Question_and_Answers_2_-_AWP_South_Dock.pdf

PDF 67 KB Posted

Attached to
Aerial Work Platforms Federal contract opportunity
Solicitation number
FA8125-18-R-0018
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Aerial Work Platforms, newest first.
File Type Posted
South_B2280_Drawings.docx DOCX document
Solicitation_Amendment-2-AWP.pdf PDF
Question_and_Answers_for_AWP_South_Dock.pdf PDF
South_B2280_Drawings.docx DOCX document
Solicitation_Amendment-1-AWP.pdf PDF
Site_Visit_Details.pdf PDF
SOW_08.07.18.pdf PDF
Solicitation-AWP.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

September 4, 2018 Questions & Answers: Aerial Work Platform

FA8125-18-R-0018

QUESTION & ANSWERS:

1. Question:

What is the required minimum clearance between the bottom of AWP in the highest position to the floor?

Answer:

The highest aircraft tail (vertical) is approximately 43 feet. Personnel will be required to perform hands on corrosion control operations (masking, sanding, sealing, etc...) to the aircraft. The platform shall be designed in a manner that will allow a person standing on the AWP to physically touch the aircraft.

2. Question:

Please see updated drawings of B2280. AMOVA should be replaced with successful contractor.