Project # ASHE 17-1015 A#1 Technical Specifications DATE: May 2018
31CES/CENM 1
TECHNICAL SPECIFICATIONS FOR
ASHE 17-1015
SUSTAIN MENSA PARKING LOT
AREA F, AVIANO AB, AVIANO (PN) ITALY
ADDENDUM #1
A1.1 Weeding, Change item 4.1 to read: “Weeding, the item consists of perform a mechanical manual weeding along the curbs (845 m), on the walkways (425 sm) and on the crossing pathways, the item includes the cleaning of the resulting vegetables and any other burden to have the area cleaned and a job performed in work man like manner.
Lump sum.
A1.2 Milling. Change item 4.4 to read: “The item consists of providing all the manpower and equipment to mill up to 15 cm asphalt paved area. Item includes pruning of about 9 high trees, putting pruning healing mastic on thick cut branches, to allow the machineries works without damaging the equipment or the trees breaching the branches, transportation to authorized dump and disposal of the resulting cut branches and of the milled material, any other burden to provide a job in a workmanlike manner.
4,788.00 Sq.m.
A1.3 Walkways maintenance and restoration, change item 4.13 to read: “The item consists of:
A1.3.1 wash with high pressure water all walkways (393 sm), curbs (845 m) and crossing paths (32 sm);
A1.3.2 Remove and partially reinstall the crossing pathways to raise the level of the pathway to have a bumper (about 32 sm);
A1.3.3 Furnishing and installation of about 40 SM of pavers of same type but white color to create walkway appearance about 50 cm wide every 50 cm regular color;
A1.3.4 Furnishing and installation of curbs regular size 6/8x25x100;
A1.3.5 Sand to increase the sand bed to reach a bumper height;
A1.3.6 Black and yellow paint on the curbs along the pathways (47 m);
A1.3.7 The item includes load on truck, transport and disposal in an authorized dump of the proven materials, all burden included to provide a job in a workmanlike manner.
Lump Sum
A1.4 Statement of work, Chapter 3 Work site condition point b. change to read: “Before works start, contractor will submit a detail works schedule and phasing plan (APPROXIMATELY FIVE PHASES) to C.O. for coordination and approval at least two weeks before starting the field works”;