Computo

CONSTRUCTION COST ESTIMATE BREAKDOWN REVISION 1
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
SUSTAIN FIRE TRAINING AIRCRAFT MOCKUP / RISTRUTTURAZIONE AREA SIMULAZIONE INCENDI VELIVOLI
PURCHASE REQUEST NUMBERPROJECT NUMBERWORK LOCATION
ASHE 16-1043AREA F - AVIANO AIR BASE, ITALY
MATERIAL COSTSLABOR COSTS
LINE NO.ITEMUNIT OF MEASUREQUANTITYUNITTOTALMANHOURS MANDAYSAVERAGE RATETOTALOTHER DIRECT COSTSLINE TOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni
Ia Structural and Civil Demolition Work - Ia Demolizioni Lavori Strutturali e Civili
1DEMOLITION OF AIRCRAFT STEEL STRUCTURE
Demolizione della struttura di acciaio del simulacro di aereoIT. No. Art. n.1Ls/Ac
2REMOVAL OF STEEL CONTROL STAND
Rimozione postazione di controllo in acciaioIT. No. Art. n.2Ls/Ac
3REMOVAL AND STORE OF GRAVEL MATERIAL
Rimozione ed accantonamento di ghiaiaIT. No. Art. n.3Cu.m/Mc
4TRENCH EXCAVATION ON BITUMINOUS PAVEMENT
Scavo in trincea pavimentazione in conglomerato bituminosoIT. No. Art. n.4aSq.m/Mq
5TRENCH EXCAVATION ON EARTH
Scavo in trincea per tubazioni di servizio su terraIT. No. Art. n.4bCu.m/Mc
6REMOVAL OF UNDERGROUND UTILITIES PIPINGS
Rimozione tubazioni sottoserviziIT. No. Art. n.5Ls/Ac
7EXCAVATION IN ANY KIND OF SOIL FOR NEW WATER RECIRCULATIO SYSTEM AND NEW GAS TANK YARD
Scavo in terreno per nuovo impianto ricircolo idrico nuova area deposito gplIT. No. Art. n.6Cu.m/Mc
8SLOT OPENING ON EXISTING CONCRETE STRUCTURE
Apertura asole su struttura in cls esistenteIT. No. Art. n.7Ls/Ac
9DEMOLITION OF UNDERGROUND UTILITIES MANHOLES
Demolizione di pozzetti utenze interrateIT. No. Art. n.8Ea/No
10DEMOLITION OF CONCRETE PAD AND BURIED TANK
Demolizione di basamento in cls e di serbatoio interratoIT. No. Art. n.9Ls/Ac
11DEMOLITION OF GAS TANK STORAGE AREA
Demolizione dell'area di deposito serbatoi gasIT. No. Art. n.10Ls/Ac
12SCARIFICATION OF BITUMINOUS CONCRETE PAVEMENT
Scarifica su pavimentazione in congl. BituminosoIT. No. Art. n.11Sq.m/Mq
Total Structural and Civil Demolition - Totale Demolizioni Strutturali e Civili
Ib Mechanical System Demolition - Ib Demolizione Impianti Meccanici
13NEUTRALIZATION OF ALL EXISTING LPG PIPING AND TANKS
Messa in sicurezza di tutte le tubazioni e serbatoi GPL esistentiIT. No. Art. n.12Ls/Ac
14REMOVAL OF VAPORIZER, VALVES, PIPING
Rimozione di vaporizzatore, valvole e tubazioni GPLIT. No. Art. n.13Ls/Ac
Total Mechanical Work - Totale Lavori Meccanici
Ic Electrical System Demolition - Ic Demolizioni Impianti Elettrici
NOT APPLICABLE/ Non applicabile
TOTAL PART I / Totale Parte I
Part II - STRUCTURAL AND CIVIL WORK / Parte II - Opere Strutturali e Civili
15CONSTRUCTION BURN AREA CONCRETE PAVEMENT
Costruzione pavimentazione in cls area incendioIT. No. Art. n.1Sq.m/Mq
16CONSTRUCTION OF WATER STORAGE TANK
Costruzione di vasca accumulo acquaIT. No. Art. n.2Ls/Ac
17GAS SEPARATOR TANK
Vasca separazione gasIT. No. Art. n.3Ls/Ac
18DRAINAGE FIELD CONSTRUCTION
Costruzione bacino di dispersioneIT. No. Art. n.4Ls/Ac
19HDPE LINED TRENCH - Apron
Trincea con rivestimento in pead - PiazzaleIT. No. Art. n.5aLm/Ml
20HDPE LINED TRENCH - BURN AREA
Trincea con rivestimento in pead - Area IncendioIT. No. Art. n.5bLm/Ml
21NEW GAS TANK STORAGE AREA
Nuova area deposito serbatoi GPLIT. No. Art. n.6Ls/Ac
22BOLLARDS FOR CONTROL STAND PROTECTION
Bitte removibili per protezione locale controlloIT. No. Art. n.7Ea/No
23FURNISH/INSTALL 3 MM DIA. COOPER WIRE
Fornitura e posa in opera di cavo di rame dia. 3mmIT. No. Art. n.8Lm/Ml
24FURNISH/INSTALL WARNING TAPE
Fornitura e posa in opera di nastro segnalatoreIT. No. Art. n.9Lm/Ml
25TRENCH BACKFILLING
Rinterro delle trinceeIT. No. Art. n.10Cu.m/Mc
26CONSTRUCT BITUMINOUS CONCRETE PAVEMENT
Costruzione di pavimentazione conglomerato bituminosoIT. No. Art. n.11Sq.m/Mq
273cm THICK WEARING COURSE ON SCARIFIED AREAS
Strato di usura, sp=3cm nelle zone scarificateIT. No. Art. n.12Sq.m/Mq
28C28/35 CONCRETE BASEMENT
Basamento in calcestruzzo C28/35IT. No. Art. n.13Ls/Ac
29RESTORE GRASS SEEDED AREAS
Ripristino aree a verdeIT. No. Art. n.14Sq.m/Mq
30CONTROL STAND RENOV. - PAINTING
Rinnovo della postazione di controllo - PitturazioneIT. No. Art. n.15aSq.m/Mq
31CONTROL STAND RENOV. - SUSPENDED CEILING
Rinnovo della postazione di controllo - ControsoffittoIT. No. Art. n.15bSq.m/Mq
32CONTROL STAND RENOV. - LIGHTING
Rinnovo della postazione di controllo - IlluminazioneIT. No. Art. n.15cEa/No
33CONTROL STAND RENOV. - WINDOWS RENOVATION
Rinnovo della postazione di controllo - Rinnovo infissiIT. No. Art. n.15dLs/Ac
34CONTROL STAND RENOV. - ELEC & MECH REMOVALS
Rinnovo della postazione di controllo - RimozioniIT. No. Art. n.15eLs/Ac
35CONTROL STAND RENOV. - WATER TANK
Rinnovo della postazione di controllo - Vasca idricaIT. No. Art. n.15fLs/Ac
36RESTORATION OF DRAINING GRAVEL AREA
Ripristino delle superfici drenanti in ghiaiaIT. No. Art. n.16Ls/Ac
37FIRE PREVENTION CERTIFICATE (CPI) Certificato di Prevenzione Incendi (CPI)IT. No. Art. n.17Ls/Ac
38PROJECT AS-BUILT
Elaborati As-Built del progettoIT. No. Art. n.18Ls/Ac
TOTAL PART II - Totale Parte II
PART III - MECHANICAL WORK / Parte III - Opere Meccaniche
IIIa Propane System - IIIa Impianto Propano
39LIQUID BURIED PROPANE PIPING WITH COATING AND FITTINGS - 1-1/2" (40 mm)
Tubazioni propano liquido interrate, incamiciate ed accessori - 1-1/2" (40 mm)IT. No. Art. n.1aLm/Ml00
40LIQUID BURIED PROPANE PIPING WITH COATING AND FITTINGS - 2" (50 mm)
Tubazioni propano liquido interrate, incamiciate ed accessori - 2" (50 mm)IT. No. Art. n.1bLm/Ml00
41VAPOR BURIED PROPANE PIPING AND FITTINGS - 1" (25 mm)
Tubazioni propano vapore interrate ed accessori - 3/4" (20 mm)IT. No. Art. n.2aLm/Ml00
42VAPOR BURIED PROPANE PIPING AND FITTINGS - 2" (50 mm)
Tubazioni propano vapore interrate ed accessori - 2" (50 mm)IT. No. Art. n.2bLm/Ml00
43PAINTED EXPOSED PROP. PIPING AND FITT.- 1" (25 mm)
Tubazioni prop. in vista verniciate ed accessori - 3/4" (20 mm)IT. No. Art. n.3aLm/Ml00
44PAINTED EXPOSED PROP. PIPING AND FITT.- 1-1/2" (40 mm)
Tubazioni prop. in vista verniciate ed accessori - 1-1/2" (40 mm)IT. No. Art. n.3bLm/Ml00
45PAINTED EXPOSED PROP. PIPING AND FITT.- 2" (50 mm)
Tubazioni prop. in vista verniciate ed accessori - 2" (50 mm)IT. No. Art. n.3cLm/Ml00
46PAINTED EXPOSED PROP. PIPING AND FITT.- 2-1/2" (65 mm)
Tubazioni prop. in vista verniciate ed accessori - 2-1/2" (65 mm)IT. No. Art. n.3dLm/Ml00
47STEEL BODY BALL VALVES AND FITTINGS - 3/4" (20 mm)
Valvole a sfera in acciaio ed accessori - 3/4" (20 mm)IT. No. Art. n.4aEa/No00
48STEEL BODY BALL VALVES AND FITTINGS - 1-1/2" (40 mm)
Valvole a sfera in acciaio ed accessori - 1-1/2" (40 mm)IT. No. Art. n.4bEa/No00
49STEEL BODY BALL VALVES AND FITTINGS - 2" (50 mm)
Valvole a sfera in acciaio ed accessori - 2" (50 mm)IT. No. Art. n.4cEa/No00
50STEEL BODY BALL VALVES AND FITTINGS - 2-1/2" (65 mm)
Valvole a sfera in acciaio ed accessori - 2-1/2" (65 mm)IT. No. Art. n.4dEa/No00
51HYDROSTATIC RELIEF VALVES AND FITTINGS PN40 - 3/4" (20 mm)
Valvole di sicurezza idrostatica PN40 ed accessori - 3/4" (20 mm)IT. No. Art. n.5Ea/No00
52INSULATION JOINTS AND FITTINGS PN40 - 3/4" (20 mm)
Giunti isolanti PN40 ed accessori - 3/4" (20 mm)IT. No. Art. n.6aEa/No00
53INSULATION JOINTS AND FITTINGS PN40 - 1-1/2" (40 mm)
Giunti isolanti PN40 ed accessori - 1-1/2" (40 mm)IT. No. Art. n.6bEa/No00
54INSULATION JOINTS AND FITTINGS PN40 -2" (50 mm)
Giunti isolanti PN40 ed accessori - 2" (50 mm)IT. No. Art. n.6cEa/No00
55LPG FEED-OUT VAPORIZER WITH EQUIPMENT AND FITTINGS
Vaporizzatore GPL tipo feed-out con accessoriIT. No. Art. n.7Ls/Ac00
56BOILER FOR LPG VAPORIZER WITH CABINET, EQUIPMENT AND FITTINGS
Gruppo termico per alimentazione vaporizzatore con accessoriIT. No. Art. n.8Ls/Ac00
57BURIED WATER PREINSULATED PEX-a De50x4,7 DN40 PIPING AND FITTINGS
Tubazioni idriche preisolate PEX-a De50x4,7 DN40 con accessoriIT. No. Art. n.9Lm/Ml00
58EXHAUST AIR SYSTEM FOR WATER STORAGE TANK AND GAS SEPARATOR WITH FAN, DUCTS AND FITTINGS
Sistema di estrazione aria da vasca di accumulo idrico e separatore di gas completo di ventilatore, canalizzazioni e accessoriIT. No. Art. n.10Ls/Ac00
59REMOVAL AND RECOLLOCATION OF EXISTING No.2 3000 LITERS LPG
Rimozione e ricollocazione di no.2 serbatoi esistenti GPL da 3000 litriIT. No. Art. n.11Ls/Ac00
IIIb Fire Protection System - IIIc Impianto Antincendio
60HDPE BURIED WATER PIPING PN16 AND FITTINGS- 110 mm
Tubazioni idriche interrate in PEAD PN16 e accessori- 110 mmIT. No. Art. n.12Lm/Ml0
61GATE VALVES AND FITTINGS PN16 - 3" (80 mm)
Valvole a saracinesca ed accessori PN16 - 3" (80 mm)IT. No. Art. n.13Ea/No0
62CHECK VALVES AND FITTINGS PN16 - 3" (80 mm)
Valvole di ritegno ed accessori PN16 - 3" (80 mm)IT. No. Art. n.14Ea/No00
63UNI70 HYDRANTS AND FITTINGS
Idranti UNI70 ed accessoriIT. No. Art. n.15Ea/No00
64UNI70 FIRE DEPARTMENT MOTOR PUMP CONNECTION
Attacco motopompa VVF UNI 70IT. No. Art. n.16Ea/No00
6570x70x120 CM PREFABRICATED REINFORCED CONCRETE PIT WITH HEAVY TRAFFIC CAST-IRON COVER
Pozzetto in calcestruzzo armato prefabbricato carrabile 70x70x120 cmIT. No. Art. n.17Ea/No00
66INSULATED METALLIC CABINET
Armadio metallico isolatoIT. No. Art. n.18Ea/No00
67Y Filter 3" (80 mm)
Filtro a Y 3" (80mm)IT. No. Art. n.19Ea/No00
68REDUCED AND CONTROLLED PRESSURE ZONE BACK FLOW PREVENTER PN16 AND FITTINGS- 3'' (80 mm) Disconnettore idaulico a zone di pressione ridotta e controllata PN16 e accessori - 3" (80 mm)IT. No. Art. n.20Ea/No00
69HEATING CABLE, INSULATION, ALU JACKET, ELECTRICAL CONNECTIONS AND ACCESSORIES Cavo scaldante, isolante, rivestimento in alluminio, alimentazione elettrica ed accessoriIT. No. Art. n.21Ls/Ac00
IIIc Water System - IIIc Impianto Idrico
70PREFABRICATED PRESSURIZATION SET WITH EQUIPMENT (CABINET, INVERTER, POWER AND CONTROL SWITCHBOARD ) AND FITTINGS
Gruppo pressurizzazione prefabbricato con equipaggiamento (cabinato, inverter, quadro alimentazione e controllo) e accessoriIT. No. Art. n.22Ls/Ac00
71HDPE BURIED WATER PIPING PN16 AND FITTINGS - De 25 mm
Tubazioni idriche interrate in PEAD PN16 ed accessori- De 25 mmIT. No. Art. n.23aLm/Ml00
72HDPE BURIED WATER PIPING PN16 AND FITTINGS - De 63 mm
Tubazioni idriche interrate in PEAD PN16 ed accessori - De 63 mmIT. No. Art. n.23bLm/Ml
73HDPE BURIED WATER PIPING PN16 AND FITTINGS - De 110 mm
Tubazioni idriche interrate in PEAD PN16 ed accessori- De 110 mmIT. No. Art. n.23cLm/Ml
74HDPE BURIED WATER PIPING PN16 AND FITTINGS - De 125 mm
Tubazioni idriche interrate in PEAD PN16 ed accessori- De 125 mmIT. No. Art. n.23dLm/Ml
75HDPE BURIED WATER PIPING PN16 AND FITTINGS - De 160 mm
Tubazioni idriche interrate in PEAD PN16 ed accessori- De 160 mmIT. No. Art. n.23eLm/Ml
76GATE VALVES AND FITTINGS - 3/4" (20 mm)
Valvole a saracinesca ed accessori - 3/4" (20 mm)IT. No. Art. n.24aEa/No
77GATE VALVES AND FITTINGS - 1-1/2" (40 mm)
Valvole a saracinesca ed accessori - 1-1/2" (40 mm)IT. No. Art. n.24bEa/No
78BALL VALVES AND FITTINGS - 3" (80 mm)
Valvole a sfera ed accessori - 3" (80 mm)IT. No. Art. n.25Ea/No
79Y Filter 1/2" (15 mm)
Filtro a Y 1/2" (15 mm)IT. No. Art. n.26Ea/No
80REDUCED AND CONTROLLED PRESSURE ZONE BACK FLOW PREVENTER PN16 AND FITTINGS - 1/2'' (15 mm) Disconnettore idaulico a zone di pressione ridotta e controllata PN16 ed accessori- 1/2" (15 mm)IT. No. Art. n.27Ea/No
81WATER PRESSURE REGULATOR/MAKE-UP WATER DEVICE AND FITT.-1/2" (15mm)
Gruppo di riempimento con accessori- 1/2" (15 mm)IT. No. Art. n.28Ea/No
82GALVANIZED STEEL WATER PIPING WITH 50x6,5 mm SLOTS AND FITTINGS- 4" (100 mm) Tubazioni idriche acciaio zincato con aperture 50X6,5 mm ed accessori- 4" (100 mm)IT. No. Art. n.29Lm/Ml
8370x70x120 CM PREFABRICATED REINFORCED CONCRETE PIT WITH HEAVY TRAFFIC CAST-IRON COVER
Pozzetto in calcestruzzo armato prefabbricato carrabile 70x70x120 cmIT. No. Art. n.30Ea/No
84FLOAT VALVES AND FITTINGS - 3" (80 mm)
Valvole a galleggiante ed accessori - 3" (80 mm)IT. No. Art. n.31Ea/No
85TRANSITION JOINTS HDPE/GALVANIZED STEEL- DN20
Giunti di transizione PEAD/acciaio zincato- DN20IT. No. Art. n.32aEa/No
86TRANSITION JOINTS HDPE/GALVANIZED STEEL- DN40
Giunti di transizione PEAD/acciaio zincato- DN40IT. No. Art. n.32bEa/No
87TRANSITION JOINTS HDPE/GALVANIZED STEEL- DN80
Giunti di transizione PEAD/acciaio zincato- DN80IT. No. Art. n.32cEa/No
88TRANSITION JOINTS HDPE/GALVANIZED STEEL- DN100
Giunti di transizione PEAD/acciaio zincato- DN100IT. No. Art. n.32dEa/No
89TRANSITION JOINTS HDPE/GALVANIZED STEEL- DN125
Giunti di transizione PEAD/acciaio zincato- DN125IT. No. Art. n.32eEa/No
90HDPE PE100 SDR 17 BURIED DRAIN WATER PIPING AND FITTINGS - De 250 mm
Tubazioni idriche drenaggio interrate in PEAD PE100 SDR 17 ed accessori- De 250 mmIT. No. Art. n.33Lm/Ml
91MANUAL LEAK MONITORING SYSTEM FOR LPG SUPPLY TO AIRCRAFT MOCK-UP
Sistema manuale di controllo perdite per le linee di mandata al simulacroIT. No. Art. n.34Ea/No
92MANUAL LEAK MONITORING SYSTEM FOR WATER DRAIN LINE FROM AIRCRAFT MOCK-UP AND GAS SEPARATOR SIPHON TO WATER STORAGE TANK
Sistema manuale di controllo perdite per la linea di drenaggio dal simulacro e dal separatore di gas verso la vasca di accumulo idricoIT. No. Art. n.35Ea/No
9370x70x180 CM PREFABRICATED REINFORCED CONCRETE PIT WITH HEAVY TRAFFIC CAST-IRON COVER
Pozzetto in calcestruzzo armato prefabbricato carrabile 70x70x180 cmIT. No. Art. n.36Ea/No
IIId Testing - IIId Collaudo
94MECHANICAL SYSTEM TESTING
Collaudo Impianti MeccaniciIT. No. Art. n.37Ls/Ac
TOTAL PART III / Totale Parte III
PART IV- ELECTRICAL WORK / Parte IV - Opere Elettriche0.000.00
952 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 2 vieIT. No. Art. n.1aLm/Ml
962 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 2 vieIT. No. Art. n.1bLm/Ml
972 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 2 vieIT. No. Art. n.1cLm/Ml
982 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 2 vieIT. No. Art. n.1dLm/Ml
994 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 4 vieIT. No. Art. n.1eLm/Ml
1004 WAYS ELECTRIC CABLE DUCT
Cavidotto elettrico a 4 vieIT. No. Art. n.1fLm/Ml
101PULLING MANHOLES
Pozzetti di tiroIT. No. Art. n.1gEa/No
102PULLING MANHOLE - MH14
Pozzetto di tiro - MH14IT. No. Art. n.1gEa/No
1034P-160A CIRCUIT BREAKER
Interruttore 4P-160AIT. No. Art. n.2Ea/No
104ELECTRICAL LINE 3X1X120+1X70N+1X70PE
Linea elettrica 3X1X120+1X70N+1X70PE.IT. No. Art. n.3aLm/Ml
105ELECTRICAL LINE 3,5x35+25PE
Linea elettrica 3,5x35+25PEIT. No. Art. n.3bLm/Ml
106ELECTRICAL LINE 3X1X70+1X35N+1X35PE
Linea elettrica 3X1X70+1X35N+1X35PEIT. No. Art. n.3cLm/Ml
107ELECTRICAL LINE 5G6
Linea elettrica 5G6IT. No. Art. n.3dLm/Ml
108ELECTRICAL LINE 5G10
Linea elettrica 5G10IT. No. Art. n.3eLm/Ml
109ELECTRICAL LINE FG16M16 4G2,5
Linea elettrica FG16M16 4G2,5IT. No. Art. n.3fLm/Ml
110ELECTRICAL LINE FG16M16 4G2,5
Linea elettrica FG16M16 4G2,5IT. No. Art. n.3eLm/Ml
111DISTRIBUTION PANEL DP
Quadro di Distribuzione DPIT. No. Art. n.4Ea/No
112CONTROL BOARD
Quadro ComandoIT. No. Art. n.5Ea/No
113LIGHTING POLE
Pali luceIT. No. Art. n.6Ea/No
114LIGHTING POLE CABLEDUCT
Cavidotto per pali luceIT. No. Art. n.7Lm/Ml
11594 W LED FLOODLIGHTS
Proiettori da 94 W a LEDIT. No. Art. n.8Ea/No
116GROUNDING /EQUIPOTENTIAL SYSTEM
Impianto di terra/equipotenzialeIT. No. Art. n.9Ls/Ac
117TVCC CAMERA SYSTEM
Impianto Telecamera TVCCIT. No. Art. n.10Ls/Ac
118TESTING OF SYSTEMS
Collaudo degli impiantiIT. No. Art. n.11Ls/Ac
0.00
TOTAL PART IV / Totale Parte IV
PART V - AIRCRAFT MOCKUP AND SYSTEMS / Parte V - Simulacro d'aereo e Impianti
Va Aircraft Mockup - Va Simulacro d'aereo
119NEW AIRCRAFT STEEL MOCK-UP
Nuovo simulacro di aereo in acciaioIT. No. Art. n.1EA/NO
Total Aircrasft Mockup - Totale Simulacro d'aereo
Vb Training Elements - Internal Fire Places - Punti di Fuoco Interni
120FIRE PLACE PASSENGER SEAT
Postazione di incendio, sedile passeggeriIT. No. Art. n.2EA/NO
121FIRE PLACE AIRCRAFT COCKPIT
Postazione di incendio, abitacolo aereoIT. No. Art. n.3EA/NO
122FIRE PLACE BATTERY
Postazione di incendio, batteriaIT. No. Art. n.4EA/NO
123CARGO BOX
Simulacro caricoIT. No. Art. n.5EA/NO
Lump Sum Total Internal Fire Places - Totale a Corpo Punti di Fuoco Interni
Vc Training Elements - External Fire Places - Punti di Fuoco Esterni
124FIRE PLACE TURBINE
Postazione di incendio, TurbinaIT. No. Art. n.6EA/NO
125FIRE PLACE TURBOPROP ENGINE
Postazione di incendio, TurboelicaIT. No. Art. n.7EA/NO
126FIRE PLACE LANDING GEAR
Postazione di incendio,Carrello di AtterraggioIT. No. Art. n.8EA/NO
127FIRE PLACE RAIL - GROUND SPIL FIRE
Postazione di incendio Fusoliera - Simulazione perdita a terraIT. No. Art. n.9EA/NO
128FIRE PLACE AUXILIARY POWER UNIT
Postazione di incendio, Alimentazione AusiliariaIT. No. Art. n.10EA/NO
129FIRE PLACE WING - GROUND SPILL FIRE
Postazione di incendio, Ala - Simulazione perdita a terraIT. No. Art. n.11EA/NO
Lump Sum Total External Fire Places - Totale a Corpo Punti di Fuoco Esterni
Vd Process Equipment - Apparecchiature di processo
13020' CONTAINER FOR TECHNICAL/CONTROL STATION
Container da 20' per locale tecnico/ controlloIT. No. Art. n.12LS / AC
131PILOT BURNER
Bruciatore pilotaIT. No. Art. n.13LS / AC
132SMOKE GENERATOR
Generatore di fumoIT. No. Art. n.14LS / AC
133SMOKE EXTRACTION SYSTEM
Impianto estrazione fumiIT. No. Art. n.15LS / AC
134FIRE ROOM STEEL CLADDING
Rivestimento in acciaioIT. No. Art. n.16LS / AC
135GAS DETECTION SYSTEM
Impianto rilevazione gasIT. No. Art. n.17LS / AC
136TEMPERATURE MONITORING SYSTEM
Impianto di controllo temperaturaIT. No. Art. n.18LS / AC
137EMERGENCY LIGHTING
Lampade di emergenzaIT. No. Art. n.19LS / AC
138EMERGENCY SHUT-OFF
Impianto di chiusura di emergenzaIT. No. Art. n.20LS / AC
139WIRED SYSTEM CONTROL (PC)
Controllo dell'impianto via PCIT. No. Art. n.21LS / AC
140WIRELESS REMOTE CONTROL
Controllo dell'impianto via wirelessIT. No. Art. n.22LS / AC
141MAIN GAS CONTROL SYSTEM
Impianto controllo gasIT. No. Art. n.23LS / AC
142INTERNAL SUPPLY PIPEWORK
Tubazioni interne utenzeIT. No. Art. n.24LS / AC
143PIPE FITTINGS AND INSTRUMENTS
Accessori tubazioni ea apparecchiatureIT. No. Art. n.25LS / AC
144WATER COOLING
Raffreddamento ad acqua via sprinklerIT. No. Art. n.26LS / AC
Lump Sum Total Process Equipment - Totale a Corpo Apparecchiature di Processo
Vd Services - Servizi
145TRANSPORT TO SITE
Trasporto al sitoIT. No. Art. n.27LS / AC
146INSTALLATION AND COMMISSIONIG
Installazione e prove di funzionamenrtoIT. No. Art. n.28LS / AC
1473rd PART CERTIFICATION
Certificazione da parte di terziIT. No. Art. n.29LS / AC
148DOCUMENTATION
DocumentazioneIT. No. Art. n.30LS / AC
149OPERATOR TRAINING
Istruzone degli operatoriIT. No. Art. n.31LS / AC
Lump Sum Total Services - Totale a Corpo Servizi
TOTAL PART V / Totale Parte V
Part VI - DESIGN SERVICES / Parte VI - Servizi di Progettazione
150NEW FIRE TRAINING DESIGN SERVICES
Sercizi di Progettazione per la nuova area addestramento incendiIT. No. Art. n.1LS / AC
TOTAL PART VI / Totale Parte VI
SUMMARY
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS
PART II - STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
PARTI IV - ELECTRICAL WORK
PARTI V - PART V - AIRCRAFT MOCKUP AND SYSTEMS
PARTI VI - PART VI - DESIGN SERVICES
TOTAL PRICE

&C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY &C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY&RSheet &P of &N

Riepilogo

ASHE 16-1043 - SUSTAIN FIRE TRAINING AIRCRAFT MOCKUP
INSTRUCTIONS FOR COMPLETING AF FORM 3052
TOTAL MATERIAL COSTS€0.00
TOTAL LABOR COSTS€0.00
TOTAL OTHER DIRECT COSTS€0.00
TOTAL DIRECT COSTS€0.00
OVERHEAD%€0.00
SUBTOTAL€0.00
PROFIT%€0.00
TOTAL PRICE€0.00
DATEFIRM NAME
TITLEBY
INSTRUCTIONS TO OFFERORS

&C&"Arial,Grassetto"&12FOR OFFICIAL USE ONLY&RSheet &P of &N

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued. Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting…