Questions and Answers to Solicitation FA706024RPR01_B18 Cooling Tower.docx
DOCX document 17 KB Posted
- Attached to
- B18 Cooling Tower Repair
- Solicitation number
- FA706024RPR01
About this file
This document contains the Questions and Answers to Solicitation FA706024RPR01 for the B18 Cooling Tower Repair contract opportunity. The key details are:
The contractor must perform a full preventative maintenance service on the one cooling tower, which will be a separate line item. The contractor is also requested to provide an add alternate option for bearing and shaft replacement if needed. There are no work hour restrictions, and no weight restrictions for the concrete pad that a crane would use. The contractor recommends adding a requirement for legionella testing by an accredited lab prior to the repair work, and for the contractor to provide a quote for any necessary remediation if legionella is found. The agency agrees to include the legionella test requirement in the Performance Work Statement. Overall, the contract is for the replacement of the motor for the chiller plant cooling tower to ensure cooling capabilities for 26 facilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - B18 Cooling Tower_PWS updated Final.docx | DOCX document | |
| Attachment 1 - B18 Cooling Tower_PWS Final.docx | DOCX document | |
| Combined Synopsis Solicitation - B-18 Cooling Towers Signed.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Received Questions and Answers to Solicitation FA706024RPR01
| Questions |
| Answers |
| 1 |
| Confirming that along with motor/ belt replacement that a full PM service on just the 1 tower will be done at the same time? And will that be a separate line item? |
| We would like the PM service on all the towers. Same line item. |
| 2 |
| Would you like an add alternative option for bearings/ shaft in the event they are worn or damaged. |
| Yes. |
| 3 |
| What are work hours? |
| Work hours are flexible, so whatever hours you believe you require to complete the work can be accommodated for. |
| 4 |
| Any weight restrictions for the concrete pad outside for crane? |
| No weight restrictions. |
| 5 |
| We recommend the following changes to the Performance Work Statement (PWS) |
The Contractor Must perform Legionella Test Per GSA Guidelines for Each Cooling Tower Before the Start of the Maintenance and Repair Work. Legionella Test must be performed by an Accredited Lab. If Legionella is Found in any of the Cooling Towers the Contractor should provide a (Fair and Reasonable) Quote for Remediation by a Qualified Contractor.
The Contractor Must Perform Manufacturer Recommended Annual Services for All Cooling Towers.
We agree with the recommendation for a legionella test. See updated verbiage under Section II of the PWS.