Q&A2,_FA8051-17-R-3017,_Skid_Units.pdf
PDF 35 KB Posted
- Attached to
- Skid Units Federal contract opportunity
- Solicitation number
- FA8051-17-R-3017
About this file
Additional responses to offerers questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q&A,_FA8051-17-R-3017,_Skid_Units.pdf | ||
| Attachment_2_-_Government_Specifications.pdf | ||
| Attachment_3_-_CLIN_Price_Sheet.xlsx | XLSX spreadsheet | |
| Attachment_2_-_Government_Specifications.pdf | ||
| Attachment_1_-_Provision_and_Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: FA8051-17-R-3017 Description: Skid Units
Question # Question Response
Fire pump enclosure:
* Are you looking for an entirely enclosed pumping system with full control panel? Or do you just want the engine/pump enclosed for noise dampening?
* Define ‘Auxiliary fire pump’? Assuming there is only 1 pump on each system.
Looking for noise dampening.
Only 1 pump unless another is used for the Class A foam system.
Front of Body discharge through the tank:
* Need more detail on the finishing for these (whip lines, turret, just caped, etc.)?
Capped
Tank Refill:
* Water tank fill and cooling line section and ‘pump to tank connection’ sections are both for a tank refill. Are both needed? (1” and 1.5”)
Cooling line could be a separate 1" line, however, if the 1.5" intake can do the same function based on design then that is sufficient.
Protective railing:
* Please provide dimensions off of bed for this?
Sufficient to protect installed components.
Rear slide out tray:
* Will roller bearing side mount slides be acceptable here?
Yes
Door ajar light:
* Is this for all compartment doors?
Yes
Automatic compartment door light switch:
* Do you mean interior compartment lights or are you requesting an exterior light that gives light to compartment?
Interior compartment lights.
Electronic Siren:
* Please specify a preferred brand/model
Whelen or similar.
2-5 gallon water cooler:
* Is this potable drinking water? Standard water cooler with spigot?
Potable water, standard cooler with spigot.
Chassis Prep:
* Is chassis prep done before Body/skid manufacturer receives chassis?
*If not:
-What type of underbody skid plating? Welded to frame or removable?
-Winch power from factory auxiliary circuits? What amperage are circuits capable of? Controls inside cab?
Most likely no chassis prep before delivery.
Any added components must be removable.
Yes, winch power from factory circuits. The exact amperage is not known. Standard winch controls outside of cab.
Who handles shipping of chassis to manufacturer? The Government will handle shipping of chassis.
Contractor Questions
Question # Question Response
Please provide a drawing or sketch of expected bed layout (compartments, tank, pump, reel, steps, railing, control panel, etc.)?
The Government does not have a sketch available but typical flat bed skid units are expected.
Sheet1