SOW Att 14 - 01 73 00 closeout procedures.docx

DOCX document 40 KB Posted

Attached to
Renovate B320, Supply Federal contract opportunity
Solicitation number
FA6712-18-R-0001
Issued by
Department of the Air Force Reserve Command

About this file

Attachment

View the file

Other files for this federal contract opportunity

Other files attached to Renovate B320, Supply, newest first.
File Type Posted
XX_AF-411-10-11_17_19_E-1_WAREHOUSE BUILDING BLDG. 320_ELECTRICAL PLAN &....pdf PDF
XX_AF-411-10-11_18_19_E-2_WAREHOUSE BUILDING BLDG. 320_SCHEDULES_1984OCT....pdf PDF
XX_AF-411-10-11_14_19_PS-1_WAREHOUSE BUILDING BLDG. 320_PLUMBING SITE PL....pdf PDF
XX_AF-411-10-11_15_19_P-1_WAREHOUSE BUILDING BLDG. 320_PLUMBING FLOOR PL....pdf PDF
A15_Amendment_One.pdf PDF
A16_Questions_Two.docx DOCX document
XX_AF-411-10-11_16_19_P-2_WAREHOUSE BUILDING BLDG. 320_DETAILS DIAGRAMS ....pdf PDF
AMRS_Meter_Specifications_dated_28_January_2016_(002).docx DOCX document
A16_Site_Visit_Sign_In_Sheet.pdf PDF
A16_Questions_One.docx DOCX document
SOW Att 17 - 01 81 30a green procurement reporting form apendx.docx DOCX document
SOW Att 12 - 01 50 00 temporary facilities and controls.docx DOCX document
SOW Att 13 - 01 59 50 safety requirements.docx DOCX document
SOW Att 9 - 01 34 00 submittal procedures.docx DOCX document
SOW Att 5 - Pittsburgh ES Plan Final 2014.docx DOCX document
SOW Att 16 - 01 81 30 green procurement requirements.docx DOCX document
SOW Att 3 - Building 320 Existing and Proposed Layout 11-9-17.pdf PDF
A15_Solicitation.docx DOCX document
SOW Att 15 - 01 73 89 cutting and patching.docx DOCX document
SOW Att 4 - Pittsburgh IAP ARS Design Guidelines 120817 v4.pdf PDF
SOW Att 19 - 02 41 19 fl - selective demolition.docx DOCX document
SOW Att 8 - 01 32 00 Constr Progr —
PR_Att_8-_General_Decision_Number_PA170001_20_OCT_2017_PA1.pdf PDF
SOW Att 10 - 01 40 00 quality requirements.docx DOCX document
PR_Att_1-_Statement_of_Work-JLSS_17-0009.docx DOCX document
SOW Att 6 - 01 14 00 work restrictions.docx DOCX document
Bid_Schedule.doc DOC document
SOW Att 11 - 01 41 00 Environmental Protection 2016.doc DOC document
SOW Att 18 - 01 87 30 - Project Record Documents.doc DOC document
SOW Att 7 - 01 31 00 - Project Management and Coordination.doc DOC document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Bid Set

SECTION 01 73 00

CLOSEOUT PROCEDURES

GENERAL

1.01 SCOPE OF WORK

This Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

Inspection procedures.

Project record documents.

Operation and maintenance manuals.

Warranties.

Instruction of Government's personnel.

Final cleaning.

PRELIMINARY FINAL INSPECTION

A meeting shall be held with the Contractor, Contracting Officer, and other designated representatives as deemed necessary by the Contracting Officer to discuss deficiencies, establish standards for quality of acceptance and to establish a beneficial occupancy date. This meeting will be held when the Contractor’s work is substantially complete.

PRE-FINAL INSPECTION

Contractor Preliminary Procedures: Complete the following before requesting pre-final inspection.

Complete startup testing of systems.

Complete final cleaning requirements, including touchup painting.

Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

Conduct own inspection, identifying items to be corrected. Submit this list to the Contracting Officer along with time frame when the items needing corrected shall be completed.

Inspection: On receipt of request, Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements. If upon inspection by the Contracting Officer more than five deficiencies are identified, then the inspection shall immediately terminate and be rescheduled when the contractor corrects all deficiencies and then notifies the Contracting Officer in writing that all deficiencies are corrected.

Reinspection: The Contractor shall request reinspection when the Work identified in the pre-final inspection as incomplete is completed or corrected.

Results of completed inspection will form the basis of requirements for Final Completion.

FINAL INSPECTION

Inspection: The Contractor shall submit a written request for final inspection for acceptance. On receipt of request, Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements. Contracting Officer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

Reinspection: Request reinspection when the Work identified in the final inspection is incomplete is completed or corrected.

WARRANTIES

Provide one (1) bound copies of all warranty documents, organized into an orderly sequence based on the table of contents of the Project Manual.

Bind warranties and bonds in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

Provide copy of each warranty in an electronic format as a closeout submittal.

OPERATION AND MAINTENANCE MANUALS (O&M)

Provide one (1) bound copies of all Operation and Maintenance (O&M) Manuals, organized into an orderly sequence based on the table of contents of the Project Manual.

Bind manuals in heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

Provide heavy paper dividers with plastic-covered tabs for each separate manual. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

Identify each binder on the front and spine with the typed or printed title "O & M MANUAL," Project name, and name of Contractor.

Provide copy of operation and maintenance manuals in an electronic format as a closeout submittal.

PRODUCTS (NOT USED)

PART 3 - EXECUTION

FINAL CLEANING

General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean all surfaces affected by construction activities, including hallways, rooms, and conference areas. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program.

Sweep concrete floors broom clean in unoccupied spaces.

Vacuum carpet and similar soft surfaces, removing debris and excess nap; shampoo if visible soil or stains remain.

Remove labels that are not permanent.

Wipe surfaces of mechanical and electrical equipment, elevator equipment, and similar equipment.

Remove excess lubrication, paint and mortar droppings, and other foreign substances.

Replace parts subject to unusual operating conditions.

Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

Subparagraph below is a major work item that may be disruptive to closeout procedures.

Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

Leave Project clean and ready for occupancy.

Remove all debris, sweep exterior concrete and other paved surfaces to a broom-clean condition.

Comply with safety standards for cleaning.

Remove waste materials from Project site and dispose of lawfully.

Do not burn waste materials.

Do not bury debris or excess materials on Government’s property.

Do not discharge volatile, harmful, or dangerous materials into drainage systems.

END OF SECTION

911th Airlift Wing – Renovate Supply B320Close Out Procedures
JLSS-17-0009SOW Attachment 1401 73 00 - 1