Q_A - Amendment 1 - FA706024Q0018.pdf

PDF 579 KB Posted

Attached to
JBAB - Scoreboard for Youth Center Federal contract opportunity
Solicitation number
FA706024Q0018
Issued by
Department of the Air Force Headquarters District Washington

About this file

This document is a set of Questions and Answers regarding Amendment 1 to Solicitation FA706024Q0018 for the JBAB - Scoreboard for Youth Center requirement. The key details are:

The solicitation is for a contractor to provide and install one scoreboard, including a non-illuminated sign, to be mounted on an existing support structure. The existing structure has 6" x 6" steel I-beam columns spaced 10' apart, with rails at 7'5" and 14'6" from the ground. The footer size is 46-1/2" x 46-1/2", but the depth is unknown. Proposals should indicate the estimated completion time. Power is available within 5' of the new scoreboard location. Equipment access to the site is available via a paved path. Additional photos of the existing structure have been added to the Statement of Work. All questions were due on July 16, 2024 by 2PM EDT, and all final offers are due on July 18, 2024 by 2PM EDT.

View the file

Other files for this federal contract opportunity

Other files attached to JBAB - Scoreboard for Youth Center, newest first.
File Type Posted
SOW - Scoreboard w Installation - Revision 4 Dated 16JUL24.pdf PDF
JBAB LL _Logo.png PNG image
WG 15-4281 11APR24.pdf PDF
Solicitation - FA706024Q0018.pdf PDF
Scoreboard Drawing.png PNG image

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF DEFENSE

JOINT BASE ANACOSTIA-BOLLING

& 11TH WING (AFDW)

WASHINGTON DC

READINESS – PARTNERSHIPS – HERITAGE

16 July 2024

MEMORANDUM FOR FA706024Q0018 - JBAB - Scoreboard for Youth Center

FROM: 11 CONS/PKA

SUBJECT: Questions and Answers

1. What type, size, and spacing are the existing columns?

a. The existing columns are 6” x 6” Steel I-beams.

b. The two columns are spaced 10’6” apart (outside to outside), 10’ ft center to center.

c. The existing columns are approximately 17 feet tall.

d. The bottom horizontal rail is 7’-5 ¼” from the ground.

e. The next upper rail is 7’-1 ½” higher than the bottom.

f. There is about 3 extra feet of column that is standing above the upper rail

2. Depth and size of the footers?

a. Depth: The depth is not known at the time.

b. Size: 46-1/2” x 46-1/2”

3. What is the allowed duration of completing the installation work?

a. Proposals should indicate the estimated completion time.

4. Is there a sufficient 120V/20A/60HZ grounded power within 5' of the new scoreboard location?

a. Yes, see the high mounted outlet. Reference Table 4-6 of the Statement of Work.

5. Will the installer be able to access the scoreboard location(s) with a lift device such as a crane or derrick truck without damaging the field, track, fencing, etc?

a. Yes, there is a paved path between the baseball fields and a parking lot access point for equipment use.

6. Are there any more photos available of the existing structure?

a. The Statement of Work has been updated to reflect two additional photos of the existing structure and are listed below.

Attachment:

- Three photos of existing structure

Contracting Officer

Photo 1

Photo 2

Photo 3