This document is a Performance Work Statement (PWS) appendix that details the contractor's submittal requirements for the maintenance and repair of fire protection systems at Aviano and Ghedi Air Bases in Italy. The key requirements include weekly, monthly, and quarterly ITM (Inspection, Testing, and Maintenance) service reports, smoke detector cleaning reports, part history summaries, work order trackers, and various other metrics and operational plans. The submittals must be provided on specific timelines, ranging from the start of service to 10 working days after contract award. The contract opportunity is a pre-solicitation notice for a firm-fixed price contract for fire protection system maintenance and repair services to be acquired using FAR Part 12 procedures for commercial items, with FAR Part 13 Simplified Acquisition Procedures governing the competitive acquisition process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX D
MAINTENANCE AND REPAIR OF FIRE PROTECTION SYSTEMS
AT AVIANO AND GHEDI ABs, ITALY
Q.ty
158 every week
421 every 6 months
N/A
N/A
Note:
‐ ITM service reports (see above table)
‐ Smoke detector cleaning reports
‐ Part History Summary
‐ Work Order Tracker
‐ Metrics
PWS
paragraph 2.1
4.2.3
4.2.2
1.3.1.2.3
1.3.1.2.3
4.4
1.4.2
1.3.1.4
1.5.3.3
1.3.2.2
1.3.3.4
4.2.1
1.3.1.5
1.3.1.3
4.4.3.1
To be submitted no later than the day that the service starts
Timing
To be submitted no later than the day that the service starts
To be submitted no later than the day that the service starts
To be submitted no later than the day that the service starts
To be submitted no later than the day that the service starts
To be submitted with the Bid proposal
To be submitted with the Bid proposal
To be submitted no later than five (5) working days after contract award
To be submitted with the Bid proposal
To be submitted at least ten (10) working days prior to the intended use of the hazardous material
CONTRACTOR'S SUBMITTALS
ITM service report forms
Notification signs
Quality Control Plan (QCP)
Submittal type
SDS (safety Data sheet)
ITM service schedule
Operational Safety Plan
Contractor contact information
Organizational chart
Emergency request service report form
Extraordinary Maintenance request service report form
To be submitted awardright after the pre‐performance meeting or within ten (10) working days after contract award, whichever is first
(*) Every month there will be a week where the contractor will delivery 158 Monthly ITM reports instead of the Weekly ones. Every 13 weeks, the contractor will delivery 158 Quarterly ITM reports instead of the Weekly or Monthly ones.
WEEKLY SUBMITTALS
to be submitted by 16:00 on the second working day of each following week
The number of the ITM reports can change depending on the ITM forms that the contractor will submit.
For Example, in buildings where the Standpipe Hoses are connected to the distribution line of the Wet Sprinkler System, it is acceptable to have a single ITM combo‐report for both of them ether to have two separate ITM reports.
OTHER SUBMITTALS
To be submitted no later than the day that the service starts
To be submitted no later than the day that the service starts
To be submitted with the Bid proposal
Employee Qualifications
Employee D‐21 Qualification Schedule
(if not already qualified and certified)
Updated Appendix C
Employee D‐21 Qualification (if available)
Metrics form To be submitted no later than the day that the service starts
Emergency Request Service Reports
Extraordinary Maintenance Request Service Reports
Semiannual/Annual ITM reports
Weekly* ITM reports