JA‐14 FA6703‐19‐R‐A004

Headquarters Air Force Reserve Command

Saber

DESIGN‐BUILD

TASK ORDER#

STATEMENT OF OBJECTIVE:

Change 1

Repair, B401

Contract Number:

xxxxxxx

Base Project Number: FGWB 18‐0005

28 AUGUST 2019

Page I of 4

1.0

2.0

INTRODUCTION:

In accordance with SABER basic contract, the Government is issuing this task order to transition from concept definition to design‐build services. The Contractor shall be capable of addressing and interpreting all aspects of Unified Facility Criteria (UFC) and Unified Facility Guide Specifications (UFGS) regarding this Task Order.

PURPOSE:

Under this contract the 94th Mission Support Group Civil Engineers (94th MSG/CE) will use the D‐ B process to repair and maintain building 401.

2.1 Project Information:

The project includes the following:

2.1.1 Interior:

2.1.1.1 Washer and Dryers: Install electrical system for 4 washers and 4 dryers in existing housekeeping office. Install dryer exhaust duct and outlets. Install new plumbing for washers. Move existing washers, and dryers in basement to new location.

2.1.1.2 Demolition and pre cleaning: Demolish electrical outlets and exposed conduit in basement. Remove damaged ceiling tile. Clean and prep walls. Demolish housekeeping door to lobby to include door frame. Demolish cabinet adjacent to lobby restroom.

2.1.1.3 Finish's: Repair and repaint walls where cabinets, washers, dryers, and ice machine were removed. Close up lobby door opening with framing and dry wall. Prep dry wall for wall paper, remove wallpaper from adjacent wall and replace with matching wall paper or wall paper ofcolor and design as approved by the government.

2.1.1.4 Ice Maker: Install electrical and plumbing connections in area near lobby restroom where cabinet was demolished. Install electrical and plumbing connections for ice maker. Move ice maker in basement to the new location.

2.1.2 Exterior:

2.1.2.1 Windows: Remove 4 basement windows and fill wall with concrete block. Apply waterproofing to exterior of new block. Fill window pit with fill and cover with stone.

Page 2of4

2.1.2.2 Trees: Trim all trees back from building. Six trees on east side of north wing, five trees on west side of north wing, one on the front of the south wing, one on the south west comer of the south wing, and one to the west of the south wing..

2.1.2.3 Sewer: Replace sewer from manhole at front of the building to the nearest manhole to the east avoiding trees and entry sidewalk.

Sewer must be under parking lot to avoid sidewalk.

Approximately 275 linear feet will need to be replaced.

2.2 SOW for Construction:

The Contractor shall construct IAW approved submittals

3.0 SCOPE

3.1

Prior to beginning onsite construction, the Contractor will initiate the Construction Phase by completing project plans and specifications, including a construction schedule. Plans shall comply with codes, laws and this statement of work. This will also require some minor interior design work in that colors and patterns must be approved by the user and BCE, however the contractor shall be responsible for making recommendations of attractive designs that does not detract from the existing building interior design, and is within Air Force Reserve standards.

3.2 Design Documents: 35% design shall be submitted to the Government for approval before start of work.

4.0 APPLICABLE DOCUMENTS:

The following are either contained in or an addition to SABER SOW Para 4. The Contractor shall identify and comply with all applicable federal, state, and local statutes; Air Force/Military Instructions, manuals, handbooks, regulations, guidance, and policy letters; (UFC) 3‐535‐01;

Executive Orders (ESO); National Fire Protection (NFPA); Engineering Technical Letters (ETL); as applicable the Unified Facility Guide Specifications (UFGS), and in SOW including all changes and amendments in effect on the date of issuance of this TO. In addition, the Contractor shall refer to the current version of the USAF Project Manager's Guide for Design and Construction, and Guidance for Contract Deliverables (GCD), current version.

Computer Products:

Provide As‐Build drawings in CADD format files on a CD.

5 PERFORMANCE

5.1 Performance Period: The performance period for this statement of work is 120 calendar days.

5.2 Progress Report: Contractor shall provide Project Manager and Inspector with weekly progress reports.