E-9A Contractor Logistics Support
RFP: FA8106-16-R-0008
Questions and Answers August 19, 2016
1) Should subfactor 5, Mission Essential Services be excluded from the Past Performance evaluation?
Yes, Subfactor 5 is excluded from the past performance evaluation.
2) Are offerors supposed to include the Past Performance Information Sheets (PPIS) in the Past Performance Volume if submitted via the electronic tool?
Yes, copies of the PPIS must be included in the Past Performance Volume as well as being completed via the PPI Tool.
3) In the Draft Solicitation, there were two separate sections the PPISs and the Narrative information, which stated that the PPISs not exceed 10 pages and Narratives not exceed 5 pages.
This iteration of the solicitation states the same page counts but is unclear because they both refer to the PPI tool.
Could the Government please provide clarification concerning the 3.3.1 PPI requirement not to exceed 10 pages for each PPI and the 3.3.2 Contract Narrative requirement not to exceed 5 pages for each narrative?
A PPI relevant contract narrative goes within each PPIS. The PPI contract narrative should be input into the Program Details Tab within the PPI tool. The Government requests the PPIS generated from the PPI tool not exceed a target of 10 pages. The contract narrative within the PPIS is requested to be limited to 5 pages.