Increased Capacity Latrine - SOW17Nov23.pdf
PDF 273 KB Posted
- Attached to
- C/KC-135 Increased Capacity Latrine
- Solicitation number
- FA810524R0001
About this file
This statement of work outlines requirements for a federal contract to design, manufacture, test, and deliver replacement increased capacity latrines for the KC-135 aircraft. The contractor shall replace the existing latrine with a larger 8-gallon model that fits within the existing footprint and does not interfere with aircraft structures or systems. The contractor must complete all engineering, testing, certification, and data package deliverables necessary to qualify the design. The contractor shall deliver low-rate production and full-rate production kits meeting requirements for capacity, installation, servicing, power interface, leak prevention, and identification marking. The contractor must also provide support for airworthiness approval, testing at contractor and government facilities, logistics evaluation, and reporting of obsolescence issues over the life of the component.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit_A_CDRLs_Latrine_DRAFT.pdf | ||
| FA810524R0001 DRAFT.pdf | ||
| Increased Capacity Latrine - SOW V3.docx | DOCX document | |
| SSS Latrine Amendment 1 rev. 110123.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
CUI Page 1 of 13
Statement of Work for
C/KC-135 Increased Capacity Latrine
Permanent Modification for the C/KC-135
Solicitation Number: TBD
Preparation Date: 16 Nov 23
PREPARING ORGANIZATION: AFLCMC/WLT TINKER AFB OK 73145
Controlled by: AFLCMC Controlled by: Legacy Tanker Division (WLT) CUI Category: CUI//SP-SSEL Distribution/Dissemination Controls: Distribution D POC: Kyle Larson, DSN 336-5215
CUI Page 2 of 13
1.0 Scope
2.0 Applicable Documents
2.1 Department of Defense (DoD) Specifications
2.2 Industry Publications
2.3 Applicable Drawings and Specifications
2.4 Contract Data Delivery Requirements (CDRLs)
2.5 Availability of DoD Documents
3.0 Requirements
3.2 Program Management
3.4.1 Technical Manual Contractor Requirement
3.5 Airworthiness
3.7 Low Rate Production
3.7.1 Physical Configuration Audit (PCA)
3.7.2 First Article Kits
3.8 Production Kits
3.9 Spares
3.10 Marking, Packaging, and Handling
3.10.1 Item Unique Identification (IUID) Requirements
3.10.2 Packaging and Handling
3.12 Diminishing Manufacturing Sources and Material Shortages (DMSMS)
3.13 Safety
3.13.1 Mishap Incident
3.13.2 Major Mishaps
3.13.3 Accident Investigation
4.0 Warranty
5.0 Contract Closeout
CUI Page 3 of 13
1.0 Scope
This statement of work (SOW) defines the effort required for the contractor to deliver replacement Increased Capacity Latrine to the United States Air Force. The work performed shall consist of the design, fabrication, manufacturing, packaging, kitting, and shipment of low-rate production and full rate production kits. The scope of this program is to replace the existing KC-135 latrine with a larger model with at least 8 gallons of capacity. The size of the new latrine is limited to the existing footprint within the latrine compartment. The new latrine cannot interfere with existing structures, components, or access to aircraft systems. No modification to major aircraft load bearing structures is allowed. The latrine should be comfortable, according to industry standard. The effort shall use a systems-based engineering process that defines the requirements and updates the engineering products necessary to qualify the solution. The contractor shall deliver meeting minutes, reports and analysis supporting Airworthiness Approval, installation and maintenance instructions, as well as Increased Capacity Latrine kits. The Increased Capacity Latrine must:
1. Have a capacity of at least 8 gallons, not to include the rinse tank.
2. Fit within the existing latrine compartment and be useable without interfering with the aircraft battery, a circuit breaker panel located on the aft wall, or any structural component.
3. Be secured to the existing floor in a manner that meets crash certification requirements in accordance with MIL-HDBK-516C 5.1.9 a(5).
4. Be installed and secured without any modification to the existing aircraft or load bearing structures (e. g. mounting to the flooring without going into the aircraft structure).
5. Be capable of servicing without removing either the latrine or any subcomponent. The latrine may be serviced by an existing cart that will connect to servicing points on the latrine. For access to the servicing points, modifications may be made to the aft latrine compartment wall. This wall is non-structural nor load bearing.
6. Be equipped with commercially available servicing points and connections.
7. Connect to an existing aircraft electrical wire connector that supplies 28 volts DC, 5
Amp circuit (cannot draw more power). The latrine may come with appropriate wiring that can be pinned to the existing connector.
8. Be capable of performing without leaks or splashing from the container at maximum roll and bank angles.
9. Latrine must have a way to prevent pressure build-up due to temperature or changes in altitude.
10. Contractor will supply an adapter fitting for standard servicing hose end to allow connection to the outbound toilet mating connector for clean out. Adapter is requested to be see through to allow visual inspection of fluid leaving the toilet holding tank.
11. Contractor shall create and install a placard to be made visible on the front of the latrine with emergency number, kit number/or serial number of kit, and date of manufacturer for reference purposes in discussion of any problematic issues.
CUI Page 4 of 13
2.0 Applicable Documents
The following documents are applicable to this SOW and attached appendices to the extent specified herein.
2.1 Department of Defense (DoD) Specifications
MIL-HDBK-61B Configuration Management Guidance
MIL-HDBK-516C Airworthiness Certification Criteria
MIL-STD-129R Military Marking for Shipment and Storage
MIL-STD-130N Identification Marking OF U.S. Military Property
MIL-STD-461G Electromagnetic Interference Characteristic Requirements for Equipment
MIL-STD-464D Electromagnetic Environment Effects Requirements for Systems
MIL-STD-810H Environmental Engineering Considerations and Laboratory Tests
MIL-STD-882E System Safety
MIL-STD-1472H Human Engineering
MIL-STD-1798D Mechanical Equipment and Subsystems Integrity Program
MIL-STD-2073-1E Standard Practice for Military Packaging
MIL-STD-38784B Department of Defense Standard Practice for Manuals, Technical: General Style and Format Requirements
CUI Page 5 of 13
2.2 Industry Publications
ASTM-D3951-18 Standard Practice for Commercial Packaging
SAE AS50881G Selection and Installation of Wiring and Wiring Devices in Aerospace Vehicles
SAE AS-9132B Data Matrix Quality Requirements for Parts Marking
2.3 Applicable Drawings and Specifications
The below Government drawings are provided as an example of the current Latrine.
Drawing Number Title
A0236574150-001 Toilet Assembly Installation Drawing
3400-001 Tank Assembly (No Drawing)
17000-022 Toilet Assembly Installation Drawing
17000-147 Tank Assembly
2.4 Contract Data Delivery Requirements (CDRLs)
The contractor shall deliver in accordance with (IAW) attached list of DD1423s.
A001 Conference Agenda A002 Presentation Materials A003 Conference Minutes A005 IUID Marking Plan
A006 IUID Verification Report A007 Technical Manual Contractor Requirements A008 Contract Summary Report A009 Requirements Data Model A012 Critical Component List A015 Product Drawings/Models and Associated Lists A020 Aircraft Test Plan
CUI Page 6 of 13
A021 A-Kit Technical Data Package (Drawings) A029 Integrated Master Schedule A030 System Engineering Management Plan A037 Monthly Contract Status Report A041 Risk Management Plan A042 Safety Assessment Report (SAR) A043 Airworthiness Risk Assessment A044 Certification Basis A045 Compliance Report
2.5 Availability of DoD Documents
The contractor shall use the current version of all referenced documents and standards. Unless otherwise indicated, copies of specifications, standards, and handbooks listed in this SOW are available online at http://quicksearch.dla.mil/qsSearch.aspx or from the Standardization Document Order Desk, 700 Robbins Avenue, Building 4D, Philadelphia, PA 19111-5094.
3.0 Requirements
The contractor shall accomplish the delivery of Increased Capacity Latrine in accordance with this Statement of Work.
3.1 Requirements Model
The contractor shall create a requirements model demonstrating 100% traceability of all requirements and use Model-Based Systems Engineering (MBSE) tenants in the creation of the models.
The contractor shall adhere to AFRL-STO MBSE Style Guide v1-2 and OMG SysML Ver 1.6 for all MBSE deliverables. Both the AFRL-STO MBSE Style Guide v1-2 and OMG SysML Ver 1.6 were created to complement each other as one complete style guide. The OMG SysML Ver 1.6 is an embedded file within the AFRL-STO MBSE Style Guide v1-2 Cameo file. This embedded OMG SysML Ver 1.6 will be provided by the government as a PDF. The contractor will need access to No Magic Cameo Systems Modeler Enterprise Edition 2021x or suitable MBSE conversion software to view AFRL-STO MBSE Style Guide v1-2. (A009)
3.2 Program Management
The contractor shall designate a Single Point of Contact (SPOC) for tasks required for the program.
The contractor SPOC shall have responsibility and authority for the control and coordination of contractor work performed under this SOW. The contractor shall also submit a management plan http://quicksearch.dla.mil/qsSearch.aspx
CUI Page 7 of 13 describing the contractor’s organization, assignment of functions, duties, and responsibilities, management procedures and policies, and reporting requirements for the conduct of contractually-imposed tasks, projects, or programs. The contractor shall provide Integrated Master Schedule for the program. (A029, A037, A041)
3.2.1 DoD Green Procurement Program
The contractor shall conform to the DoD Green Procurement Program (GPP). GPP is a mandatory federal acquisition program that focuses on the purchase and use of environmentally preferable products and services. FAR 23.404 applies and states the GPP requires 100% of EPA designated product purchases that are included in the Comprehensive Procurement Guidelines (CPG) list that contains recovered materials, unless the item cannot be acquired: a) competitively within a reasonable timeframe; b) within appropriate performance standards; or c) at a reasonable price. The prime contractor is responsible for ensuring that all subcontractors comply with this requirement.
3.3 Meetings
The contractor shall conduct a series of meetings in the specified conduct.
3.3.1 Kick-Off Meeting
The contractor shall conduct a Kick-off meeting. At this meeting, the contractor shall provide a baseline program schedule. The contractor agenda shall address and provide details to their understanding of the contract requirements and interpretation of the CDRLs at Table 1. The contractor shall also address the qualification plan for the proposed solution, installation process, and environmental testing. (A001, A002, A003, A029)
3.4 Engineering
3.4.1 Technical Manual Contractor Requirement
The contractor shall adhere to the preparation of technical manual content and format requirements detailed in the Technical Manual Contractor Requirements. (A007, A021)
3.5 Airworthiness
The contractor shall provide subject matter support for Airworthiness (AW) activities required by the Government to conduct an AW assessment and receive an AW approval. These AW
CUI Page 8 of 13 activities include development of a Certification Basis, executing compliance verification activities to obtain airworthiness data supporting a Compliance Report and documentation, and assessment of residual risk(s).
3.5.1 Airworthiness Products
3.5.1.1 Certification Basis
The contractor shall develop and deliver the Certification Basis document associated with the Program. The Certification Basis shall comply with AWB-130 and contain the system description, applicable criteria, standards, and methods of compliance from MIL-HDBK-516C, as designated by the Government for this effort, and rationale for non-applicability. This document shall become part of the functional baseline for this program. (A044)
The contractor shall assist the Government in updating the Certification Basis ahead of each AW approval. An updated certification basis shall include rationale for the criteria that have been updated.
3.5.1.2 Compliance Report
The contractor shall develop and deliver the Compliance Report. The Compliance Report shall comply with AWB-140 and provide a mapping of substantiating data to each applicable criterion in the certification basis from MIL-HDBK-516C. Any documentation used to substantiate the AW of the design shall be made available with sufficient time to allow for Government Program Office to review and analyze information in preparation to show AW compliance. (A045)
The contractor shall support all updates of the Government’s Compliance Report, to include rationale for criteria that have been updated (e.g. flight test and production).
3.5.1.3 Airworthiness Risk Assessment
The contractor shall identify hazards due to non-compliances, recommend near term restrictions, and identify work remaining to strengthen compliance. This information shall be captured in the Compliance Report, the associated Program Safety Assessment Report, and the AW Risk Acceptance (AWRA) package. The contractor shall support the Government’s risk acceptance efforts in accordance with AWB-150B. (A042, A043)
3.5.1.4 Support to Obtain Airworthiness Approval
The contractor shall provide the necessary data (e.g. data, information, meeting attendance, etc.)
enabling the Government’s effort of obtaining the AW Approval prior to conducting any flight operations. The contractor shall maintain configuration control of data used to support Military AW Certification and make data access available to the Government for the lifespan of the component(s) following certification approval.
CUI Page 9 of 13
3.6 Test & Evaluation
The contractor shall support integrated contractor/Government Test and Evaluation (T&E) program as described in the latest version DoDI 5000.02, DoDI 5000.89, DAFI 99-103 Test and Evaluation, Capabilities Based Test and Evaluation, KC-135 TEMP, KC-135 Integrated Test Team (ITT) Charter, and applicable Federal Aviation Administration (FAA) regulations, that verifies contractual requirements and accomplishes required T&E for clearances, endorsements, and certifications. Testing is forecasted to take place at Roland R. Wright Air National Guard Base, Salt Lake City, UT.
The contractor shall support Lead Developmental Test Organization (LDTO) dedicated ground and flight test planning and test execution as required IAW DCMA 8210-1D. Testing may happen at both the contractor and an USAF facility.
The contractor will coordinate with the USAF to travel to Roland R. Wright Air National Guard Base, Salt Lake City, Utah to ensure proper installation of the first article for test. Tests shall be coordinated with the Air National Guard Air Force Reserve Test Center.
The contractor shall participate in Test Plan Working Groups (TPWG) aiding in the creation of an aircraft test plan, Test Matrices, and Test Information Sheets (TIS) to include necessary events leading to ground and flight test. TPWGs are estimated to occur monthly up until testing.
(A020)
The contractor shall support the Government in executing iterative testing, in accordance with the latest version of Technical Orders and their associated checklists for flight acceptance testing.
The contractor shall collaborate with the LDTO and Operational Test Organization to trace requirements to the aircraft Test Objectives, Measures of Performance, Measures of Suitability, Measures of Effectiveness, and test development methodologies.
The contractor shall support T&E status updates during ITT meetings, such as T&E schedule, T&E execution status, and progress towards development and delivery of T&E plans, procedures, and reports.
At the Government’s discretion, the contractor shall allow Government observation of, or participation in, functional and integration T&E.
The contractor shall support hardware T&E or provide documentation providing T&E analysis.
The contractor shall be present and mission ready for Test-day-minus-1 (T-1) and Test-day (T-0) meetings.
The contractor shall provide the Government access to data, analysis, and test results for all test events, to include contractor-only test events, integrated contractor-Government test events, and prior test events from existing or modified systems that are used to build evidence for system performance.
The contractor shall support Post Installation Checkout (PICO) of the Latrine.
CUI Page 10 of 13
The contractor shall support logistics T&E by allowing observational access by Government personnel to maintenance activities during manufacturing, modification, flight, and ground activities for the purpose of data collection efforts and evaluation to aid the Government in determining system maintainability, integration, supportability, availability, and life cycle management.
The contractor shall support Operational Test & Evaluation (OT&E) by fielding questions and providing system expertise, as required.
The contractor shall provide engineering technical support on the use of the special equipment and associated software to Government personnel.
The contractor shall deliver interface data and operating instructions for the equipment.
At the completion of integration testing, the contractor shall participate in a T&E Deficiency Review Board (DRB) chaired by the Government with membership from the ITT to review the deficiencies and integration problems/issues discovered during testing. As agreed by the T&E DRB, deficiencies and integration problems/issues not corrected in the build may be designated as watch items for the next test phase or documented as Deficiency Reports (DR) IAW the
USAF TO 00-35D-54.
The contractor shall collaborate with LDTO in developing a System Test Report (STR) detailing Latrine qualification test results, system and sub-system test results, deficiencies, limitations to Integrated Test & Evaluation, and possible hazardous conditions associated with the latrine modification.
3.7 Low Rate Production
3.7.1 Physical Configuration Audit (PCA)
The Government will conduct, with contractor participation, a 100% PCA prior to shipment of the first article to verify the actual configuration meets the approved drawing and technical data package specifications. The contractor shall notify the Government 10 business day prior to the scheduled PCA. The contractor shall ensure the PCA kits consist of quantities of equipment called out in the kit drawing. (A012, A015)
3.7.2 First Article Kits
The contractor shall deliver the first article kits in accordance with the contract schedule. The contractor shall manufacture, fabricate, kit and produce kits in accordance with approved drawings.
The government will complete a first article inspection and will provide written notice of
CUI Page 11 of 13 approval/disapproval to proceed with full production. First articles that do not conform to the design specifications shall be destroyed or returned to the contractor at contractor expense.
3.8 Production Kits
The Government defines production kit as consisting of increased capacity latrine and if needed or required, cables, wiring harnesses, mounts, associated installation hardware, power supplies and other components as well as supporting equipment as agreed upon by the contractor and the government. Production kits shall meet all the requirements as stated in Paragraph 3.0 and subparagraphs.
3.9 Spares
The Government defines spares as consisting of increased capacity latrine and if needed or required, cables, wiring harnesses, mounts, associated installation hardware, power supplies and other components as well as supporting equipment as agreed upon by the contractor and the government. The contractor shall provide production lead times and Mean Time Between Failure for sustainment. Spares shall meet all the requirements as stated in Paragraph 3.0 and subparagraphs.
3.10 Marking, Packaging, and Handling
3.10.1 Item Unique Identification (IUID) Requirements
The contractor shall identify and mark the kits with IUID labeling IAW DFARS 211.274-5, Policy for Assignment of Government-assigned serial numbers. The contractor shall provide an IUID Marking Plan and an IUID Verification Report. All IUID markings will comply IAW SAE AS- 9132B, Data Matrix Quality Requirements for Parts Marking as required by MIL-STD-130N, DOD Standard Practice Identification Marking of U.S. Military Property. (A005, A006)
3.10.2 Packaging and Handling
The contractor shall package kits IAW ASTM--D3951-18, Commercial Packaging or MIL-STD-2073-1E w/ Change 4, the Standard Practice for Military Packaging. The contractor shall mark the packages for shipping and storage IAW MIL-STD-129R w/ Change 2, Military Marking for Shipment and Storage, and ship them to the address below or as cited on the individual order.
CUI Page 12 of 13
The contractor shall cover all shipping costs. The contractor shall verify that each outside shipping box displays the kit National Stock Number (NSN) and contract number clearly marked on the outside of each shipping box. In addition, the contractor shall ensure that each individual box inside the outside shipping box has the kit NSN and contract number marked on the outside of each individual box.
Government may amend shipping instructions.
FB2039
DLA Distribution Central Receiving 3301 F Ave, Bldg 506, Door 22 Tinker AFB, OK 73145 Comm: 405-855-3855
Mark for: Account 09 (NSN to be provided) (Contract # to be provided)
3.12 Diminishing Manufacturing Sources and Material Shortages
(DMSMS)
The contractor shall identify and notify the Government of all issues related to the loss or impending loss of manufacturers and suppliers, and the obsolescence of all electronic and nonelectronic parts, Non-Developmental Items (NDI), and material required for performance of this contract. The contractor shall identify and implement solutions to resolve DMSMS issues. The contractor’s DMSMS solutions shall minimize impact to the Increased Capacity Latrine’s life cycle cost and assess impacts to data rights, licenses, certification, training, testing, TOs, Operation Manuals, and sustainment. Once identified, the contractor shall report obsolescence within five (5) calendar days and mitigating alternatives will be identified within fifteen (15) calendar days to the KC-135 Program Manager.
3.13 Safety
3.13.1 Mishap Incident
Per AFI 91-202 and FAA 49CFR830.5, the contractor must immediately notify the contracting organization in the event of a Class A mishap or reportable incident involving the components while operating under contract. The contractor must cooperate with and provide access to evidence, data, and personnel requested by the Government or the Safety Investigation Board for any mishap involving the system.
3.13.2 Major Mishaps
CUI Page 13 of 13
When a major mishap ($10,000 or more) involving Government property occurs, the contractor shall immediately secure the accident scene and the damaged item until released by the accident investigative authority as designated by the contracting AFLCMC Safety Office. Such release shall be accomplished by the Administrative Contracting Officer (ACO). If the Government elects to conduct an investigation of the accident, the contractor shall cooperate fully and assist Government personnel until the investigation is completed.
3.13.3 Accident Investigation
The contractor shall include a clause in each of its subcontracts requiring subcontractor cooperation and assistance in accident reporting and investigation.
4.0 Warranty
The contractor shall provide a minimum 1-year warranty IAW FAR Part 52.246-17 Warranty of Supplies of a Noncomplex Nature.
The contractor will provide training manuals, service manual, and all associated troubleshooting documentation with the delivery of each kit. Kits will have a service call in number for emergency issues that would respond within 6 hours to allow for emergency support of a problematic system.
5.0 Contract Closeout
The contractor shall provide a contract summary report. (A008)
| 1.0 Scope |
| 2.0 Applicable Documents |
| 2.1 Department of Defense (DoD) Specifications |
| 2.2 Industry Publications |
| 2.3 Applicable Drawings and Specifications |
| 2.4 Contract Data Delivery Requirements (CDRLs) |
| 2.5 Availability of DoD Documents |
| 3.0 Requirements |
| 3.2 Program Management |
| 3.2.1 DoD Green Procurement Program |
| 3.3 Meetings |
| 3.3.1 Kick-Off Meeting |
| 3.4 Engineering |
| 3.4.1 Technical Manual Contractor Requirement |
| 3.5 Airworthiness |
| 3.6 Test & Evaluation |
| 3.7 Low Rate Production |
| 3.7.1 Physical Configuration Audit (PCA) |
| 3.7.2 First Article Kits |
| 3.8 Production Kits |
| The Government defines production kit as consisting of increased capacity latrine and if needed or required, cables, wiring harnesses, mounts, associated installation hardware, power supplies and other components as well as supporting equipment as agr... |
| 3.9 Spares |
| 3.10 Marking, Packaging, and Handling |
| 3.10.1 Item Unique Identification (IUID) Requirements |
| 3.10.2 Packaging and Handling |
| 3.12 Diminishing Manufacturing Sources and Material Shortages (DMSMS) |
| 3.13 Safety |
| 3.13.1 Mishap Incident |
| 3.13.2 Major Mishaps |
| 3.13.3 Accident Investigation |
| 4.0 Warranty |
| 5.0 Contract Closeout |