SOW Att 6 - 01 14 00 work restrictions.docx

DOCX document 38 KB Posted

Attached to
Renovate B320, Supply Federal contract opportunity
Solicitation number
FA6712-18-R-0001
Issued by
Department of the Air Force Reserve Command

About this file

Attachment

View the file

Other files for this federal contract opportunity

Other files attached to Renovate B320, Supply, newest first.
File Type Posted
XX_AF-411-10-11_15_19_P-1_WAREHOUSE BUILDING BLDG. 320_PLUMBING FLOOR PL....pdf PDF
XX_AF-411-10-11_17_19_E-1_WAREHOUSE BUILDING BLDG. 320_ELECTRICAL PLAN &....pdf PDF
XX_AF-411-10-11_18_19_E-2_WAREHOUSE BUILDING BLDG. 320_SCHEDULES_1984OCT....pdf PDF
XX_AF-411-10-11_14_19_PS-1_WAREHOUSE BUILDING BLDG. 320_PLUMBING SITE PL....pdf PDF
XX_AF-411-10-11_16_19_P-2_WAREHOUSE BUILDING BLDG. 320_DETAILS DIAGRAMS ....pdf PDF
A15_Amendment_One.pdf PDF
A16_Questions_Two.docx DOCX document
AMRS_Meter_Specifications_dated_28_January_2016_(002).docx DOCX document
A16_Site_Visit_Sign_In_Sheet.pdf PDF
A16_Questions_One.docx DOCX document
SOW Att 3 - Building 320 Existing and Proposed Layout 11-9-17.pdf PDF
A15_Solicitation.docx DOCX document
SOW Att 15 - 01 73 89 cutting and patching.docx DOCX document
SOW Att 4 - Pittsburgh IAP ARS Design Guidelines 120817 v4.pdf PDF
SOW Att 19 - 02 41 19 fl - selective demolition.docx DOCX document
SOW Att 17 - 01 81 30a green procurement reporting form apendx.docx DOCX document
SOW Att 12 - 01 50 00 temporary facilities and controls.docx DOCX document
SOW Att 13 - 01 59 50 safety requirements.docx DOCX document
SOW Att 9 - 01 34 00 submittal procedures.docx DOCX document
SOW Att 5 - Pittsburgh ES Plan Final 2014.docx DOCX document
SOW Att 16 - 01 81 30 green procurement requirements.docx DOCX document
Bid_Schedule.doc DOC document
SOW Att 11 - 01 41 00 Environmental Protection 2016.doc DOC document
SOW Att 18 - 01 87 30 - Project Record Documents.doc DOC document
SOW Att 7 - 01 31 00 - Project Management and Coordination.doc DOC document
SOW Att 8 - 01 32 00 Constr Progr —
PR_Att_8-_General_Decision_Number_PA170001_20_OCT_2017_PA1.pdf PDF
SOW Att 14 - 01 73 00 closeout procedures.docx DOCX document
SOW Att 10 - 01 40 00 quality requirements.docx DOCX document
PR_Att_1-_Statement_of_Work-JLSS_17-0009.docx DOCX document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT: JLSS 02-0002

SEAL APRON JOINTS – EAST / WEST APRON

Construction Bid Set

SECTION 01 14 00

WORK RESTRICTIONS

GENERAL

CONTRACTOR USE OF PREMISES AND RESPONSIBILITIES

Coordinate use of premises under direction of Contracting Officer. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated. Cooperate with 911th Airlift Wing personnel during construction operations to minimize conflicts and facilitate 911th Airlift Wing usage.

Limits: Confine construction to areas indicated on construction drawings and/or as designated by the Contracting Officer. Confine storage area as designated by the Contracting Officer.

Driveways and Entrances: Keep driveways and entrances serving premises clear and available to 911th Airlift Wing employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

Schedule deliveries to minimize use of driveways and entrances.

Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

Perform the work so as not to interfere with 911th Airlift Wing operations.

Assume full responsibility for protection and safekeeping of products under this Contract.

Work periods may be limited in duration without additional compensation to the Contractor aside from an extension to the performance period for lost time. Work schedule shall be as follows:

Normal work hours shall be between 0700 to 1600 (7:00 AM to 4:00 PM), Monday through Friday, with no work on federal holidays.

Any deviations from the normal working hours must be approved 3 working days in advance by the Contracting Officer.

The Contractor shall be responsible for protecting all remaining permanent equipment.

Work is prohibited on UTA training weekends, which typically occurs the first and third weekends each month.

Obtain and pay for use of additional storage or work areas needed for operations under this contract.

Comfort stations are not provided by 911th Airlift Wing.

PRODUCTS (Not Applicable) EXECUTION (Not Applicable)

END OF SECTION

WORK RESTRICTIONSSECTION 01140-1