Attachment 14 - Giant Voice System Upgrade Questions and Answers 20220909.pdf
PDF 140 KB Posted
- Attached to
- Giant Voice (GV) System Upgrade
- Solicitation number
- FA670322R0003
About this file
This document contains questions and answers regarding a Giant Voice System Upgrade opportunity for Dobbins Air Reserve Base. The incumbent contractor is required to engineer, design, furnish, install and test a turnkey upgrade to the existing Giant Voice communication system to address unreliable performance issues. This includes utilizing existing infrastructure where possible, integrating new indoor and outdoor speakers, control units and radios, and implementing a conventional radio repeater or trunked system for command and control depending on the existing Motorola P25 land mobile radio configuration. The contractor must also replace outdated modems and control units while maintaining all current system functionalities. Quantities in the statement of work tables are provided as guidance only as the contractor is responsible for the full engineered solution.
The related solicitation is for the Giant Voice System Upgrade opportunity with the issuing agency being the Department of the Air Force Reserve Command. Full details of the requirement are contained in the attached combined synopsis and solicitation document.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Giant Voice System Upgrade Questions and Answers
9 September 2022
Questions – Site Visit, 28 July 2022
1. Are strobes to be supplied for each of the existing speakers and with each of the new speakers requested?
No strobes for existing speakers. See Table 2 of the SOW for strobe requirements on new contractor furnished speakers.
2. Are the existing speakers to be reused with the new ICU equipment within each building?
Yes. All existing indoor speakers are to be used in addition to new contractor furnished per Table 2.
3. Can you provide details regarding the GFE modems to be reused for each SCU and ICU with the copper cable including the manufacturer, make and model?
DATA CONNECT ENTERPRISE IG96HFP‐LV 100‐0101d
4. How many local control units are required with each ICU?
The contractor is responsible to Engineer, design, furnish, install and test a turnkey GianVoice system per the SOW.
5. Just to confirm we can use as much of the existing installation infrastructure (i.e. wood Poles, Conduit, Brackets, pole mounting brackets, etc.)
Existing Infrastructure can be used, Brackets, mounts, screws etc. are NOT considered infrastructure.
6. Just to confirm we are to re‐use the existing ACE3600 modems at the following existing locations:
a. (8) Indoor ISU
b. (2) Existing Control Stations
c. (6) Outdoor Siren location
See 1.0.4 of SOW.
7. Who is responsible for procuring the additional (2) New ACE3600’s modems; (1) for the Controller and (1) for the Seventh New Outdoor Siren location?
The contractor is responsible to Engineer, design, furnish, install and test a turnkey GiantVoice system per the SOW.
8. The request mentions providing (15) APX4500 Radios, to confirm can we add (3) more radios, one for each Central Control Unit (CCU)? For a Grand Total of (18) APX 4500 radios.
All required equipment should be provided based on the contractor design. This is a turnkey solution.
See 1.0 of SOW.
9. Who is responsible for bringing the copper infrastructure to the New Seventh Siren location?
N/A. No copper to the contractor installed seventh siren location.
10. For the new Siren location will 120/ 220 VAC be provided within 10’ of the Final Pole location?
See 3.1.6.4 of SOW.
11. For the new Indoor Speakers and Speakers w/ Strobes listed through‐out the site are they to be directly wired into the existing Wheelock Safepath? Or is it acceptable to wire the new speakers into a new amplification unit?
The contractor is responsible to Engineer, design, furnish, install and test a turnkey GianVoice system per the SOW.
12. Are the Wheelock Safepath Panels configured as Mass Notification Systems (MNS) panels or as Fire Alarm Panels (FAP)? Considering that the SOW mentions the existence of Monaco FAP’s.
Current Legacy Giant Voice system is entirely independent of Monaco FAP.
13. Can it be confirmed whether all of the outdoor siren locations are pole mounted or if there are any outdoor sirens that are mounted on buildings?
Five current existing pole outdoor sirens; one current existing wall‐mounted on building siren and one new outdoor siren location which is stated to be contractor engineer, design, furnish, install and test. See 3.1.6.1 ‐ 3.1.6.4 in SOW new outdoor siren location requirements.
14. Section 3.2.5.2 of the SOW states "Aforementioned C2 bldgs. shall have new audible appliances installed, i.e., new ceiling speakers, strobes, and horns, IAW Table 2 of this SOW." yet states "Tables in this SOW serve as a guide only and shall not be used quantitatively for installation (i.e., ordering).".
Can clarification be provided to confirm if the new speaker quantities in Table 2 shall be used to quantify the number of new sirens? If not, what requirement shall be met to determine new speaker quantities?
The highlighted statement has been removed from the initial SOW; therefore, a revised version of the
SOW has been uploaded to Sam.gov.
15. What Mfg is the current GV System?
The current system is a multivendor system.
QUESTIONS – Site Visit, 1 Sep 2022
1. Can drawings be provided for each building for the work to be performed in the Statement of Work for the Giant Voice (GV) System Upgrade dated August 12, 2022?
Building drawings are available by request only. Contact Ms. Patrina Sheffield at patrina.sheffield@us.af.mil and the drawings shall be forwarded via the DoD SAFE system.
2. Could you confirm per the site visit of September 01, 2022 that the contractor shall remove and dispose of all speakers and cabling for buildings identified on page 23, Table 2: “Small Voice” MNS for C2
Buildings, Dobbins ARB GA?
Table 2 addresses the quantity of existing speakers and the quantity of new speakers to be installed. No speakers and cabling are to be removed and disposed.
3. Could you confirm the requirement to supply all new speakers, strobes and cabling for buildings identified on page 23, Table 2: “Small Voice” MNS for C2 Buildings, Dobbins ARB GA to include
366 5W ceiling speakers, 35 5W ceiling speakers with strobes and 24 15W wall speakers?
Table 2 addresses new equipment to be installed as quantity of thirty‐five 5W ceiling speakers with strobes and quantity of two 15W wall speakers. The other noted ceiling speakers and wall speakers are existing equipment.
4. Could you provide details of the existing ELMR infrastructure referenced on page 2, section 1.0 Scope in the Statement of Work for the Giant Voice (GV) System Upgrade dated August 12, 2022?
This information shall be provided after contract award. NOTE: This is a Motorola P25 Enterprise Land
Mobile Radio system that is not control by Dobbins ARB but AFRC.
5. Is the Government maintaining responsibility for the requirement on page 2, section 1.01 in the
Statement of Work Giant Voice (GV) System Upgrade dated August 12, 2022 to "utilize the existing
ELMR infrastructure and existing backup landline copper infrastructure" because on page 2, section 1.0
Scope reference is made to the "unreliable performance of the existing landline copper communications infrastructure and inoperative trunked ELMR radio infrastructure"? Could you please clarify?
The infrastructure is in working order; however, the current Giant Voice System is unreliable and inoperable at times. Must engineer a system to work with existing infrastructures per SOW.
6. Radios
1.0 Calls out using existing LMR system in sow. 3.1 Also mentions standalone RF system. (“ standalone, two way,RF repeater”) 3.2.7.3 as well . These statements conflict. Which is the desired configuration?
1. Standalone RF system or
2. using existing elmr system?
Must the standalone system utilize a repeater if all devices (sirens, control points) are able to communicate directly to each other? (Eliminates points of failure, increased reliability)
Must engineer a system to work with existing infrastructures per SOW.
7. Siren control OTA format
2.1 mentions “turnkey GV communications system utilizing FSK”
This is possible on a standalone RF system but will pose issues if voice trunked system is digital phase
2. Typically, this would utilize encrypted DTMF due to incompatibilities in the vocoder/transport depending on the system (phase 1 or phase 2). Is encrypted DTMF acceptable if the system is phase
2/other digital compressed format?
The contractor is responsible to engineer, design, furnish, install, and test a turnkey Giant Voice system per the SOW.
8. Existing ELMR system
Please describe existing ELMR radio system. (IE p25 trunked, phase I, phase II, capacity+/MAX)
Are there plans to upgrade the backbone/controller/technology?
Regarding answers above, for clarity, which should be quoted?
a)New conventional repeater with encrypted fsk format as command/control OTA transport (two available exclusive radio frequencies needed)
b) half duplex conventional encrypted FSK system with all interior antennas run to the exterior of the buildings. (single radio frequency needed, repeater not needed as all sites will communicate directly)
c) using existing trunked system (no new repeater/antenna system on the radio tower)
This information shall be provided after contract award. NOTE: This is a Motorola P25 Enterprise Land Mobile Radio system that is not control by Dobbins ARB but AFRC.
9. Indoor units:
3.2.5.3 mentions 8 new indoor control units. It does not mention if amplifier replacements are
*required*. The current Safepath SP40s functions exclusively as an amplifier/speaker distribution center in the current configuration. The Whelen/ACE3600 (to be removed/replaced) act as command/audio relays.
A) 8 New indoor control units that replace the existing Whelen cabinet, PA control, ACE3600
RTU, AND the Safepath indoor PA system?
B) 8 New indoor control units that replace the existing Whelen cabinet/PA control, as well as the
ACE3600 RTU. ASC ICU can integrate with the existing saftepath sp40S indoor PA system
(currently working, supported and manufactured) and provide real time status feedback? (Significant cost savings)
The contractor is responsible to Engineer, design, furnish, install and test a turnkey Giant Voice system
10. Table 1 mentions addition of volume control speakers – does this volume control need to be wall mounted/accessible, or can this control exist on the speaker itself.
The contractor is responsible to Engineer, design, furnish, install and test a turnkey Giant Voice system
11. Current system has a dial in number tie‐in from a phone in hangar 5 for voice announcements to that building only. Will this functionality be needed? It is not mentioned in scope. Note – if keeping
Safepath, this functionality would remain
Any and all current functionalities must remain intact after the Giant Voice System has been upgraded.