Contractor

CONSTRUCTION COST ESTIMATE BREAKDOWN
CONTRACTORADDRESS
CONTRACT FOR (Work to be performed)PROPOSED TOTAL CONTRACT PRICE
RPR Install & Calibrate Fuel Meters0.00 €$0.00
WORK ORDER NUMBERWORK LOCATION
17146MORON AIR BASE, SPAIN
UNITMATERIAL COSTLABOR COSTSOTHER
LINITEMOFDIRECTLINE
NO.MEAS.QUANTI.UNITTOTALMH/MDAV.RATTOTALCOSTSTOTAL
(1)(2)(3)(4)(5)(6)(7)(8)(9)(10)
Building 115
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Vacostato and hose
Ls
4Discriminatory sensor and CPU battery
Ls
5Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 115
Building 121
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes
Ls
4Vacostato and hose
Ls
5Discriminatory sensor and CPU battery
Ls
6Magnetic probes 9 feet & installation kit
Ls
7Fuel float kit
Ls
8Water float kit
Ls
9Cable 4x2,5 explosionproof
Lm
10Module Smarts 8 connection
Ls
11Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 121
Building 203
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes & Veeder-Root TLS-350
Ls
Total Building 203
Building 212
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Vacostato and hose
Ls
4CPU battery
Ls
5Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 212
Building 302
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes & Veeder-Root TLS-350
Ls
Total Building 302
Building 303
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes
Ls
4Vacostato and hose
Ls
5Discriminatory sensor and CPU battery
Ls
6Magnetic probes 9 feet & installation kit
Ls
7Fuel float kit
Ls
8Water float kit
Ls
9Cable 4x2,5 explosionproof
Lm
10Module Smarts 8 connection
Ls
11Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 303
Building 312
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes
Ls
4Supply & Install Veeder-Root TLS-350 unit
Ls
4Vacostato and hose
Ls
5Discriminatory sensor and CPU battery
Ls
6Magnetic probes 9 feet & installation kit
Ls
7Fuel float kit
Ls
8Water float kit
Ls
9Cable 4x2,5 explosionproof
Lm
10Module Smarts 8 connection
Ls
11Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 312
Building 1426
1Clean and degas manhole
Ls
2Brushing and Painting with approval color
Ls
3Removal existing probes
Ls
4Supply & Install Veeder-Root TLS-350 unit
Ls
4Vacostato and hose
Ls
5Discriminatory sensor and CPU battery
Ls
6Magnetic probes 9 feet & installation kit
Ls
7Fuel float kit
Ls
8Water float kit
Ls
9Cable 4x2,5 explosionproof
Lm
10Module Smarts 8 connection
Ls
11Fuel Tank calibration (CALIBEX 3D)
Ls
Total Building 1426
SUMMARY
Edificio 115
Edificio 121
Edificio 203
Edificio 212
Edificio 302
Edificio 303
Edificio 312
Edificio 1426
TOTAL
DATE:FIRM NAME: