General Decision Number: NY130011 02/22/2013 NY11

Superseded General Decision Number: NY20120011

State: New York

Construction Types: Heavy and Highway

County: Niagara County in New York.

HEAVY AND HIGHWAY CONSTRUCTION PROJECTS

Modification Number Publication Date

0 01/04/2013

1 01/18/2013

2 01/25/2013

3 02/01/2013

4 02/08/2013

5 02/22/2013

BOIL0007-001 01/01/2012

Rates Fringes

BOILERMAKER......................$ 29.64 24.30

BRNY0045-002 07/01/2012

Bricklayer, Stonemason...........$ 30.48 17.94

Marble mason.....................$ 30.23 17.69

Pointer, cleaner and caulker.....$ 30.48 17.94

Tile & Terrazzo Worker...........$ 30.23 17.69

Tile, Marble & Terrazzo

Finisher.........................$ 27.52 11.29

CARP0276-015 07/01/2011

CARPENTER

CARPENTER...................$ 28.30 17.05

MILLWRIGHT..................$ 27.59 22.09

PILEDRIVER..................$ 29.10 21.06

ELEC0237-001 07/30/2012

Electricians:

Cable Splicers..............$ 33.77 22.89

Electricians................$ 30.70 22.89

ELEC1249-003 05/07/2012

LINE CONSTRUCTION: Lineman

(LIGHTING AND TRAFFIC SIGNAL

3/18/2013http://www.wdol.gov/wdol/scafiles/davisbacon/NY11.dvb?v=5

Including any and all Fiber

Optic Cable necessary for

Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems)

Flagman.....................$ 23.70 7%+18.25

Groundman Truck Driver

(tractor trailer unit)......$ 33.58 7%+18.25

Groundman Truck Driver......$ 31.60 7%+18.25

Lineman & Technician........$ 39.50 7%+18.25

Mechanic....................$ 31.60 7%+18.25

FOOTNOTE:

a. New Year's Day, Memorial Day, Independence Day, Labor

Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.

* ELEC1249-004 05/07/2012

Line Construction:

Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities (where no other trades are or have been involved):

Flagman....................$ 27.14 7.5%+18.25+a

Groundman digging machine operator...................$ 40.71 7.5%+18.25+a

Groundman truck driver

(tractor trailer unit).....$ 38.45 7.5%+18.25+a

Groundman Truck driver.....$ 36.18 7.5%+18.25+a

Lineman and Technician.....$ 45.23 7.5%+18.25+a

Mechanic...................$ 36.18 7.5%+18.25+a

Overhead transmission line work (where other trades are or have been involved):

Flagman....................$ 27.14 7.5%+18.25+a

Groundman digging machine operator...................$ 40.71 7.5%+18.25+a

Groundman truck driver

(tractor trailer unit).....$ 38.45 7.5%+18.25+a

Groundman truck driver.....$ 36.18 7.5%+18.25+a

Lineman and Technician.....$ 45.23 7.5%+18.25+a

Mechanic...................$ 36.18 7.5%+18.25+a

Substation:

Cable Splicer..............$ 46.99 7.5%+18.25+a

Flagman....................$ 25.63 7.5%+18.25+a

Ground man truck driver....$ 34.18 7.5%+18.25+a

Groundman digging machine operator...................$ 38.45 7.5%+18.25+a

Groundman truck driver

(tractor trailer unit).....$ 36.31 7.5%+18.25+a

Lineman & Technician.......$ 42.72 7.5%+18.25+a

Mechanic...................$ 34.18 7.5%+18.25+a

Switching structures;

railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation

Cable Splicer..............$ 46.99 7.5%+18.25+a

Flagman....................$ 27.77 7.5%+18.25+a

Groundman Digging Machine

Operator...................$ 38.45 7.5%+18.25+a

Groundman Truck Driver

(tractor-trailer unit).....$ 36.31 7.5%+18.25+a

Groundman Truck Driver.....$ 34.18 7.5%+18.25+a

Lineman & Technician.......$ 42.72 7.5%+18.25+a

Mechanic...................$ 34.18 7.5%+18.25+a

TELEPHONE, CATV

FIBEROPTICS CABLE AND

EQUIPMENT

Cable splicer..............$ 27.99 4.43 + 3%

Groundman..................$ 12.48 4.43 + 3%

Installer Repairman-

Teledata

Lineman/Tecnician-

Equipment Operator.........$ 26.57 4.43 + 3%

Tree Trimmer................$ 21.64 7.36+3%

a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial

Day, Good Friday, Independence Day, Labor Day, Thanksgiving

Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New

York State, provided the employee works two days before or two days after the holiday.

b. New Years Day, Washington's Birthday, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving Day and Christmas

Day.

ENGI0463-001 07/01/2012

Power Equipment Operator

HEAVY AND HIGHWAY

CONSTRUCTION

GROUP A....................$ 31.88 24.81

GROUP A1...................$ 33.88 24.81

GROUP B....................$ 30.17 24.81

Master Mechanic............$ 33.65 24.81

Notes:

Hazardous Waste 3.00

ZONE PAY: crane boom premium for boom and jib 100-199 ft

(1.00 over group A) crane boom premium for boom and jib 100-199 ft

(1.50 over group A) crane boom premium for boom and jib 100-199 ft

(2.00 over group A)

GROUP A1: Backfillers, backhoes, automatic batch plant operator, black-top spreaders, bulldozers, CMI grading machines, cableways, clambuckets, combination hoe boom or shovel boomattached (except farm type crawler or rubber tired tractor unless used with hydraulic back-hoe), compressor (with paing breaker attached), concrete mixers

(one yard and over), concrete planner, concrete pump (truck mounted), concrete spreader operator, crane work, cranes

(overhead or bridge), crane operator (over 100, 200, 300 feet booms earn premiums as noted herein), derricks, draglines, Euclid type belt loaders, finishing machine operators, fork-lifts and hoists 9 when lifting material at an elevation higher than twenty-five feet), form puller, generator and compressor (power driven-when used simultaneously and for any make of portable concrete batching machine), graders, graders (with bulldozer blades), hoists (multiple drum with air compresor when used simultaneously for more than one purpose), hoists - single drum when used to hoist steel), hydraulic concrete joint hammers, hydraulic rock drill (Ingersoll-Rand LM 500 type), hydro-axe, Kolman Loaders, loaders (front & back - except small type), lubrication engineers, mechanic, pavement breaker (except hand operated pavement breakers), pile driving rigs, pipe pushing rigs, pipe pushing machines

(mechanicl and hydraulic), post drivers (except truck mounted post drivers), reapir work on maintenance work under the supervision of a master mechanic, rollers (all)

(on finish blacktop), scoopmobiles (all), scrapter (either double or single bowl), S-240 Lazer-Guided screed, shovels, snow-loader, steel erection, stone crushers (portable), stone spreaders (power driven), tractors use din conjunction with scraper wagons (all), tree bandit or similar chipper, tranchers (when excavation over six feet in depth), tunnel mucking machines, vibrators

(self-propelled riding), welder

GROUP A2: crane boom premium for boom and jib 100-199 ft

(1.00 over group A)

GROUP A3: crane boom premium for boom and jib 100-199 ft

(1.50 over group A)

GROUP A4: crane boom premium for boom and jib 100-199 ft

(2.00 over group A)

GROUP B: air compresors (over 165 cu. ft), bobcat type skid loader, compressors when used in banks of two and not over three within a fifty foot radius and if fuel is stored, it would be stored within the same radius, concrete blowers, concrete pumps, conveyors, crawler or rubber tire tractor

(small farm typewith blade or bucket not to exceed 0.5 yd capacity), earth drills (all), elevators (all), forklift while used to lift material not over 25 ft, gunnite machines, heaters (gasoline -use in banks of two and not over three within an area of one hudnred foot radius, highlift hoists while used to lift material not over 25 ft, material hoists, single drum hoist for hoisting materials other than steel, Latourneau turnatrailers, light and power systems 9 gas or diesel driven - temporary 25 KW capacity or over), Loaders 9 small front or back), locomotive, parts room - when a parts room is manned it shall be an engineer, pavement busters, pin pullser, post drivers 9 truck mounted), pug machine, pums over 4 Inches, (road rollers except on finish balcktop, road widener mounted on a loader, rolles (self propelled - not on finish blacktop and under 7 tons), scoopmobiles - when used as a station ary hoist, or one used to lift material not in excess of 25 feet, snow-go, stone crushers and winch hoists mounted on trucks, tractors, trenchers excavating up to 6 ft deep), trenchers on the back of a jeep, welding machines (for 2 but not over 3 gasoline or diesel driven), winch tractors

ENGI0463-002 07/01/2012

POWER EQUIPMENT OPERATOR:

(TUNNEL AND SHAFT)

GROUP A.....................$ 33.42 24.81

GROUP A1....................$ 35.42 24.81

GROUP B.....................$ 33.42 24.81

GROUP C.....................$ 27.52 24.81

Master Mechanic.............$ 35.18 24.81

NOTES: Hazmat premium 3.00

ZONE PAY:

Add $1.00 to GROUP A - long boom crane premium 100 ft - 199 ft

Add $1.50 to GROUP A- long boom crane premium 200 ft - 299 ft

Add $2.00 to GGROUP A - long boom crane premium 300 ft and over

a. PAID HOLIDAYS: New Year's Day; Memorial Day;

Independence Day; Labor Day; Thanksgiving Day; Christmas

Day provided employee works the day before and the day after the holiday.

TUNNEL AND SHAFT CLASSIFICATIONS

GROUP A1: Crane (underground), front end loader (tunnel and shaft), hoist (2 or 3 drum), maintenance engineer (tunnel and shaft), mining machine (mole and similar types), motor man, mucking machine, shovel, tripper/maintenance engineer

(tunnel and shaft), tunnel shovel

GROUP B: automated central mix concrete plant, backhoe

(topside), boring machine, compressors (4 or less, exceeding 2,000 C.F.M. combined capacity, but not to exceed

5,000 C.F.M. with a distance not to exceed 1,500 feet), concrete pump, crane (topside, front end loader (topside), Grayco epoxy machine, hoist (2 or 3 drum -- topside), maintenance engineer (topside), maintenance grease man, personnel hoist, pump crete, shotcrete machine, shovel

(topside)

GROUP C: comrpessors (4 not to exceed 2,000 C.F.M. combined capacity or 3 or less with more than 1,200 C.F.M. but not to exceed 2,000 C.F.M. with a distance for compressors), dust collectors, generators, pumps, welding machines (4 of any type or combination) with a distance not to exceed

1,500 feet; conveyor, electric pump used inconjunction with well point system grout pump over 5 cubic feet

(manufacturer's rating), hydro-blaster, motorized form carrier, truck crane oiler, well point

GROUP D: Compressors (3 or less not to exceed 1,200 C.F.M.

combined capacity with a distance not to exceed 1,500 feet;

comrpessors (any size but subject to other provisions for compressors), dust collectors, generators, pumps, welding machines (three or less of any type or combination) with a distance not to exceed 1,500 feet; fireman, grease man, IRON0009-003 05/01/2012

Ironworkers:

IRONWORKER..................$ 28.97 20.98

SHEETER.....................$ 31.87 20.98

LABO0091-002 07/01/2012

Laborers:

COMPRESSED AIR

GROUP 1....................$ 24.50 28.46+a

GROUP 2....................$ 28.17 28.46+a

GROUP 3....................$ 29.40 28.46+a

GROUP 4....................$ 30.62 28.46+a

GROUP 5....................$ 31.85 28.46+a

GROUP 6....................$ 33.07 28.46+a

HEAVY & HIGHWAY

CLASSIFICATIONS

GROUP 1....................$ 24.50 28.46+a

GROUP 2....................$ 24.80 28.46+a

GROUP 3....................$ 25.00 23.96+a

GROUP 4....................$ 25.10 28.46+a

GROUP 5....................$ 25.35 28.46+a

GROUP 6....................$ 25.50 28.46+a

GROUP 7....................$ 26.50 28.46+a

GROUP 8....................$ 26.95 28.46+a

GROUP 9....................$ 29.50 28.46+a

TUNNEL FREE AIR

CONSTRUCTION

GROUP 1....................$ 24.50 28.46+a

GROUP 2....................$ 26.59 28.46+a

GROUP 3....................$ 28.17 28.46+a

GROUP 4:...................$ 29.40 28.46+a

GROUP 5:...................$ 46.59 28.46+a

LABORERS CLASSIFICATIONS

GROUP 1: Common Laborers, Multi-Trade Tender, Decontamination of all Machines, Horizontal Directional

Drill/Locator; All terrain Vehicles with Attachments/All wheel or Track Types

GROUP 2: Potman, Pipelayers, Pavement Breakers or Busters, Jackhammer Operators; Barco Rammers; Chain Saw; Powder

Monkey; Black Top Rakers; Scalers; Drill Tenders; Mortar

Mixers; Concrete Polishing Machine; Operation & Maintenance of all Robotic Remote Systems in Hazardous Environment; Men

Working from Swinging Scaffold Bo'sns Chair, suspended cage or bucket; All Other Operators of Mechanical Tools, Including Vibrators Regardless of Type of Power and Boat

Men; Operation of All Types of Video Machinery Used in the

Inspection of Pipe; Work in Caissons below 8 feet; Concrete

Motor Buggy

GROUP 3: Respirator Required for Busting

GROUP 4: Form Setter; Road Finisher; Gunnite Nozzleman;

Sandblasters; Burning Torch; Concrete Saw Operators;

Utility Pile Driver; Tree Topper; Grout Machine and Grout

Pump Operator

GROUP 5: Laser Beam Operator

GROUP 6: Welders; Wagon Drill & Air Track Drill; Self

Contained Drill; Respirator Required due to Atmospheric

Conditions (Excluding Respirators Required for Hazardous

Waste & Toxic Materials, Asbestos Abatement or Lead

Abatement)

GROUP 7: Chemical Waste - Men Working with Hazardous Waste &

Toxic Materials or in Areas of Radioactive Material &

Asbestos; The Removal of Asbestos from Roofs, Ceilings, Pipes, Walls, Boilers etc., and All Machinery, & the

Recovering of Same; Removal of Lead

GROUP 8: Grade Checker & Blaster

GROUP 9: Supplied Air Respirators

For TUNNEL FREE AIR CLASSIFICATIONS

GROUP 1: General Laborer; Mole Nipper (one per shift); Top

Laborer

GROUP 2: Tenders for Divers

GROUP 3: Tunnel Workers; Miners; Drill Runners; Conveyor

Men; Powder Carriers; Chuck Tenders; Trackmen; Nippers;

Burners; Brake Men; Derail Men; Cable Men; Hosemen; Grout

Men; Gravel Men; Form Men; Bottom Bell; Top Bell; Signal

Men; Movers; Shaft Men; Tunnel Laborers

GROUP 4: Blasters; Welders; Steel Erectors; Piledrivers;

Riggers; Ironmen

GROUP 5: Divers

For COMPRESSED AIR CLASSIFICATIONS

GROUP 1: Top Laborers

GROUP 2: Top Bell; Signal Men; Shaft Men; Outside Man; Lock

Tender; Gauge Tender; Outside Muck Lock Tender

GROUP 3: Top Nipper

GROUP 4: Bottom Bell; Mole Nippers per Working Shaft per

Shift up to and Including Two Moles

GROUP 5: All Tunnel Workers Including Miners; Drill Runners;

Ironmen; Muck Men; Inside Mucklock Tender; Pumpmen;

Hydrualic Men; Shield Drivers; Monorail Operators;

Motormen; Conveyor Men; Powdermen; Pan Men; Chuck Tenders;

Track Men; Nippers; Brakemen; Derail Men; Cable Men; Hose

Men; Grout Men; Gravel Men; Tunnel Laborers

GROUP 6: Blasters; Mucking Machine Operators

FOOTNOTE: a. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day Labor Day, Thanksgiving Day, Christmas

Day, and Election Day

PAIN0004-002 05/01/2012

TOWNSHIPS OF HARTLAND, LOCKPORT NORTH TONAWANDA, NEWFANE,

PENDLETON, ROYALTON, SOMERSET and the eastern halves of

CAMBRIA and WILSON

Painters: (HEAVY & HIGHWAY

CONSTRUCTION)

CONSTRUCTION

BRIDGES....................$ 35.70 20.85

PAINTERS

BRUSH & ROLLER.............$ 24.68 19.51

DRYWALL/TAPING.............$ 25.18 19.51

WALLCOVERING...............$ 24.93 19.51

PAIN0004-005 05/01/2012

TOWNSHIPS OF LEWISTON, NIAGARA FALLS, PORTER, WHEATFIELD and the western halves of CAMBRIA and WILSON

Painters:

CONSTRUCTION

Bridge Painting............$ 35.70 20.85

Lead Abatement..............$ 25.43 15.30

Painters....................$ 24.68 15.30

Spraying, Paperhangers, Sand-Blasting, Swinging scaffold....................$ 24.93 15.30

Tapers......................$ 25.18 15.30

PAIN0004-011 05/01/2012

GLAZIER..........................$ 24.60 16.62

PLAS0111-002 07/01/2011

CEMENT FINISHER..................$ 27.00 25.42

PLUM0022-005 05/01/2012

Plumber and Steamfitter

ZONE 1......................$ 31.38 20.03

ROOF0074-002 06/01/2011

Roofers:

Composition.................$ 25.00 16.18

Slate & Tile................$ 25.15 16.18

SFNY0669-001 01/01/2013

SPRINKLER FITTER.................$ 29.83 20.42

SHEE0071-002 05/15/2011

Sheet metal worker...............$ 31.50 17.45

TEAM0449-003 07/01/2012

Heavy & Highway

Truck drivers:...................$ 31.24 4.85+a+b

Work on a hazardous waste site then additional $2.00 per hour.

FOOTNOTE: a. Pension $43.60 per day

b. Paid Holidays: New Years Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day, Christmas Day provided the employee has worked the working day before and after the holiday

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION