Cable_question.pdf

PDF 14 KB Posted

Attached to
Stadium Cabling Federal contract opportunity
Solicitation number
FA700018Q0005
Issued by
Department of the Air Force Headquarters Air Force Academy

About this file

Question and response (in RED or Bold following the question) REMINDER: THIS RFQ IS EXTENDED TO 11 JUN 2018.

View the file

Other files for this federal contract opportunity

Other files attached to Stadium Cabling, newest first.
File Type Posted
CBS_Cable_Lengths.pdf PDF
Attachment_3_-_Falcon_Stadium_Map_Locations.pdf PDF
Revised_Combined_Synopsis_-Stadium_Cabling_31_May_18.docx DOCX document
Revised_Cabling_PWS_final_31_May_18.docx DOCX document
WD_2015-5417_Rev9_Attachment_4.pdf PDF
Attachment_2.pdf PDF
Combined_Synopsis_-Stadium_Cabling_29_May_18.pdf PDF
Attachment_3_-_Falcon_Stadium_Map_Locations.pdf PDF
Attachment_1.pdf PDF
Cabling_PWS_final.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers pertaining to FA700018Q0005 Stadium Cabling cable specifications / use and the number of cables for Junction boxes.

DT12 cables – cable shall be suitable for application in both outdoor/indoor environments

Triax Cables – cable shall be suitable for application in both outdoor/indoor environments

Video Fiber – cable shall be suitable for application in both outdoor/indoor environments

SMPTE cables – cable shall be suitable for application in both outdoor/indoor environments

XLR Cables – cable shall be suitable for application in both outdoor/indoor environments

Questions continued

TV Booth shows 2 triax and 2 SMPTE but attachment one does not list them do we follow diagram or written info

Are the SMPTE cables Fiber only or with stranded for power

Section M7,M8,M9 show 8 strands of fiber on panel layout and calls for 12 strand on attachment 1 also attachment 1 calls for 2 XLR but not shown on the layout

Does high right ez equal scoreboard south end if so on panel layout shows 8 strand attachment 1 says 12 strand

Roof panel layout shows 4 strands of fiber and attachment one calls for 6

Both north and south EZ layout shows only one triax and one SMPTE Attachment 1 calls for two

High left section U13 layout shows 4 strands of fiber attachment one calls for 6

Please use the numbers for the cabling found in Attachment two (2) of the RFQ