Questions Answers 4th Jul Elect Installation.pdf

PDF 632 KB Posted

Attached to
4th of July Electrical Support Services Federal contract opportunity
Solicitation number
FA561322Q0009
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

View the file

Other files for this federal contract opportunity

Other files attached to 4th of July Electrical Support Services, newest first.
File Type Posted
Atch 1 PWS_Ramstein July 4th Electrical Installation.pdf PDF
Atch 4 Data Privacy Statement.pdf PDF
Atch 3 Price List.xlsx XLSX spreadsheet
Request for Quote FA561322Q0009.pdf PDF
Atch 2 4th July Electrical Layout - Tentative.pdf PDF
Atch 7 EMS Awareness Flyer.pdf PDF
Atch 6 Subcontractor Consent Form.pdf PDF
Atch 5 Past Performance Questionnaire.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5613-22-Q-0009

27 Apr 2022 Questions and Answers

Ramstein 4th of July Electrical Installation

1. PWS, Paragraph 3.0 – What Government Property exactly is provided?

Response: Government equipment are the electrical distribution panels inside the electrical substations for supplying power. A forklift will also be provided.

2. Are theft-proof storage facilities available on site or must the contractor provide its own containers?

Response: No Government facility, for contractor use, will be provided.

3. How many electricians should be available on site?

Response: It is up to the contractor with how many people the Government’s need will be fulfilled, as per Performance Work Statement (PWS).

4. Who pays for damages of contractor property, such as damaged electrical material and electrical distribution boards, etc.?

Response: This is on the contractor’s risk, if it should happen proof needs to be provided and then negotiations will be done (after performance was provided).

5. Who provides the electrical supply/connection for WC containers?

Response: One of the awardees of the Blanket Purchase Agreements (BPAs).

The contractor who receives the placed call.

6. Will the Government provide a forklift?

Response: A forklift will be on site. Coordination between contractor and customer needs to be done in advance.

7. Is it possible to store all the electrical material in advance in a safe place on base?

Response: No Government facility, for contractor use, will be provided.

The parking lot will be closed. The contractor is allowed to store electrical material in the parking lot, the police will do routine checks.