Attachment 8 - Revised Seed Site Layout - Paint Hangar 1.pptx

PPTX presentation 207 KB Posted

Attached to
Protective Coatings IDIQ
Solicitation number
FA706022R0033
Issued by

View the file

Other files

File Type Posted
Attachment 10 - Sections L and M revised.docx DOCX document
Amendment 3 FA706022R00330003.pdf PDF
Attachment 12 - Questions and Answers corrected.docx DOCX document
Amendment 2 FA706022R00330002.pdf PDF
Attachment 12 - Questions and Answers.docx DOCX document
Amendment 1 - FA706022R00330001.pdf PDF
Attachment 7 - Revised Seed SOW - Paint Hangar 1.docx DOCX document
Amendment 1 - Attachment 6 - FOPR for Seed Project-signed.pdf PDF
Attachment 9 -Wage Determination - Buildings DC20220002 07082022.pdf PDF
Attachment 8 - Seed Site Layout - Paint Hangar 1.pptx PPTX presentation
Attachment 7 - Seed SOW - Paint Hangar 1.docx DOCX document
Attachment 4 - Financial Reference.docx DOCX document
Attachment 1 - SOW 5 Year Protective Coating IDIQ - 6-13-22.docx DOCX document
Attachment 2 - MACC Conditions.docx DOCX document
Attachment 11- CUI JBAB Base Access Registration Form.xlsx XLSX spreadsheet
Attachment 6 - FOPR for Seed Project-signed.pdf PDF
Solicitation - FA706022R0033.pdf PDF
Attachment 9 - Wage Determination - Buildings DC20220002 06242022.pdf PDF
Attachment 3 - Past Performance Information Form.docx DOCX document
Attachment 5 - Subcontractor Consent.docx DOCX document
Attachment 10 - Sections L and M.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA706022R0033

Attachment 8

Notes to Layout

1 – Only interior of the rooms highlighted in red will be painted, have trim and doors refinished, and have all necessary wall repairs made.

2 revised – The facility will be occupied while working is completed, the contractor is responsible to move furniture and equipment and move back into position when work is complete.

3 – Contractor is responsible to verify dimensions of each room.

4 – Contractor responsible to protect existing flooring and equipment from paint and damage.

5 – The admin office J3 area is two story and both levels require paint image1.png