This is a Questions and Answers document for federal contract solicitation FA704626QRJ1 issued on 21 May 2026 for HQ Carpet & Paint work at Kirtland Air Force Base (KAFB).
The project involves carpet replacement and interior painting across multiple locations. Carpet work includes the Leaf Presentation Center (including the stage area with separate carpet submission required), the annex (using carpet squares in a single pattern), and the hallway in Building 20129. Paint work encompasses walls, ceilings, door frames, and hand railings in stairwells; the vestibule of Building 20219 with cove base and vinyl base replacement; Room 211 including closet interior and the prefinished kitchenette door frame; and specified vault door surfaces. Minor drywall repairs are included only for signage removal areas in the Leaf Presentation Center lobby and stairwell corner bead seams. Doors, accordion doors, windows, cabinets, furniture, and tile flooring are excluded from refinishing. All work must occur during normal duty hours with coordination required for Room 211 command staff functions, annex events, and Building 20129 hallway occupant protection. Contractor personnel require daily badging through AFOTEC security. The government will handle removal and storage of artwork, electronics, and furniture movement. Laydown and staging areas are available in adjacent parking lots, cordoned with tape and stanchions rather than temporary fencing. Davis Bacon wage rates apply. The project is funded with Fiscal Year 26 appropriations with no specific completion deadline beyond standard contract terms. No asbestos, temporary storage, special fencing, or barrier requirements are necessary.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions And Answers
21 May 2026
Requirement: – HQ Carpet & Paint
Solicitation ID: FA704626QRJ1
1. Is a GB-98 License required?
Yes. Any contractor performing work on KAFB will require all necessary local, state, and federal licensure to be considered for award. However, no submission of such will be required. The government assumes that any vendor offering under this solicitation holds and maintains all necessary licensure.
2. Do chairs need to be removed to do carpet in the Leaf Presentation Center?
Yes.
3. What is under the carpet?
Concrete
4. Is carpet replacement needed for the stage area in the Leaf Presentation Center?
Yes, carpet replacement is needed for the stage. Carpet squares are unlikely suitable, as a result, separate carpet should be submitted as part of your quote and color options provided as part of the submittal process.
5. Are doors being refinished?
Doors will not be refinished
6. Who is removing and storing art? Electronics?
AFOTEC facilities personnel will remove and store artwork and electronics.
7. Where are items removed from walls being stored?
AFOTEC facilities personnel will determine location to store items.
8. Is tile flooring being replaced?
No.
9. Do cabinets/furniture require refinish?
Cabinets and furniture do not require refinishing
10. Who is removing the lettering for the Leaf Presentation Center located on the entryway wall? Is drywall being repaired under the scope of this contract?
The letters will not be removed from the wall. Minor drywall repairs should be done.
11. Who is moving furniture?
AFOTEC facilities personnel
12. Is laydown/storage space available?
Yes
13. In room 211, are accordion doors and surrounding wood trim being refinished?
No
14. In room 211, is the window being refinished?
Window is not being refinished
15. In room 211, the door frame into the kitchenette is prefinished. Is it being painted?
Yes. The frame needs to be painted
16. In room 211, is the closet interior included in the scope of work?
Yes. The closet is to be painted
17. Is carpet being replaced in the annex? If so, will it be replaced with carpet squares?
Yes, carpet is being replaced in the annex with carpet squares
18. Are there any considerations or limitations on when work can be performed in different areas of the project?
Yes. Room 211 will require coordination to ensure command staff functions are not interrupted. Additionally, coordination will be required to ensure events in the annex common area are uninterrupted. Finally, painting and Carpet of the hallway in Bldg.
20129 will require coordination to ensure occupants do not damage recently installed/painted surfaces.
19. Could you please provide the actual dimensions, floor plans, or any available blueprints containing layout notes and measurements for the areas identified in the Statement of Work?
Floor plans have been uploaded to the solicitation.
20. Please provide photographs of each room, hallway, stairwell, and any other areas referenced within the SOW.
Photographs uploaded to solicitation
21. Please provide the actual dimensions, floor plans, or any available blueprints containing layout notes and measurements for the areas identified in the Statement of Work.
Floor plans have been uploaded to the solicitation.
22. Please confirm that only walls, ceilings, door frames, and hand railings within the stair corridors are to be painted, and that stairs, stair risers, and flooring are excluded from new paint or finish work.
Confirmed that stairs, stair risers, and flooring are excluded in stairwell areas
23. Please confirm the carpet in the Annex is to be replaced. If replacement is included, please advise whether the new carpet will consist of a single color/pattern or if multiple patterns/colors requiring field layout and cutting will be required.
Carpet in the annex is to be replaced. New carpet will consist of single/pattern
24. 20219 - Please advise whether the vestibule walls and existing door frames are to be included in the painting scope of work.
Yes, vestibule walls and existing door frames are to be included and the cove base replaced.
25. 20219 - Please advise whether the vestibule walls are to be included in the vinyl base scope of work.
Yes, included.
26. 20219 - Please confirm whether both sets of vault doors, including both sides of each vault door, are to be painted as part of the project scope.
Both sides of door that meets the hallway. Only the outer portion of the inner door.
27. Please advise whether any special badging, security clearance, or escorting requirements will be necessary for contractor personnel during construction activities.
Contractor will provide a list of employees that will be working at the facility. That list will be sent to AFOTEC security office and employees will sign out a badge and return it each day.
28. Please advise whether any night work or weekend work will be required, or if it will be acceptable to install temporary barriers/construction signage and perform work during normal hours within occupied areas.
All work will be performed during normal duty hours
29. At the upper portions of the stairwell ceilings near the skylights, there are areas where the corner bead appears separated and visible seams are present. Please confirm that no drywall repair or patching of these areas is required and that these surfaces are only to receive paint finishes.
Confirmed. No drywall repair or patching is required. Only paint finishes.
30. Please confirm that no additional drywall patching is anticipated within the project scope, with the exception of patching associated with signage/lettering removal in the LEAF PC Lobby.
Confirmed.
31. Please advise whether any portion of this project is tied to fiscal year funding deadlines or otherwise fiscally constrained such that completion or invoicing must occur prior to a specific date.
This requirement is funded with Fiscal Year 26 appropriations, however, there is no constraint regarding completion and invoice beyond the terms and conditions for completion identified in the contract.
32. Please provide the Davis Bacon Wage Rates for the project.
Wage Rates are amended to the solicitation.
33. Please confirm a staging area can be allocated during construction in one of the adjacent parking lots.
Yes staging area can be allocated
34. Please advise if any temporary fencing is needed around the staging area/dumpster or if it is acceptable to cordon off with tape and stanchions.
No temporary fencing/it is acceptable to cordon off with tape and stanchions.
35. Please advise if any fencing or special barriers/ temporary construction is needed inside or outside of the building.
Not needed
36. Please advise if any onsite temporary storage is needed for client stored material.
No temporary storage is needed
37. Is asbestos present in any work areas?
No