RFI 001_Repair Airfield Pavement Crack Seal_signed.pdf
PDF 409 KB Posted
- Attached to
- Repair Airfield Pavement Crack Seal
- Solicitation number
- FA660626B0002
About this file
This is a Request for Information (RFI) report documenting contractor questions and government responses regarding Air Force contract FA6606-26-B-0002 for Repair Airfield Pavement Crack Seal, project YTPM 25-3002. The RFI was requested by 439 CONF/PKB for KTR(s) on 20 March 2026 and addresses clarifications on work specifications and execution requirements.
The five questions and responses cover critical project details: (1) the "not-to-exceed" refers to joint seal products as defined in SOW sections 1.B and 2.D; (2) joint sealant repairs must use hot-applied crack sealant conforming to ASTM D6690 per UFC 3-270-01, not cold-applied asphalt sealing; (3) the bid schedule is priced in linear feet (LF), derived from average crack width per gallon calculations per SOW section 2.D; (4) normal working hours are 7:30 am to 4:15 pm Monday through Friday excluding federal holidays, with contractors requiring seven days' advance written notice for work outside these hours; and (5) on the East Ramp, contractors will access the asphalt area adjacent to the concrete ramp with security barriers either moved for free access or remaining in place with contractor escort behind the restricted area line. The document notes that RFI responses do not authorize additional work and contractors must notify the Contracting Officer's Representative if responses constitute changed conditions.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION REPORT (RFI)
RFI (Preaward) NO. PAGE NO.
SOLICITATION TITLE:
Contractor's Request for Information
REQUESTED BY: Potential Cost Impact
[No] Potential Schedule
Impact [No]SUBCONTRACTOR
RFI
SUBJECT:
DRAWINGS
INFORMATION REQUESTED:
ATTACHMENTS FROM CONTRACTOR: (1 attachment)
NOTE: THE RFI SYSTEM IS INTENDED TO PROVIDE AN EFFICIENT MECHANISM FOR RESPONDING TO CONTRACTOR'S REQUESTS FOR
INFORMATION. IT DOES NOT PROVIDE AUTHORITY TO PROCEED WITH ADDITIONAL WORK. IF THE CONTRACTOR CONSIDERS
THE RFI RESPONSE A CHANGED CONDITION, PROVIDE WRITTEN NOTICE TO THE CONTRACTING OFFICER'S REPRESENTATIVE
IN ACCORDANCE WITH CONTRACT PROVISIONS.
QA REVIEWER'S SIGNATURE DATE
RFI FORM
SOLICITATION NO:
FA6606-26-B-0002 Repair Airfield Pavement Crack Seal YTPM 25-3002
DATE REQUESTED:
20 MARCH 2026
QUESTION 01: Is the "not-to-exceed" referring to a concrete joint seal product?
WARB RESPONSE 01: Please read the SOW; 1.B, 2.D
QUESTION 02: Are the joint sealant repairs to be cold-applied or hot-poured asphalt sealing, meeting the ASTM D6660 material specification?
WARB RESPONSE 02: Use crack sealant conforming to ASTM D6690, Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements. Per UFC 3-270-01
QUESTION 03: Is the work listed as LF (amount of work performed) or LBS/TONS for material used?WARB
RESPONSE 03: The bid schedule is in LF. The LF is derived from using an average crack width per gallon.
Read section 2.D of the SOW.
QUESTION 04: What are the work hours, and are weekends available for work to be performed?
WARB RESPONSE 04: The normal working hours for contractors are between 7:30 am (0730) and 4:15 pm
(1615) Monday through Friday, excluding federal holidays. Contract work in the project area(s) will be available during this time, but may be interrupted by mission operations and requirements. The Contractor may desire or need to perform work during hours or days other than the hours or workdays stated, he shall submit a written request seven (7) days prior to required start of work.
QUESTION 05: What access will the contractor be given when working on the East Ramp?
WARB RESPONSE 05: The contractor will be granted access to the asphalt area adjacent to the concrete ramp.
Security barriers will either moved to allow for free access or the barriers shall remain and the contractor will be escorted during the duration of the work behind the restricted area line.
PROJECT NAME:
439 CONF/PKB for KTR(s)
| RFI_HGC_0001_10.Aug.2020 |
| RFI_HGC_0001_10.Aug.2020_2 |
| 2026-03-20T08:56:06-0400 | |
| OWEN.GEORGE.R.JR.1051532267 |
File details come from the government source that posted it. Updated .