Solicitation_Amendment_FA660619RA0050001_SF_30.pdf

PDF 525 KB Posted

Attached to
Taxiway G & East Ramp, Joint Repair
Solicitation number
FA660619RA005
Issued by

About this file

Amendment to change POP

View the file

Other files

File Type Posted
RFI_001_Taxiway_G_20190815_P1_of_2.pdf PDF
RFI_001_Taxiway_G_20190815_P2_of_2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section B - Supplies or Services & Prices or Costs

The following CLIN(s) / SLIN(s) were modified:

0001 - EAST RAMP REPAIR PROJECT YTPM 14-0021

Contractor shall provide all materials, labor, equipment, tool and incidentals necessary to complete all work as identified in the Specs, drawings, and attachments in association with this solicitation

INFORMATION FROM TO

Product/Service Personal Property Services

0002 - REPAIR TAXIWAY GOLF PROJECT YTPM 19-3002

Contractor shall provide all materials, labor, equipment, tool and incidentals necessary to complete all work as identified in the Specs, drawings, and attachments in association with this solicitation

INFORMATION FROM TO

Product/Service Personal Property Services

Section F - Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) were modified:

0001 - EAST RAMP REPAIR PROJECT YTPM 14-0021

Contractor shall provide all materials, labor, equipment, tool and incidentals necessary to complete all work as identified in the Specs, drawings, and attachments in association with this solicitation

Place of Performance - F5N3FQ - 439 MSG CEC

INFORMATION FROM TO

Delivery 350 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

390 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

0002 - REPAIR TAXIWAY GOLF PROJECT YTPM 19-3002

Contractor shall provide all materials, labor, equipment, tool and incidentals necessary to complete all work as identified in the Specs, drawings, and attachments in association with this solicitation

Place of Performance - F5N3FQ - 439 MSG CEC

INFORMATION FROM TO

Delivery 350 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

390 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

FA660619RA0050001

The following clauses were modified:

52.211-10 - Commencement, Prosecution, and Completion of Work. Mar 1984 hereby reads as follows:

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction. Commencement, Prosecution, and Completion of Work (Apr 1984) The Contractor shall be required to (a)commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b)prosecute the work diligently, and (c)complete the entire work ready for use not later than 390

CALENDAR DAYS (NOT INCLUDING WINTER SHUTDOWN PERIODS OF 01 DECEMBER

THROUGH 31 MARCH) FROM RECEIVING NOTICE TO PROCEED.* The time stated for completion shall include final cleanup of the premises. * The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

FA660619RA0050001

IDCode:
Page: 1
Pages: 3
AmendNo: 0001
EffDate: 8/20/2019
ReqNo: F5N3FQ8346AW01
ProjNo: YTPM 14-0021/19-3002
IssCode: FA6606
AdmCode:
IssuedBy: FA6606 439 CONF LGC

BLDG 2400 CP 413 557 3508

250 AIRLIFT DR

WESTOVER AFB, MA 01022-1507

United States Amy Dumais, Email: amy.dumais@us.af.mil Telephone: 413-557-3110

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA660619RA005
SolDate: 7/23/2019
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt:
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: 1
Require:
Copies:
Descript: The purpose of this Amendment to Solicitation to FA6606-19-R-A005 is to change the period of performance from 350 calendar days to 390 calendar days not including the winter shutdown periods of 01 December through 31 March.

CLINS 0001 and 0002 as well as FAR clause 52.211-10 have been updated to reflect this change.

All other items of the solicitation remain unchanged and in full force.

ContNameTitle:
CoNameTitle: Debra F. Scarborough

Email: debra.scarborough@us.af.mil Telephone: 4783271616

ContDate:
CODate:

File details come from the government source that posted it.