This statement of work outlines requirements for the supply of Large Clearance Blade Assemblies to support rapid explosive hazard mitigation on airfields. The contractor shall supply up to 100 blade assemblies built to specifications using government-provided metal alloys and attaching to equipment via ISO couplers. Blades must pass first article and conformance inspections. The contractor shall develop customized packaging for worldwide shipment, and is responsible for loading, offloading, and addressing any shipping damages. The contractor shall provide status reports, safety data sheets, production schedules, and ship completed blades within 180 days of order to multiple military installations globally. Technical support is available from Air Force Civil Engineer Center personnel.

View the file

Other files for this federal contract opportunity

Other files attached to Rapid Explosive Hazard Mitigation (REHM) Large Clearance Blade Assembly (L-CBA), newest first.
File Type Posted
FA805121R3010 Attachment 4 PPI submission form.docx DOCX document
FA805121R3010 Attachment 1 LCBA SOW 20 July 2021.docx DOCX document
Solicitation - FA805121R3010.pdf PDF
FA805121R3010 Attachment 5 Subcontractor Consent form.docx DOCX document
FA805121R3010 Attachment 3 LCBA CLIN Price Sheet.xlsx XLSX spreadsheet
FA805121R3010 Attachment 2 Combined LCBA Design Specifications - 20210511.pdf PDF
Combined LCBA Design Specifications - 20210511.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Air Force Civil Engineer Center Rapid Explosive Hazard Mitigation (REHM) Large Clearance Blade Assembly (L-CBA) Date: 30 June 2021

1.0 SCOPE. This Statement of Work (SOW) defines the effort associated with the supply of Large Clearance Blade Assemblies (L-CBA) to mount on armored front end loaders.

2.0 BACKGROUND. The objective of the Airfield Damage Repair (ADR) Modernization Program is to develop capabilities to rapidly assess damage to airfield pavements, mitigate unexploded ordnance from the airfield pavement, and repair damaged airfield pavements for the full spectrum of operational scenarios including base recovery after an attack, expedient repairs at deployed locations, and sustainment of operating surfaces at forward operating bases. In all of these scenarios, time is a critical factor, either to restore flying operations or minimize airfield closures. The L-CBA is an armored blade required to safely push ordnance off airfield surfaces using an Armored Front End Loader. Air Force Civil Engineering Center (AFCEC)/Acquisition and Requirements Office (CXA) has designed and tested an effective blueprint for this capability.

3.0 REQUIREMENTS. The work required by this contract shall be performed in accordance with standards and formats identified within this SOW. The L-CBA’s must be:

a. Built to the performance specifications

b. Built with specified metals

c. Incorporate International Organization for Standardization (ISO) coupler for attachment to Government armored front end loaders

d. Comply with specified schedule, data items, and other deliverables

e. Shipped to specified destinations

3.1 Product/Performance Requirements.

3.1.1 The contractor shall supply and deliver REHM L-CBAs, to selected worldwide locations.

Locations

Tyndall AFB, Florida

Guam

Korea

Japan

Qatar

Kuwait

United Arab Emirates

Oman

Italy

Germany

United Kingdom

Spain

3.1.2 L-CBA(s) must be manufactured in accordance with the attached technical data package specification design drawings (Attachment 1, Combined LCBA Design Specifications - 20210511). Paint components prior to assembly and touch up L-CBA once assembled.

3.2 Specified metals. Built with Government specified metal alloys

a. An Astralloy-V plate

b. A514 Steel Plate

c. A36 Steel angles

d. A500 Tubing

3.3 Comply with ISO Standard. The L-CBA must attach to Government armored front end loader, NSN: 3805-01-686-4441 using International Organization for Standardization (ISO) 23727:2009 hydraulic quick coupler with cab mounted hydraulic attachment pressure release function. Couplers will be delivered under separate contract with the armored front end loader.

3.4 Schedule, Data Items, and Other Deliverables.

3.4.1.1 Schedule For Fully Procured REHM L-CBAs. The contractor shall commence work immediately After Receipt of each Order (ARO). The contractor shall provide production schedule plans within 90 days and first article for review and approval not later than 160 calendar days ARO. Once an L-CBA order is assembled the contractor shall submit an element for review and approval, and once approved, shall complete shipment of procured additional L-CBAs in accordance with Table 1. The Government requires up to a maximum of 14 calendar days to inspect and approve the submissions.

3.4.1.2 Inspections Locations. The Government may provide on-site inspections based on the contractor’s production completion schedules. Inspections will be completed or waived by the Government prior to any L-CBA and/or items shipped. Inspections may take up to one work day to complete, per L-CBA; and include inventory of all end items and packaging. The contractor shall coordinate with the AFCEC Technical Advisors identified in Paragraph 3.4.5.1 for scheduling all inspections.

3.4.1.3 Inspection Details. Specific inspection details will be outlined in each Delivery Order issued against the contract.

3.4.1.4 Data Items. The contractor shall submit complete Safety Data Sheets on hazardous materials (if applicable) with the L-CBAs no later than 30 calendar days ARO to the Technical Advisors identified in Paragraph 3.4.5.

3.4.1.5 Tool Kit. Each L-CBA will be delivered with an accessory tool kit secured in the storage container. Tool Kits will include:

a. Milwaukee Cordless Impact Wrench, Model Number 2962P-22, ½” Square Drive, 54275A35

b. 6 Point Impact Socket, Deep, ½” Square Drive, 1-5/16” Size, 3-1/2” Long, 5549A146

c. 6 Point Deep Socket, ½” Square Drive, 15/16” Size, 5545A288

d. 12-Point Box Opening Combination Wrench with Dull Chrome-Plated Finish, 1-5/16” Size, 16-3/4” Overall Length, 5441A35

e. 12-Point Box Opening Combination Wrench with Dull Chrome-Plated Finish, 15/16” Size, 13-1/4” Overall Length, 5441A28

f. 12-Point Box Opening Combination Wrench with Dull Chrome-Plated Finish, ¼” Size, 4-7/8” Overall Length, 5441A11

g. Electrical-Insulating Socket Extension, 5-1/2” Long, 5556A23

h. Tool Bag or box to contain above tools

3.4.1.6 Weekly Status Report. The contractor shall provide, per delivery order, weekly status of shipped, delivered and delivery schedules to Technical Advisors outlined in Paragraph 3.4.5. The first report shall be due seven (7) calendar days ARO and no later than 1200 CST every Monday thereafter until all deliveries are completed.

Table 1. Production and Shipment timelines

Action
REHM L-CBAs (#Days ARO)
Submit status reports to technical advisors
Weekly
Submit Safety Data Sheets on hazardous materials to technical advisors
30
Provide production completion schedule
90
Produce physical configuration audit first article of L-CBA for Government inspection and approval
160
Incorporate revisions identified by Government inspection
*
Complete shipment of L-CBAs per Delivery Order
180
Complete shipment of partial L-CBAs or individual items per delivery Order
*

*Will be coordinated per delivery order

3.4.2 Packaging. The contractor shall develop a customized packaging solution for worldwide shipment and protection of the blade from the elements. The L-CBA estimated weight is 13,000 lbs or less. Packaging shall:

a. Be designed to allow pick up and removal of the blade from the packaging solution with a Caterpillar Model 966H armored loader (e.g. custom crating or acquiring and customizing ISO side opening shipping containers)

b. Be designed to allow replacement of the blade into the packaging solution with a Caterpillar Model 966H armored loader

b. Protect the blade from inclement weather (rain, sleet, snow)

c. Be capable of being shipped by land, sea, and air

d. Include tie down points to secure the blade and tool kit

3.4.3 Shipment. Ship to specified worldwide destinations specified in para 3.1.1.

3.4.3.1 First article inspection. Obtain Government physical configuration audit blade assembly inspection prior to full rate production and shipment L-CBA(s).

3.4.3.2 Loading and unloading. The Contractor shall load and unload all REHM L-CBAs, at their origin and at each destination (door to door). The contractor shall provide all equipment, manpower, tools, and vehicles to perform all product loading and unloading. The contractor shall offload all REHM L-CBAs in their packaged shipping/environmental protection containers, from shipping truck/containers at destinations and deliver to the installation final location per each Point of Contact (POC).

3.4.3.3 Deliveries. Deliveries under this contact are to Main Operating Base (MOB) or Forward Operating Base (FOB) destinations. The contractor shall employ packaging and shipping techniques to preclude any damage from rough transport. The contractor shall be responsible for expenditures associated with damage incurred during shipping to include on-site repairs or replacement of damaged items. The contractor shall provide all product loading at the origin and all product offloading at the destination (door to door) as outlined above.

3.4.3.4 ISO Container Serial #s (IF APPLICABLE TO THE PACKAGING SOLUTION). The Government will provide applicable container control numbers (USFU #s) for all purchased ISO containers and track all information in the Joint Container Management System (JCMS). Contractor shall follow the specifications in the Defense Transportation Regulation (DTR) 4500.9R – Part VI, Chapter 603, dated February 2020, (Ref: https://www.ustranscom.mil/dtr/part-vi/dtr_part_vi_603.pdf ). The contractor shall contact the Technical Advisors identified in Paragraph 3.4.5.3. for assistance.

3.4.3.5 Destination POC. The contractor shall contact the applicable installation POC prior to shipment to give the installation a formal notification of an upcoming delivery and to verify the delivery address. The POCs and shipping addresses will be identified in each Delivery Order issued against the contract. The contractor shall also provide product and/or delivery schedule information to specified Technical Advisors in Paragraph 3.4.5.

3.4.3.6 External Tracking. The contractor shall make available to the Government all automated tracking information employed by the shipping agencies (i.e., web-based search engines, posted manufacture spreadsheets, etc.).

3.4.3.7 Shipping Cost. Firm fixed pricing will be negotiated on an order by order basis in accordance with the contract ordering procedures.

3.4.4 REHM L-CBA Components Verification

3.4.4.1 Classification of Inspections of REHM L-CBAs components. The inspection requirements specified herein are classified as follows:

· First article inspection.

· Conformance inspection.

3.4.4.2 First Article Inspection. The purpose of this inspection shall be to determine REHM L-CBA’S conformity with the drawing attachment and vendor proposed plans Acceptance of the First Article inspection shall not constitute a waiver by the Government of its rights under the provisions contract document or relieve the manufacturer from any requirements defined in this specification. Failure to meet inspection criteria shall constitute cause for rejection.

3.4.4.3 Conformance Inspection. The conformance inspection shall be conducted on all REHM L-CBAs prior to the vendor shipping the REHM L-CBAs.

3.4.5 AFCEC Technical Advisors

3.4.5.1 Program Manager

Mr. John Stewart john.stewart.38@us.af.mil 850-283-6191

3.4.5.2 Research Engineer (Drawings and Construction)

Mr. Sean Cloud sean.cloud@us.af.mil 850-283-6170

3.4.5.3 Technical Specifications

Mr. Robert Dalton robert.dalton.11.ctr@us.af.mil 850-283-6647