Attch 1. MN ARB PWS-POL Rv. 1.pdf
PDF 378 KB Posted
- Attached to
- Cleaning, Inspection, and Hazardous Waste Removal for Two 10,000-Gallon Oil/Water Separators
- Solicitation number
- FA663327QA001
About this file
This is a Performance Work Statement (PWS) for cleaning, inspection, and hazardous waste removal services for two 10,000-gallon Oil/Water Separators (OWS) at the Minneapolis-St. Paul Air Reserve Base POL facility. The contractor must complete all work within 60 calendar days from contract award, working Monday through Friday from 0600 to 1630 hours, excluding Federal holidays, with any outside-hours work requiring prior written approval from the Contracting Officer's Representative (COR). The contractor shall provide all personnel, equipment, tools, materials, vehicles, and supervision necessary to perform complete cleaning, inspection, and waste disposal operations in compliance with Small Quantity Generator (SQG) environmental standards and Air Force environmental compliance policies.
The specific work scope includes: performing pre-cleaning hazardous waste testing on all separator contents (floating materials, liquids, and sludge); if hazardous materials are detected, immediately terminating work and notifying the COR and environmental office; if contents are non-hazardous, pumping and completely evacuating all oil, oil residue, sludge, and waste from both separators without discharge to environment, sanitary sewer, or stormwater systems; thoroughly washing and cleaning separator interiors with all secondary wash water captured and containerized; removing, cleaning, and fully drying reusable coalescing media and internal filters; conducting comprehensive structural inspections documenting vault integrity, internal components, seals and gaskets, and plumbing/valve conditions; refilling separators with clear water to re-establish operational seal; and managing all waste transport and disposal through certified hazardous waste transporters to RCRA-permitted Treatment, Storage, and Disposal Facilities. Deliverables include a Service and API 421 Inspection Report detailing findings and OWS unit condition, and initial and final Hazardous Waste Manifests with tracking documents. All contractor personnel handling hazardous waste must possess current HAZWOPER training certification per 40 CFR Part 262, Subpart A and DAFMAN 32-7002, and must comply with installation security requirements including obtaining gate passes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SITE VISIT QUESTIONS.pdf | ||
| Vendor questions Rv1.pdf | ||
| Vendor questions.pdf | ||
| Attch 3. CLS provisions & Clauses Rv1.pdf | ||
| 20261021 Combo RV1.pdf | ||
| Picture2.png | PNG image | |
| Picture4.jpg | JPG image | |
| Attch 1. MN ARB PWS-POL.pdf | ||
| Attch 5. OWS 2 - Bldg 606.pdf | ||
| Attch 3. CLS provisions & Clauses.pdf | ||
| Attch 2. WD 2015-4945 RV 33.pdf | ||
| Attch 4. OWS 1 - Bldg 602.pdf | ||
| Picture1.jpg | JPG image | |
| Picture3.jpg | JPG image | |
| Picture5.jpg | JPG image |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
Performance Work Statement (PWS)
Cleaning, Inspection, and Hazardous Waste Removal for Two 10,000-Gallon Oil/Water Separators
1.0 Scope of Work
The contractor shall provide all personnel, equipment, tools, materials, vehicles, supervision, and other items and services necessary to perform the complete cleaning, inspection, and waste disposal for two (2) 10,000-gallon Oil/Water Separators (OWS) located at the POL facility. The installation operates as a Small Quantity Generator (SQG), and all waste management must comply with applicable SQG environmental standards and Air Force environmental compliance policies.
1.1 Location: Minneapolis-St. Paul ARB / POL facility
1.2. Period Of Performance
The total period of performance shall not exceed 60 calendar days from the date of contract award. All on-site work and final waste disposal must be completed within this timeframe.
1.3 Work Hours
Normal work hours are Monday through Friday, 0600 to 1630, excluding Federal holidays.
Work outside these hours requires prior written approval from the Contracting Officer's
Representative (COR).
2.0 Applicable Directives and References
The contractor shall comply with all applicable federal, state, and local laws, as well as Air
Force and industry regulations, including but not limited to:
• Occupational Safety & Health Administration (OSHA):
o 29 CFR 1910, Occupational Safety and Health Standards o 29 CFR 1910.120, Hazardous Waste Operations and Emergency Response
(HAZWOPER)
o 29 CFR 1910.146, Permit-Required Confined Spaces
• Environmental Protection Agency (EPA):
o 40 CFR Part 279, Standards for the Management of Used Oil o 40 CFR Part 112, Oil Pollution Prevention o 40 CFR Part 110, Discharge of Oil o 40 CFR Parts 260-282, Hazardous Waste
• Department of Transportation (DOT):
o 49 CFR Parts 171-180, Hazardous Materials Regulations
• Department of the Air Force Manual (DAFMAN):
o DAFMAN 32-7002, Environmental Compliance o DAFI 91-203, Air Force Consolidated Occupational Safety Instruction
• State & Local:
o Minnesota Rules, Chapter 7045, Hazardous Waste
2.1 Spills
Spill protection is required by the contractor. The contractor shall carry spill supplies such as absorbent material capable of emergency cleanup of spills or drips. In the event of a spill, the contractor shall notify the Contracting Officer’s Representative (COR) as soon as it is safe to do so.
3.0 Specific Tasks and Performance Requirements
3.1 Pre-Cleaning Sampling and Testing
Prior to any cleaning and pumping operations, the contractor shall perform appropriate tests of the OWS contents (including floating materials, liquids, and sludge) to determine if the materials meet the criteria for hazardous waste.
• Hazardous Contingency: If tests indicate the presence of hazardous materials, the contractor shall immediately terminate servicing and contact the COR and the installation environmental office. The environmental office will determine the subsequent requirements for the disposal of hazardous contents.
3.2 Pumping, Evacuation, and Packaging
If the contents are confirmed as non-hazardous, the contractor shall proceed with the cleaning operations. The contractor shall pump all oil, oil residue, sludge, and other waste from both 10,000-gallon separators, draining them completely.
• Discharge Prohibition: In accordance with DAFMAN 32-7002 and related local supplements, the contractor shall not discharge any OWS residue, wash water, or industrial waste to the environment, sanitary sewer, or stormwater sewer systems under any circumstances without explicit written approval from the Installation
Environmental Office.
• Waste Disposal: The contractor shall be responsible for the safe transport and legal disposal of all waste. Disposal must occur at an approved off-base facility in accordance with environmental regulations.
3.3 Cleaning Procedures
The contractor shall thoroughly wash and clean the interior of the separators. Any reusable coalescing media or internal filters must be carefully removed, cleaned, and fully dried before reinstallation. All secondary wash water generated during this process must be captured, containerized, and managed in accordance with Section 3.2.
While the separators are empty and clean, the contractor shall conduct a comprehensive inspection of the structural integrity and functionality of all system components.
The contractor shall provide a detailed report of the items inspected.
3.4 Inspection Report
The inspection protocol must include:
• Structural Integrity: Inspection of the vault bottom and walls for cracks, leaks, corrosion, and overall structural degradation.
• Internal Components: Checking the condition and alignment of coalescing plate packs, baffles, and skimmer mechanisms.
• Seals and Gaskets: Inspecting all access ports, hatches, and pump seals for degrading gaskets.
• Plumbing and Valves: Inspecting associated transfer pumps, effluent pumps, and non-return (check) valves.
3.5 System Restoration
Following the washing and inspection phase, the contractor shall refill the separators with clear water to re-establish the proper operational seal, ensuring no residue is flushed into the discharge line during restart. The Government will provide access to an on-site water source at no cost to the Contractor for the purpose of refilling the OWS units after cleaning. The Contractor shall be responsible for providing all necessary hoses, fittings, and conveyances to transport water from the source to the OWS.
3.6 Non-Hazardous and Hazardous Waste Tracking and Disposal (DAFMAN 32-7002 Compliance)
If the waste material is hazardous, the contractor shall utilize a certified hazardous waste transporter to safely remove the containerized waste from the installation.
• Tracking/Manifesting: The contractor must prepare the EPA Uniform Hazardous
Waste Manifest utilizing the base's SQG EPA ID number. In no event shall the contractor sign the manifest. Only a COR with active manifest-signing certification shall sign the manifest.
Disposal: The waste must be transported to a fully permitted Resource
Conservation and Recovery Act (RCRA) Treatment, Storage, and Disposal Facility
(TSDF).
4.0 Deliverables
• 4.1 Service and API 421 Inspection Report: The contractor shall provide a written report to the Contracting Officer Representative (COR) detailing the inspection findings, the condition of the OWS units.
• 4.2 Hazardous Waste Manifests & Tracking Documents: The contractor must submit the initial signed Uniform Hazardous Waste Manifests upon departure from the base and provide the final TSDF-signed return-to-generator manifests to the base environmental office within the required timeframe for SQGs. Additionally, any waste tracking documents related to non-hazardous waste shall be submitted to the COR.
5.0 Security and Safety Requirements
• 5.1 Training Certification: In accordance with DAFMAN 32-7002, all contractor personnel handling hazardous waste must have successfully completed HW training appropriate to their job responsibilities as required by 40 CFR Part 262, Subpart A (e.g., HAZWOPER) prior to executing this work.
• 5.2 Installation Security: All contractor personnel must adhere to installation security requirements, including obtaining necessary gate passes and maintaining a safe working environment. All on-site work, including mobilization and demobilization of equipment, shall be performed between the hours of 0600 and
1630, Monday through Friday, excluding Federal Holidays.
| CUI |
| Performance Work Statement (PWS) |
| 1.0 Scope of Work |
| 2.0 Applicable Directives and References |
| • Occupational Safety & Health Administration (OSHA): |
| • Environmental Protection Agency (EPA): |
| • Department of Transportation (DOT): |
| • Department of the Air Force Manual (DAFMAN): |
| • State & Local: |
| 2.1 Spills |
| 3.0 Specific Tasks and Performance Requirements |
| 3.2 Pumping, Evacuation, and Packaging |
| The contractor shall thoroughly wash and clean the interior of the separators. Any reusable coalescing media or internal filters must be carefully removed, cleaned, and fully dried before reinstallation. All secondary wash water generated during this ... |
| While the separators are empty and clean, the contractor shall conduct a comprehensive inspection of the structural integrity and functionality of all system components. |
| The contractor shall provide a detailed report of the items inspected. |
| 3.4 Inspection Report |
| 3.5 System Restoration |
| 3.6 Non-Hazardous and Hazardous Waste Tracking and Disposal (DAFMAN 32-7002 Compliance) |
| 4.0 Deliverables |
| 5.0 Security and Safety Requirements |