ATT09_250131_Submittal Register.pdf
PDF 134 KB Posted
- Solicitation number
- FA813726R0048
About this file
This is a Submittal Register for a construction contract at Tinker Air Force Base for the replacement of ridge cap on Hangar Roof (Building B824), Project No. WWYK250131. The register serves as a tracking document for all required contractor submissions throughout the project lifecycle.
The register identifies 122 submittal line items organized by specification section and submission type, including preconstruction submittals, certificates, product data, test reports, manufacturer's instructions, and closeout submittals. Key preconstruction submittals required include the Health and Safety Plan, Construction Phasing Plan, Storm Water Pollution Prevention Plan, Quality Control Plan, Baseline Construction Schedule (within 10 days of Notice to Proceed), and Submittal Register. Environmental and safety-related submittals include the Restoration Plan, Environmental Management System Awareness Training, Monthly Hazardous Material Usage Reports (due first week of each month), Monthly Debris Management Reports, and Safety Data Sheets. The register requires a Metal Ridge Cap submittal (Section 07 41 13) and installer warranty as closeout documentation. Additional required submittals include Working As-Built Drawings and Record Drawings in both electronic and hard copy formats, Contract Progress Reports submitted weekly using AF Form 3065, Quality Control Documentation provided weekly with progress reports, and an Airfield Construction Waiver (submitted by the 5th of the month with 45-day processing time). The register tracks approval authority (Government or A/E Reviewer), submission deadlines, approval dates, and material delivery requirements for each submittal item.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Section L - Instructions to Offerors .pdf.pdf | ||
| WWYK250131 RFIs COR.pdf | ||
| Section L - Instructions to Offerors.pdf | ||
| Section M - Evaluation Factors for Award.pdf | ||
| Site Visit Sign In 07 August 2026.pdf | ||
| ATT10_250131_Drawings.pdf | ||
| ATT08_250131_MACB_SOW.pdf | ||
| Solicitation - FA813726R0048.pdf | ||
| 250131_Specs.zip | ZIP file | |
| EAL List - 250131.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti vity
Transm ittal #
Specification Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR / Auth
Date RCD From
CONTR
Date FWD To Other Revwr
Date RCD From Other Reviewer
Action Code
Date Of Action
Mailed To CONTR/ Date
RCD From
APPR
Authority Remarks
1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G
2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1
6 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1
7 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G
8 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G
9 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2
10 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G
11 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G
12 00 71 00 01 Preconstruction Submittals Contractor Offices and Plants 1.5 G
13 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G
14 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G
15 00 71 00 01 Preconstruction Submittals Airfield Construction Waiver 1.5 G
Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing.
16 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G
17 00 71 00 07 Certificates Safety Meetings 1.3
18 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4
19 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G
20 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G
22 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous Material Request/Authorization 1.4 G
24 00 72 00 01 Preconstruction Submittals Environmental Management System Awareness Training 1.1
26 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement 1.3.10 G Provide only one. Reference specification for additional information
28 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate 1.3.4.1
29 00 72 00 07 Cerificates Monthly Hazardous Material Usage Report 1.4 G Provide 1st week of each month during construction
32 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data Sheets 1.4
33 00 72 00 11 Closeout Submittals Notice of Termination (ODEQ Form 640-572) 1.3.3.2 G
73 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction
74 00 72 00 - Attch 11 01 Preconstruction Submittals Tree Planting/Removal Permit 1.1 G
76 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.
80 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G
93 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G
97 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress Report
98 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G
99 01 50 00 01 Preconstruction Submittals Photographic Record 1.3
100 01 78 00 03 Product Data Warranty Letter 1.7.1
101 01 78 00 03 Product Data Warranty Tags 1.7.3
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
TITLE: Tinker AFB General Requirements Specification (Div 00-01)
SUBMITTAL REGISTER
JOB NAME: WWYK250131 Replace Ridge Cap on Hangar Roof
LOCATION: B824
CONTRACT NO:
CONTRACTOR:
Submittal Register_v3_03/07/22
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti vity
Transm ittal #
Specification Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR / Auth
Date RCD From
CONTR
Date FWD To Other Revwr
Date RCD From Other Reviewer
Action Code
Date Of Action
Mailed To CONTR/ Date
RCD From
APPR
Authority Remarks
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
105 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and
(2) hard copies
106 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and
(1) hard copy
118 SOW 07 Certificates Contract Progress Report(s) 2.4 G Provide weekly throughout life of contract.
Utilize AF Form 3065, Contract Progress Report (or equal)
121 07 41 13 01 Preconstruction Submittals Metal Ridge Cap 2.4
122 07 41 13 01 Close out Submittal Installer warranty 1.8.3
Submittal Register_General Requ