AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
JLSUVY
2. AMENDMENT/MODIFICATION NO.
FA8105-22-R-0006-0001
3. EFFECTIVE DATE
10 JUN 2022
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO (If applicable)
FA810522R0001
6. ISSUED BY CODE
DEPARTMENT OF THE AIR FORCE, AFLCMC WLTK
3001 STAFF DR STE 2AI 85A
TINKER AFB OK 73145-3303
BUYER: Diana Kennedy/AFLCMC/WLT diana.kennedy@us.af.mil Phone: (405) 736- 1863
7. ADMINISTERED BY (If other than item 6) CODEFA8105
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
X
9A. AMENDMENT OF SOLICITATION NO.
FA810522R0006
9B. DATED (SEE ITEM 11)
13-MAY-2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods. ( a ) By completing Items 8 and 15, and returning copies of the amendment; ( b ) By acknowledging receipt of this amendment on each copy of the offer submitted; or ( c ) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
FMS REQUIREMENT
Routine
15A. NAME AND TITLE OF SIGNER (Type or print)
15B. CONTRACTOR/OFFEROR
BY ________________________________________________________
(Signature of person authorized to sign)
15C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16B. UNITED STATES OF AMERICA
BY ____________________________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
FACILITY CODE
NSN 7540-01-152-8070
PREVIOUS EDITION UNUSABLE
30-105 STANDARD FORM 30 (REV. 10-83)
PRESCRIBED BY GSA
FAR (48 CFR) 53.243
X
X X
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
FA8105-22-R-0006-0001
Continuation of block 14. DESCRIPTION OF AMENDMENT/MODIFICATION
The purpose of the amendment is as follows:
FIRST: The attached Performance Work Statement (PWS), dated 31 May 2022 is hereby incorporated and supercedes the previous edition.
SECOND: The contract data requirement list attachments (CDRL) DD 1423 are hereby revised and suprecedes the previous edition.
THIRD: Contract line item numbers (CLINS) description were updated.
FOURTH: Option I thru Option IV contract line item numbers (CLINS) are expect to be negotiated at a later date.
FIFTH: All other terms and conditions remain unchanged.
PART I - THE SCHEDULE
SECTION B
SUPPLIES OR SERVICES AND PRICES/COSTS
Assumptions
The contractor shall provide Services as defined in the attached Performance Work Statement to support C/KC135 Avionics Sustaining Engineering Services (ASES) with a twoyear basic contract period, four (4) twoyear options. Options to extend the term of contract may be awarded at the Governments discretion.
1) Ordering Period: (Basic period to begin upon date of contract award execution) (Option periods awarded at the Governments discretion)
Basic Estimated to be 03 Apr 23 through 02 Apr 25 Option 1 Estimated to be 03 Apr 25 through 02 Apr 27 Option 2 Estimated to be 03 Apr 27 through 02 Apr 29 Option 3 Estimated to be 03 Apr 29 through 02 Apr 31 Option 4 Estimated to be 03 Apr 31 through 02 Apr 33
2) The services and prototyping the government seeks are highly specialized to C/KC135 aircraft. The contractor must be capable of sustaining avionics systems. Rockwell Collins (also known as Collins Aerospace) is the original manufacture and integrator for over 95% of the C/KC135 avionics including the Communication Navigation Surveillance/Air Traffic Management (CNS/ATM), Global Air Traffic Management (GATM) and Pacer CRAG (Compass, Radar and GPS) avionics modification that provide for an integrated avionics solution on C/KC135 aircraft.
3) The contract line item number (CLIN) structure allows for multiple task assignments to be awarded from single proposals and allows for multiple deliverables on an individual order without use of subcontract line item numbers (SubCLINs) to facilitate multiple funding appropriations when required.
The CLIN structure is not sequentially numbers, but instead allows for future CLINs if needed.
4) The minimum basic order will be for one month of CLIN 0002 Recurring Engineering Support.
5) Notice to Offeror(s)/Supplier(s): Funds are not presently available for this effort. No award will be made under this solicitation until funds are available for the minimum order. The Government reserves the right to cancel this solicitation, either before or after the closing date for receipt of proposals. In the event the Government cancels this request, the Government has no obligation to reimburse for any costs.
6) Federal Acquisition Regulation (FAR) clause 52.2178, Option to Extend Services: If FAR 52.2178, Option to Extend Services, is exercised, within the terms of the clause stated herein, the basic contract prices specified in the existing contract ordering period immediately preceding the exercise of FAR
52.2178 will apply to all task orders issued under the Option to Extend Services. The CLIN structure for continued performance of services under the option will be incorporated via modification at the time of option exercise.
7.) CONTRACT APPEARANCE: The resulting contract may be awarded using a different contract writing system which may result in a different format or appearance. This contract may also be bilaterally reissued after award at the exercise of an option with a different format or appearance.
Task Order Proposal Preparation Item No.
Firm Fixed Price Quantity U/I Unit Price Estimated Total Price TBN
LO To be Negotiated
CLIN ACRN ACRN Total
0001 AA
R425 The contractor will perform activities on behalf of the KC135 Avionic Sustainment Engineering Service (ASES) Performance Work Statement (PWS). These activities include incorporating section 3.1.1.5. This is expected to be used with contract line item numbers (CLIN) 00100068.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Class I ODS Substance Application/Use Quantity Prohibited IAW PWS Paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
A TBD LO TBC
Proposed Delivery
A TBD LO
Recurring Engineering Support OnSite Liaison Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
24 MO
CLIN ACRN ACRN Total
Recurring Engineering Support OnSite Liaison
0002 AA
R425 Recurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS Section 3.2, 3.3, subsection 3.3.1 (paragraphs 3.3.1.1 thru 3.3.1.4.4) and 3.3.2 (paragraphs 3.3.2.1 thru 3.3.2.9). This CLIN will include reoccurring technical support in the PWS Table 3.3 for Category A.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Wide Area Work Flow (WAWF) Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
MO TBC
Proposed Delivery
MO
Recurring Engineering Support Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Estimated Total Price
LO To be Negotiated
CLIN ACRN ACRN Total
0003 AA
R425 Recurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS.This line item is reserved for future use to be negotiated.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
Recurring Engineering Support
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
Recurring Engineering Support Item No.
Cost Plus Incentive Fee Estimated Quantity
U/I Est Target Cost Target Fee Total Estimated Cost
LO To be Negotiated
CLIN ACRN ACRN Total
0004 AA
R425 Recurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS.This line item is reserved for future use to be negotiated.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Recurring Engineering Support Proposed Period of Performance
LO
NonRecurring Engineering Service Requirements Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
1 LO To be Negotiated
CLIN ACRN ACRN Total
0010 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
In accordance with (IAW) with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW FAR Part 46 and its supplements.
The total price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
1 LO To be Negotiated
CLIN ACRN ACRN Total
0011 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW FAR Part 46 and its supplements.
The total price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of
Informational Only
NonRecurring Engineering Service Requirements Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
1 LO To be Negotiated
CLIN ACRN ACRN Total
0020 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The target price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohoibited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
NonRecurring Engineering Service Requirements Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
1 LO To be Negotiated
CLIN ACRN ACRN Total
0021 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The target price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
Cost Plus Fixed Fee
NonRecurring Engineering Service Requirements Estimated Quantity
U/I Estimated Cost Fixed Fee Est Total Cost
1 LO To be Negotiated
CLIN ACRN ACRN Total
0030 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The estimated (Est) total cost for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
Cost Plus Fixed Fee Estimated Quantity
U/I Estimated Cost Fixed Fee Est Total Cost
NonRecurring Engineering Service Requirements 1 LO To be Negotiated
CLIN ACRN ACRN Total
0031 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The estimated (Est) total cost for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohibited IAW PWS Paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
To be negotiated on the task assignment.
NonRecurring Engineering Service Requirements Item No.
Cost Plus Incentive Fee Estimated
U/I Est Target Cost Target Fee Total Estimated Cost
NonRecurring Engineering Service Requirements 1 LO To be Negotiated
CLIN ACRN ACRN Total
0040 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The total estimated cost for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS Paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
Cost Plus Incentive Fee Estimated Quantity
U/I Est Target Cost Target Fee Total Estimated Cost
1 LO To be Negotiated
NonRecurring Engineering Service Requirements
0041 AA
R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4 NonRecurring Engineering Services Requirements and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The total estimated cost for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
NonRecurring Engineering Service Requirements Item No.
Time & Material Estimated Quantity
U/I Fixed Rate Ceiling Price
1 LO To be Negotiated
0050 AA
NonRecurring Engineering Service Requirements Title: Labor Categories R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4.1 and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The Ceiling Price will be determined on the task order.
This CLIN is intended to use if an occurence should occur as an emergency situation under PWS paragraph 3.4.1 Aircraft Mishap Incident Investigations.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LI Y
NonRecurring Engineering Service Requirements Item No.
Time & Material Estimated Quantity
U/I Fixed Rate Ceiling Price
LO To be Negotiated
CLIN ACRN ACRN Total
0051 AA
Title: Labor Category R425 NonRecurring Engineering Services (USAF) The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4.1 and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW with FAR Part 46 and its supplements.
The Ceiling Price will be determined on the task order.
This CLIN is intended to use if an occurrence should occur as an emergency situation under PWS paragraph 3.4.1 Aircraft Mishap Incident Investigations.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required
LO TBC
Proposed Delivery
LO
Test Procedures Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
1 EA To be Negotiated
CLIN ACRN ACRN Total
0060 AA
AD24
The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.4.6 as directed with each individual task assignment.
Quantity Variance (Over Percent): (Under Percent):
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohoibited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
EA TBC
Proposed Delivery
EA
Technical Support Modification Requirements Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
1 LO
Technical Support Modification Requirements
0061 AA
R425 Technical Order Sustainment Contractor shall perform in accordance with performance work Statement (PWS) paragraphs as follows:3.3.1.4, 3.3.2.1.8,
3.2.11.1 and Table 3.3 Technical Order (T.O) Category B.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
Technical Support (Nonrecurring Engineering) Requirements Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
1 LO
CLIN ACRN ACRN Total
0062 AA
R426 Nonrecurring Engineering Services Contractor shall perform in accordance with each task order and the C/KC135 ASES performance work Statement (PWS) paragraphs as follows:3.3.1.4, 3.3.2.1.8, 3.2.11.1 and table 3.3 Technical Order (T.O) Category A.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohibited IAW PWS paragraph 3.2.9
Technical Support (Nonrecurring Engineering) Requirements Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
Technical Support (Nonrecurring Engineering) Requirements Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
1 LO To be Negotiated
CLIN ACRN ACRN Total
0063 AA
R426 Contractor shall perform in accordance with each task order and the C/KC135 ASES performance work Statement (PWS) paragraphs as follows:3.3.1.4, 3.3.2.1.8, 3.2.11.1 and table 3.3 Technical Order (T.O) Category B.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed
Technical Support (Nonrecurring Engineering) Requirements Item No.
Cost Plus Fixed Fee Quantity U/I Estimated Cost Target Cost % Est Total Cost
EA % To be Negotiated
CLIN ACRN ACRN Total
0064 AA
R426 Contractor shall perform in accordance with each task order and the C/KC135 ASES performance work Statement (PWS) paragraphs as follows:3.3.1.4, 3.3.2.1.8, 3.2.11.1 and table 3.3 Technical Order (T.O) Category D.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
EA TBC
Proposed Delivery
EA
Technical Support (Nonrecurring Engineering) Requirements Item No.
Cost Plus Incentive Fee Estimated Quantity
U/I Est Target Cost Target Fee Total Estimated Cost
LO To be Negotiated
CLIN ACRN ACRN Total
0065 AA
R426 Contractor shall perform in accordance with each task order and the C/KC135 ASES performance work Statement (PWS) paragraphs as follows:3.3.1.4, 3.3.2.1.8, 3.2.11.1 and table 3.3 Technical Order (T.O) Category D.
Limitations of Liability: Other Than High Value Item
Technical Support (Nonrecurring Engineering) Requirements
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
Data Item No.
To Be Negotiated Quantity U/I Unit Price
LO TBN
DATA
Data Contractor shall provide the data identified in Section J, Exhibit A in accordance with the Performance Work Statement or Task Assignment hereof. The Government shall have unlimited rights to all developed software, test materials, documents, notes, records, and software documentation meeting the criteria specified in Defense Federal Acquisition Regulation Supplement (DFARS) 252.2277013, 252.2277014 and 252.2277015. The costs associated with data are included in CLINS.
Exhibit: A Class I ODS Substance Application/Use Quantity Prohobitied IAW PWS paragraph 3.2.9
Material Item No.
Cost Reimbursement No Fee Estimated Quantity
U/I Est Unit Cost Total Estimated Cost
1 LO To be Negotiated
CLIN ACRN ACRN Total
0067 AA
NSN: 1680
Material is for supporting Prototypes. IAW PWS 3.3.2.1.8 prototype efforts will be addressed in individual task assignments.
Material
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Buy American Act/Balance of Payments Program
Transportation From Continental United States CONUS (CONUS) Sources
TYPE / SHIP TO CODE F.O.B.
A TBD ORIGIN
Class I ODS Substance Application/Use Quantity
NONE
Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
A TBD LO TBC
Proposed Delivery
A TBD LO
Travel Item No.
Cost Reimbursement No Fee Quantity U/I Est Unit Cost Total Estimated Cost
1 LO
CLIN ACRN ACRN Total
0068 AA
TRAV
Travel (Base) Informational IAW with FAR Part 31, Joint Travel Regulation (JTR), 3.3.1.1 bullet h, PWS paragraph 3.3.1.2 bullet g, 6.2 and each individual task assignment and ASES PWS. Travel request must be submitted to the cognate COR for the task order and approved by the Procurement Contracting Officer (PCO)/Administrative Contracting Officer (ACO) before travel begins and is subject to the limitation of cost 52.23220.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Travel Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
Agile Software Proposal Preparation Item No.
Firm Fixed Price Quantity U/I Unit Price Estimated Total Price TBN
LO To be Negotiated
CLIN ACRN ACRN Total
0076 AA
R425 Agile Software Proposal Preparation The contractor will perform activities on behalf of the KC135 Avionic Sustainment Engineering Service (ASES) Performance Work Statement (PWS). These activities include incorporating section 3.1.1.5. This is expected to be used with contract line item numbers (CLIN) 00770082, in the event a task assignment is requested.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of
Agile Software Development Item No.
Fixed Price Level of Effort Estimated Quantity
U/I Estimated Unit Price Estimated Total Price
1 LO
CLIN ACRN ACRN Total
0077 AA
R425 Agile Software Development IThe contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.3.2.10, 3.3.2.10.3, and 3.3.2.10.4.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Certificate of Conformance Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
Agile Software Review Item No.
Fixed Price Level of Effort Estimated Quantity
U/I Estimated Unit Price Estimated Total Price
1 LO
CLIN ACRN ACRN Total
0078 AA
R425 Agile Software Reviews The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section
3.3.2.10.5 and 3.3.2.10.5.2.
Agile Software Review
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Certificate of Conformance Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
Agile Software Release Cycle Item No.
Cost Plus Fixed Fee Estimated Quantity
U/I Estimated Cost Fixed Fee Est Total Cost
1 LO
CLIN ACRN ACRN Total
0079 AA
R425 Agile Software Release Cycle The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include in PWS section 3.3.2.10.6.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of
Agile Software Release Cycle Proposed Period of Performance
LO
Agile Design Documentation Item No.
Cost Plus Fixed Fee Estimated Quantity
U/I Estimated Cost Fixed Fee Est Total Cost
LO
CLIN ACRN ACRN Total
0080 AA
R425 Agile Design Documentation The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.3.2.10.5.2.1.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
Agile Sprint Review Item No.
Cost Plus Incentive Fee Estimated
U/I Est Target Cost Target Fee Total Estimated Cost
Agile Sprint Review
1 LO
CLIN ACRN ACRN Total
0081 AA
R425 Agile Sprint Reviews The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section
3.3.2.10.5 and 3.3.2.10.5.1.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
Agile Test Item No.
Cost Plus Fixed Fee Estimated Quantity
U/I Estimated Cost Fixed Fee Est Total Cost
1 LO
CLIN ACRN ACRN Total
0082 AA
R425 Test Procedures The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS section 3.3.2.10.1.
Agile Test
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
FMS Task Order Proposal Preparation Item No.
Firm Fixed Price Quantity U/I Unit Price Estimated Total Price TBN
LO To be Negotiated
CLIN ACRN ACRN Total
0101 AA
R425 FMS Task Assignment B&P The contractor will perform activities on the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include incorporating section 3.1.1.5. This is expected to be used with contract line item numbers (CLIN) 01060110.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Foreign Military Sales :FMS Case:
Prohobited IAW PWS paragraph 3.2.9
FMS Task Order Proposal Preparation Type / Ship To Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Delivery
LO TBC
Proposed Delivery
LO
FMS Recurring Engineering Support Item No.
Firm Fixed Price Quantity U/I Unit Price Estimated Total Price 1 LO To be Negotiated
Turkey
France
EA
Chile
EA
CLIN ACRN ACRN Total
0102 AA
R425 FMS Recurring Engineering Services Requirements The contractor will perform activities on behalf of the KC135 ASES PWS. These activities include incorporating PWS Section 3.2, 3.3, subsection 3.3.1 (paragraphs 3.3.1.1 thru 3.3.1.4.4) and 3.3.2 (paragraphs 3.3.2.1 thru 3.3.2.9). This CLIN will include reoccurring technical support in the PWS Table 3.3 for Category A.
FMS requirements will include Letter of Offer and Acceptance with amendments as appropriate. Each Country will be assigned a SubCLIN when funding becomes available.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Foreign Military Sales :FMS Case:
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of
Proposed Period of Performance
LO
FMS Recurring Engineering Support Item No.
Cost Plus Incentive Fee Estimated Quantity
U/I Est Target Cost Target Fee Total Estimated Cost
1 LO To be Negotiated
Turkey
EA
France
EA
Chile
EA
CLIN ACRN ACRN Total
0103 AA
R425 FMS Recurring Engineering Services Requirement The contractor will perform activities on behalf of the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include the PWS section 3.3.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Foreign Military Sales :FMS Case:
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of
FMS Recurring Engineering Support Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
1 LO To be Negotiated
Turkey
EA
France
EA
Chile
EA
CLIN ACRN ACRN Total
0104 AA
R425 FMS Recurring Engineering Services Requirement The contractor will perform activities on behalf of the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include the PWS section 3.3.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Foreign Military Sales :FMS Case:
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
FMS Recurring Engineering Support Item No.
Cost Plus Fixed Fee Estimated
U/I Estimated Cost Fixed Fee Est Total Cost
FMS Recurring Engineering Support
1 LO
Turkey
EA
France
EA
Chile
EA
CLIN ACRN ACRN Total
0105 AA
R425 FMS Recurring Engineering Services Requirement The contractor will perform activities on behalf of the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include the PWS section 3.3.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO 90012008 2008
Foreign Military Sales :FMS Case:
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
FMS NonRecurring Engineering Service Requirements Item No.
Firm Fixed Price Estimated Quantity
U/I Unit Price Estimated Total Price
1 LO To be Negotiated
Turkey
EA
France
EA
FMS NonRecurring Engineering Service Requirements Chile
EA
CLIN ACRN ACRN Total
0106 AA
R425 FMS NonRecurring Engineering Services Requirement The contractor will perform activities on behalf of the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include incorporating PWS section 3.4 and individual order documents.
In accordance with (IAW) with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW FAR Part 46 and its supplements.
The total price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Destination Acceptance: Destination Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Standard Inspection Foreign Military Sales :FMS Case:
Class I ODS Substance Application/Use Quantity Prohobited IAW PWS paragraph 3.2.9 Place of Perf Quantity (U/I) To be cited on individual orders issued hereunder
_ Req No / Pri
Required Period of Performance
LO TBC
Proposed Period of Performance
LO
FMS NonRecurring Engineering Services Requirements Item No.
Incentive Firm Target Estimated Quantity
U/I Target Cost Target Profit Target Price
Turkey
FMS NonRecurring Engineering Services Requirements
EA
France
EA
Chile
EA
CLIN ACRN ACRN Total
0107 AA
R425 FMS NonRecurring Engineering Services Requirement The contractor will perform activities on behalf of the United States of America Letter of Offer and Acceptance (LOA) and KC135 ASES PWS. These activities include incorporating PWS section 3.4 and individual order documents.
IAW with PWS 3.1.1 Task assignment will be used to authorize nonrecurring engineering Support Services under the PWS. A Task Assignment is a Legacy Tanker Division developed form that identifies the problem, defines the work to be accomplished, specifies due dates, priorities, and provides the funding information for the support being acquired.
Quality Standard, inspection and acceptance must be cited on the order IAW FAR Part 46 and its supplements.
The target price for task assignment will be negotiated for each task order.
Limitations of Liability: Other Than High Value Item
Inspection: Origin Acceptance: Origin Inspection/Acceptance Report: Receiving Report Required Quality Assurance: Higher Level Contract Quality Requirements The Contractor shall comply with the standard(s) listed below. (if more than one, check the appropriate standard.)
Title Number Date Tailoring
ISO…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .