ASHE_18-1072_SUSTAIN_INDOOR_FIRING_RANGE_Question_and_Answer.pdf

PDF 104 KB Posted

Attached to
ASHE 18-1072 SUSTAIN INDOOR FIRING RANGE
Solicitation number
FA568218R0022
Issued by

About this file

Questions and Answers to concerns raised by vendors

View the file

Other files

File Type Posted
ASHE_18-1072_Add_1_draft.pdf PDF
FA568218R00220002.pdf PDF
FA568218R00220001.pdf PDF
ASHE_18-1072_CCEB.xls XLS spreadsheet
ADDITIONAL_REQUIREMENTS_March_2018.pdf PDF
ASHE_18-1072_Technical_Specifications_REV._1.pdf PDF
FA568218R0022.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASHE 18-1072 SUSTAIN INDOOR FIRING RANGE

BLDG 1433, AREA "F", AVIANO AB, ITALY

QUESTIONS AND ANSWERS VERSION-1

1. With reference to subject solicitation, this is to request extension of closing date since the remaining days are not enough to elaborate a design plan. Also, to provide a design plan it is necessary a dwg file version of building existing conditions. Could you please provide it?

The wording in the solicitation will be amended from design plan to diagram. The diagram simply needs to be a drawing or illistration of the effected rooms inside the Indoor Firing Range indicating the placement of the lights. Further, a short description will be included to describe the placement of the lights to include what the lights will be asfixed to, as well as, the types of lights/bulbs to be used.

See amendment for timeline extension.

2. As per OFFEROR INSTRUCTION L-01 – 1. TECHNICAL ACCEPABILITY – 1.

TECHNICAL DATA, a schedule for completion of all work is requested. Could you please explain what is it intended for?

The closing the indoor firing range requires coordination by the customer. This solicitation requires the contractor to provide a schedule indicating how long it will take to conduct the different aspects of the work (example: floors-5 days, lights-7 days) and how many days it will take to complete all work (example: total-15 days). The intent of this section is to provide the Government a timeline and planning document to track timelines for range closure.