a03Product DataList of MaterialB.2
7100 72 00 - Attch 3a08Manufacturer's InstructionsMaterial Data SheetsB.3
7200 72 00 - Attch 501Preconstruction SubmittalsConstruction Debris Analysis Plan1.2.3G
7300 72 00 - Attch 507CertificatesMonthly Debris Management Report2GProvide 1st week of each month during construction
7400 72 00 - Attch 1101Preconstruction SubmittalsTree Planting/Removal Permit1.1G
7500 72 00 - Attch 1101Preconstruction SubmittalsTree Protection Plan2.1G
7601 32 16.00 2001Preconstruction SubmittalsBaseline Construction Schedule1.2GProvide within 10 days of NTP.
7701 32 16.00 2001Preconstruction SubmittalsBaseline Design Schedule1.2GProvide within 10 days of NTP.
7801 32 16.00 2007CertificatesMonthly Updates1.4Provide 1st week of each month during construction, or as directed by CO
7901 32 16.00 2007Certificates3-Week Look Ahead Schedule1.6Provide weekly with the Contract Progress Report
8001 33 0001Preconstruction SubmittalsSubmittal Register1.8G
8101 33 16.00 1001Preconstruction SubmittalsDesign Quality Control Plan1.5.1G
8201 33 16.00 1001Preconstruction SubmittalsInitial Design Conference1.5.2.2
8301 33 16.00 1001Preconstruction SubmittalsPreconstruction Conference1.5.2.3
8401 33 16.00 1001Preconstruction SubmittalsDCM Procedures3.5.1G
8501 33 16.00 1001Preconstruction SubmittalsSubmittal Register3.8.4G
8601 33 16.00 1005Design DataDesign and Code Checklists1.7.1C
8701 33 16.00 1005Design DataInterim Design Submittals3.2.1R
8801 33 16.00 1005Design DataInterior And Exterior Building Finishes Scheme3.6.5.1.1G
8901 33 16.00 1005Design DataConference Documentation3.7.3
9001 33 16.00 1005Design DataFinal Design Submittals3.8R
9101 33 16.00 1005Design DataDesign Complete Documents3.9C
9201 33 16.00 1011Closeout SubmittalsDD Form 13543.8.5A
9301 45 00.00 1001Preconstruction SubmittalsQuality Control (QC) Plan3.2G
9401 45 00.00 1001Preconstruction SubmittalsAdditional Requirements for Design Quality Control (DQC) Plan3.2.2G
9501 45 00.00 1005Design DataDiscipline-Specific Checklists3.2.2
9601 45 00.00 1005Design DataDesign Quality Control3.9.1
9701 45 00.00 1006Test ReportsQC Documentation3.9Provide weekly with the Contract Progress Report
9801 50 0001Preconstruction SubmittalsRequest for Contractor Staging Area1.1G
9901 50 0001Preconstruction SubmittalsPhotographic Record1.3
10001 78 0003Product DataWarranty Letter1.7.1
10101 78 0003Product DataWarranty Tags1.7.3
10201 78 0003Product DataSpare Parts Data1.5
10301 78 0008Manufacturer's InstructionsInstructions1.7.1
10401 78 0010Operation and Maintenance DataOperation and Maintenance Manuals3.4GProvide (2) electronic sets (optical media) and (1) hard copy
10501 78 0011Closeout SubmittalsWorking As-Built Drawings3.1GProvide (2) electronic sets (optical media) and (2) hard copies
10601 78 0011Closeout SubmittalsRecord Drawings3.3GProvide (2) electronic sets (optical media) and (1) hard copy
10701 78 0011Closeout SubmittalsCertification of EPA Designated Items2.3G
10801 78 0011Closeout SubmittalsCertification Of USDA Designated Items2.4G
10901 78 0011Closeout SubmittalsDD FORM 13543.6G
11001 78 0011Closeout SubmittalsChecklist for DD FORM 13543.6G
11101 78 2310Operation and Maintenance DataOperation and Maintenance Data1.2GProvide 30 days prior to scheduled Training
11201 78 2310Operation and Maintenance DataO&M Database1.3G
11301 78 2310Operation and Maintenance DataTraining Plan3.1.1GProvide 30 days prior to scheduled Final Inspection
11401 78 2310Operation and Maintenance DataTraining Content3.1.2GProvide 14 days prior to scheduled Training
11501 78 2310Operation and Maintenance DataTraining Outline3.1.3GProvide 14 days prior to scheduled Training
11601 78 2311Closeout SubmittalsTraining Video Recording3.1.4G
11701 78 2311Closeout SubmittalsValidation of Training Completion3.1.6G
118SOW07CertificatesContract Progress Report(s)2.4GProvide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal)
119SOW01Preconstruction SubmittalsB3001 Visitor Badge Issue Receipt1.3.7
120SOW11Closeout SubmittalsB3001 Visitor Badge Return Receipt1.3.7
12102 41 0001Preconstruction SubmittalsDemolition and Deconstruction1.6G
12207 92 0003Product DataJoint Sealants2.1.2G
12308 11 1302Shop DrawingsSteel Frames2.7G
12408 11 1303Product DataSteel Frames2.7G
12508 14 0002Shop DrawingsWood Doors-CUSTOMSOW 4.2 (1)G
12608 14 0003Product DataWood Doors-CUSTOMSOW 4.2 (1)G
12708 14 0004SamplesWood Doors-CUSTOMSOW 4.2 (1)G
12808 71 0002Shop DrawingsDoor HardwareG
12908 71 0003Product DataDoor HardwareG
13008 81 0002Product DataGlazing-Laminated2.2.6G
13109 29 0003Product DataGypsum BoardSOW 4.2 (4)G
13209 51 0003Product dataAcoustical CeilingsSOW 4.2 (2)G
13309 65 0003Product dataResilient Flooring (LVT Wainscot for wall)2.5 & SOW 4.2 (4)G
13409 65 0003Product dataChair RailSOW 4.2 (6)G
13509 65 0003Product dataRubber BaseSOW 4.2 (7)G
13609 90 0003Product dataPaints and CoatingsG
13710 14 0003Product dataSignageSOW 4.2 (10)G
13810 26 0003Product dataStainless Steel Corner Guards2.2.2
13910 44 1603Product dataFire extinguisersG
14021 13 1303Product DataWet Pipe Sprinkler-escutcheons2.7 & 2.12.2G
14123 00 0003Product dataDiffusers2.9.9G
14226 51 0003Product DataExit signs2.6 & SOW 4.9.2G
14326 51 0002Shop DrawingsLuminaire DrawingsSOW 4.9G
14426 51 0003Product DataLuminairesSOW 4.9G
14523 01 30.411Preconstruction SubmittalsNADCA Supervisor Qualifications1.4.1G
14623 01 30.411Preconstruction SubmittalsRecords of Experience in the Field of HVAC System Cleaning1.4.2G
14723 01 30.411Preconstruction SubmittalsNADCA Work Execution Schedule1.5.1G
14823 01 30.413Product DataSafety Data Sheets (SDS)1.4.3G
14923 01 30.416Test ReportsTesting Procedures Summary3.3.2G
15023 01 30.416Test ReportsGravimetric Analysis3.3.1.3G
15123 01 30.416Test ReportsPost-Project Report3.3.2G
15223 05 152Shop DrawingsInstallation Drawings3.1G
15323 05 153Product DataHeat Trace Systems2.1G
15423 05 156Test ReportsHeat Trace Cable Tests3.2G
15523 05 157CertificatesList of Qualified Permanent Service Organizations1.4.2G
15623 05 1510Operation and Maintenance DataOperation and Maintenance Manuals3.3G
15723 05 48.00 402Shop DrawingsInstallation Drawings1.2
15823 05 48.00 403Product DataEquipment and Performance Data1.2
15923 05 48.00 403Product DataIsolators2.2.3
16023 05 48.00 406Test ReportsType of Isolator2.4
16123 05 48.00 406Test ReportsType of Base2.4
16223 05 48.00 406Test ReportsAllowable Deflection2.4
16323 05 48.00 406Test ReportsMeasured Deflection2.4
16423 05 931Preconstruction SubmittalsRecords of Existing Conditions1.3.3G
16523 05 931Preconstruction SubmittalsIndependent TAB Agency and Personnel Qualifications1.5.1G
16623 05 931Preconstruction SubmittalsTAB Design Review Report1.7.2.1G
16723 05 931Preconstruction SubmittalsTAB Firm1.5.1.1G
16823 05 931Preconstruction SubmittalsTAB Team Assistants1.2G
16923 05 931Preconstruction SubmittalsTAB Team Engineer1.2G
17023 05 931Preconstruction SubmittalsTAB Specialist1.5.1.1G
17123 05 931Preconstruction SubmittalsTAB Team Field Leader1.2G
17223 05 932Shop DrawingsTAB Schematic Drawings and Report Forms1.3.3G
17323 05 933Product DataTAB Related HVAC Submittals1.5.1.2G
17423 05 933Product DataTAB Procedures1.5.5G
17523 05 933Product DataCalibration1.5.5G
17623 05 933Product DataSystems Readiness Check1.3.3G
17723 05 936Test ReportsCertified Final TAB Report1.5.2.3
17823 05 936Test ReportsSeason 13.3.5.2
17923 05 936Test ReportsSeason 23.3.5.2G
18023 05 936Test ReportsTAB Report for Season 11.5.7.1G
18123 05 936Test ReportsTAB Report for Season 21.5.7.1G
18223 05 937CertificatesTAB Submittal and Work Schedule1.7.2G
18323 05 937CertificatesTAB Pre-Field Engineering Report1.7.2.2G
18423 05 937CertificatesInstrument Calibration Certificates1.5.4G
18523 05 937CertificatesTAB Procedures Summary3.6G
18623 05 937CertificatesAdvanced Notice for Season 1 TAB Field Work1.7.2G
18723 05 937CertificatesPrerequisite HVAC Work Check Out List For Season 11.7.2G
18823 05 937CertificatesAdvanced Notice for Season 2 TAB Field Work1.7.2G
18923 05 937CertificatesPrerequisite HVAC Work Check Out List For Season 21.7.2G
19023 07 002Shop DrawingsMICA Plates2.1G
19123 07 002Shop DrawingsPipe Insulation Systems2.3
19223 07 002Shop DrawingsDuct Insulation Systems2.4
19323 07 002Shop DrawingsEquipment Insulation Systems2.5
19423 07 002Shop DrawingsRecycled content for insulation materials2.3.1
19523 07 003Product DataPipe Insulation Systems2.3G
19623 07 003Product DataDuct Insulation Systems2.4G
19723 07 003Product DataEquipment Insulation Systems2.5G
19823 07 007CertificatesIndoor air quality for adhesives2.2.1S
19923 07 008Manufacturer's InstructionsPipe Insulation Systems2.3G
20023 07 008Manufacturer's InstructionsDuct Insulation Systems2.4G
20123 07 008Manufacturer's InstructionsEquipment Insulation Systems2.5G
20223 09 002Shop DrawingsDDC Contractor Design Drawings3.3G
20323 09 002Shop DrawingsDraft As-Built Drawings3.3G
20423 09 002Shop DrawingsFinal As-Built Drawings3.3G
20523 09 003Product DataProgramming Software1.8.3G
20623 09 003Product DataController Application Programs1.8.4G
20723 09 003Product DataConfiguration Software1.8.1G
20823 09 003Product DataController Configuration Settings1.8.2G
20923 09 003Product DataManufacturer's Product Data2.2G
21023 09 006Test ReportsExisting Conditions Report3.1.1G
21123 09 006Test ReportsStart-Up Testing Report3.5.2G
21223 09 006Test ReportsPVT Procedures3.6.1G
21323 09 006Test ReportsPVT Report3.6.3G
21423 09 006Test ReportsPre-Construction Quality Control (QC) Checklist1.9.1G
21523 09 006Test ReportsPost-Construction Quality Control (QC) Checklist1.9.2G
21623 09 0010Operation and Maintenance DataOperation and Maintenance (O&M) Instructions3.7G
21723 09 0010Operation and Maintenance DataTraining Documentation3.9.1G
21823 09 0011Closeout SubmittalsEnclosure Keys2.5G
21923 09 0011Closeout SubmittalsPassword Summary Report3.2.6.1G
22023 09 0011Closeout SubmittalsCloseout Quality Control (QC) Checklist1.9.3G
22123 11 202Shop DrawingsGas Piping System1.5.2G
22223 11 203Product DataPipe and Fittings2.2.7G
22323 11 203Product DataGas Equipment Connectors1.5.2G
22423 11 203Product DataPressure Regulators2.5G
22523 11 203Product DataValves2.3G
22623 11 206Test ReportsTesting3.13G
22723 11 206Test ReportsPressure Tests3.13.1G
22823 11 206Test ReportsTest with Gas3.13.2G
22923 11 207CertificatesWelders Procedures and Qualifications1.5.1G
23023 11 207CertificatesAssigned Number, Letter, or Symbol1.5.1G
23123 21 232Shop DrawingsSystem Coordination2.1.2G
23223 21 233Product DataInstructions2.2.2G
23323 21 233Product DataEquipment Data2.2.5G
23423 21 233Product DataTraining Period3.5.2G
23523 21 236Test ReportsField Quality Control3.3
23623 21 237CertificatesManufacturer's Representative1.3.1
23723 21 2310Operation and Maintenance DataOperation and Maintenance Manuals3.5.1G
23823 21 2310Operation and Maintenance DataTraining3.5.2G
23923 22 13.35 403Product DataManufacturer's Catalog DataPart 2G
24023 22 13.35 402Shop DrawingsInstallation Drawings3.1G
24123 22 13.35 407CertificatesList of Product Installations1.3G
24223 22 13.35 407CertificatesSteam Traps2.2G
24323 22 13.35 407CertificatesTrap Bodies and Components2.2G
24423 30 002Shop DrawingsDetail Drawings1.4.3G
24523 30 003Product DataInsulated Nonmetallic Flexible Duct Runouts2.8.1.1
24623 30 003Product DataDuct Connectors2.8.1.2
24723 30 003Product DataDuct Access Doors2.8.2G
24823 30 003Product DataManual Balancing Dampers2.8.3G
24923 30 003Product DataAcoustical Duct Liner2.8.4.1
25023 30 003Product DataDiffusers2.8.5.1G
25123 30 003Product DataRegisters and Grilles2.8.5.2G
25223 30 003Product DataAir Handling Units2.1G
25323 30 003Product DataVariable Volume, Single Duct Terminal Units2.11.1.1G
25423 30 003Product DataTest Procedures1.4.4
25523 30 003Product DataIndoor Air Quality for Duct Sealants2.8.1G
25623 30 003Product DataUnit Heaters2.12G
25723 30 006Test ReportsPerformance Tests3.1G
25823 30 008Manufacturer's InstructionsManufacturer's Installation Instructions3.2
25923 30 008Manufacturer's InstructionsOperation and Maintenance Training3.12.2
26023 30 0010Operation and Maintenance DataOperation and Maintenance Manuals3.12.1G
26123 30 0010Operation and Maintenance DataManual Balancing Dampers2.8.3G
26223 30 0010Operation and Maintenance DataAir Handling Units2.1G
26323 30 0010Operation and Maintenance DataVariable Volume, Single Duct Terminal Units2.11.1.1G
26423 30 0010Operation and Maintenance DataUnit Heaters2.12G
26523 30 0011Closeout SubmittalsIndoor Air Quality During Construction3.11G
26623 52 43.00 202Shop DrawingsFuel Train1.2.2.2
26723 52 43.00 202Shop DrawingsWiring Diagram1.2.2.2
26823 52 43.00 203Product DataPackaged Boiler Systems2.1G
26923 52 43.00 203Product DataBoiler Trim and Control Equipment2.3
27023 52 43.00 203Product DataBurners and Control Equipment2.2
27123 52 43.00 203Product DataStack, Breeching, and Supports2.3.12G
27223 52 43.00 206Test ReportsOperational Tests3.4.1G
27323 52 43.00 207CertificatesBurners and Control Equipment2.2
27423 52 43.00 207CertificatesBoiler Trim and Control Equipment2.3
27523 52 43.00 208Manufacturer's InstructionsPackaged Boiler Systems2.1
27623 52 43.00 2010Operation and Maintenance DataPackaged Boiler Systems2.1
27723 52 43.00 2011Closeout SubmittalsPackaged Boiler Systems2.1
27823 64 103Product DataWater Chiller3.1G
27923 64 103Product DataPosted Instructions3.1.3
28023 64 103Product DataVerification of Dimensions1.6.1
28123 64 103Product DataFactory Tests2.8G
28223 64 103Product DataSystem Performance Tests3.6
28323 64 103Product DataDemonstrations3.7
28423 64 103Product DataRefrigerant2.5.1G
28523 64 103Product DataWater Chiller - Field Acceptance Test Plan3.5.1
28623 64 106Test ReportsField Acceptance Testing3.5
28723 64 106Test ReportsWater Chiller - Field Acceptance Test Report3.5.2
28823 64 106Test ReportsFactory Tests2.8G
28923 64 106Test ReportsSystem Performance Tests3.6
29023 64 107CertificatesRefrigeration System3.1.9G
29123 64 107CertificatesOzone Depleting Substances Technician Certification1.3.1
29223 64 107CertificatesWater Chiller - Installation Instructions3.1G
29323 64 1010Operation and Maintenance DataOperation and Maintenance Manuals3.7G
29423 64 263Product DataGrooved Mechanical Connections For Steel2.2.2.4G
29523 64 263Product DataGrooved Mechanical Connections For Copper2.4.3G
29623 64 263Product DataCalibrated Balancing Valves2.5.8G
29723 64 263Product DataCombination Strainer and Pump Suction Diffuser2.6.2
29823 64 266Test ReportsPiping Welds NDE Report3.1.1.3
29923 64 266Test ReportsPressure Tests Reports3.3.2G
30023 64 267CertificatesEmployer's Record Documents (For Welding)3.1.1.1
30123 64 267CertificatesWelding Procedures and Qualifications3.1.1.2
30223 64 267CertificatesPiping for Steam and Condensate2.3
30323 64 267CertificatesFittings2.3
30423 64 267CertificatesUnions2.3
30523 64 267CertificatesFlanges2.3
30623 64 267CertificatesGaskets2.3
30723 64 267CertificatesBolting2.3
30823 64 268Manufacturer's InstructionsLesson plan for the Instruction Course3.4G
30923 64 2610Operation and Maintenance DataCalibrated Balancing Valves2.5.8G
31023 64 2610Operation and Maintenance DataCombination Strainer and Pump Suction Diffuser2.6.2G
31123 81 003Product DataSpare Parts3.7.1
31223 81 003Product DataPosted Instructions3.4
31323 81 003Product DataCoil Corrosion Protection2.5.1
31423 81 003Product DataTraining3.4G
31523 81 003Product DataManufacturer's Standard Catalog Data2.2G
31623 81 006Test ReportsRefrigerant Tests, Charging, and Start-Up3.5G
31723 81 006Test ReportsSystem Performance Tests3.6G
31823 81 007CertificatesService Organizations3.7.2
31923 81 0010Operation and Maintenance DataOperation and Maintenance Manuals3.4G
32023 81 0011Closeout SubmittalsOzone Depleting Substances2.2.2.3G
32126 20 002Shop DrawingsPanelboards2.11G
32226 20 002Shop DrawingsMini Power zone2.21G
32326 20 002Shop DrawingsMarking Strips3.1.6.1
32426 20 003Product DataReceptacles2.1G
32526 20 003Product DataCircuit Breakers2.11.3G
32626 20 003Product DataSwitches2.8G
32726 20 003Product DataMotor Controllers2.12G
32826 20 003Product DataManual Motor Starters2.13G
32926 20 006Test Reports600-volt Wiring Test3.5.2G
33026 20 006Test ReportsGround-fault Receptacle Test3.5.3G
33126 20 007CertificatesFuses2.9G
33226 20 0010Operation and Maintenance DataElectrical Systems1.5.1G
33326 28 01.00 103Product DataFault Current Analysis2.1
33426 28 01.00 103Product DataProtective Device Coordination Study and Arc Flash Hazard Analysis2.1
33526 28 01.00 103Product DataSystem Coordinator1.4.1
33626 29 232Shop DrawingsSchematic Diagrams1.5.1G
33726 29 232Shop DrawingsInterconnecting Diagrams1.5.2G
33826 29 232Shop DrawingsInstallation Drawings1.5.3G
33926 29 232Shop DrawingsAs-Built Drawings1.5.3G
34026 29 233Product DataAdjustable Speed Drives2.1G
34126 29 233Product DataWires and Cables2.3G
34226 29 233Product DataEquipment Schedule1.5.4
34326 29 236Test ReportsASD Test3.3.1G
34426 29 236Test ReportsPerformance Verification Tests3.3.2G
34526 29 236Test ReportsEndurance Test3.3.3G
34626 29 237CertificatesTesting Agency's Field Supervisor3.3.1G
34726 29 238Manufacturer's InstructionsInstallation instructions1.5.5G
34826 29 239Manufacturer's Field ReportsASD Test Plan2.5.1G
34926 29 239Manufacturer's Field ReportsStandard Products1.5.6
35026 29 2310Operation and Maintenance DataAdjustable Speed Drives2.1
35126 41 002Shop DrawingsOverall lightning protection system1.4.1.1G
35226 41 002Shop DrawingsEach major component1.4.1.2G
35326 41 006Test ReportsLightning Protection and Grounding System Test Plan1.4.3G
35426 41 006Test ReportsLightning Protection and Grounding System Test3.5.1G
35526 41 007CertificatesLightning Protection System Installers Documentation1.2.3G
35626 41 007CertificatesComponent UL Listed and Labeled1.4.2G
35726 41 007CertificatesLightning protection system inspection certificate1.4.4G
35826 41 007CertificatesRoof manufacturer's warranty3.1.1G
14528 31 761Preconstruction SubmittalsFire alarm system designer1.9.2.1G
14628 31 761Preconstruction SubmittalsSupervisor1.9.2.2G
14728 31 761Preconstruction SubmittalsTechnician1.9.2.3G
14828 31 761Preconstruction SubmittalsInstaller1.9.2.4G
14928 31 762Shop DrawingsWiring Diagrams1.9.1.4G
15028 31 762Shop DrawingsSystem Layout1.9.1.5G
15128 31 762Shop DrawingsNotification Appliances1.9.1.6G
15228 31 762Shop DrawingsAmplifiers1.9.1.8G
15328 31 762Shop DrawingsBattery Power1.9.1.9G
15428 31 762Shop DrawingsVoltage Drop Calculations1.9.1.10G
15528 31 763Product DataNotification Appliances1.9.1.6G
15628 31 763Product DataBatteries2.14.1G
15728 31 763Product DataBattery Chargers2.14.2G
15828 31 763Product DataSupplemental Notification Appliance Circuit Panels2.14.1.1G
15928 31 763Product DataAuxiliary Power Supply Panels2.14.1.1G
16028 31 763Product DataAlarm Wiring2.15G
16128 31 763Product DataBack Boxes and Conduit3.3.4G
16228 31 763Product DataCeiling Bridges3.2.9G
16328 31 766Test ReportsTest Procedures3.6.1G
16428 31 767CertificatesVerification of Compliant Installation3.6.2.1G
16528 31 767CertificatesRequest for Government Final Test3.6.2.2G
16628 31 7610Operation and Maintenance DataOperation and Maintenance (O&M) Instructions3.8G
16728 31 7611Closeout SubmittalsNFPA 72 System Record of CompletionG
16828 31 7611Closeout SubmittalsAs-Built Drawings1.9.1.13G

&8Submittal Register_v3_03/07/22