SOO_Coordination_Study.doc

DOC document 86 KB Posted

Attached to
Electrical Distribution Study Federal contract opportunity
Solicitation number
FA5575-16-Q-0003
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Statement of Objectives (English)

View the file

Other files for this federal contract opportunity

Other files attached to Electrical Distribution Study, newest first.
File Type Posted
Power_Plant_Single_Diagram.pdf PDF
SOO_Coordination_Study_(Spanish).doc DOC document
Combined_Synopsis_Solicitation.docx DOCX document
Cost_Estimate_Breakdown.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVES

(SOO)

FOR

PERFORM ELECTRICAL DISTRIBUTION FAULT PROTECTION COORDINATION STUDY

BUILDING 212

CIVIL ENGINEERING 496 ABS/CEORM

(26 July 2016)

PERFORMANCE WORK STATEMENT (PWS)

TABLE OF CONTENTS

SECTION

PAGE

1. DESCRIPTION OF SERVICES

5/6

2. SERVICES SUMMARY

3. GOVERNMENT FURNISHED UTILITIES

4. GENERAL INFORMATION

7/9

5. APPENDICES

1. DESCRIPTION OF SERVICES. The contractor shall provide all management, tools, supplies, equipment and labor needed to perform the non-severable service of electrical distribution fault protection coordination study. Calibrate all central Power Plant distribution feeder relays (four circuits), 50/60 frequency rotary converter and 50/60 frequency static converters units (6x750 KW) in relationship to coordination study results from Moron AB distribution system at Power Plant, building 212.

1.1. System Description.

The power plant of the Moron AB feeds the Energy consumptions from a medium voltage busbar with four feeders, in accordance with attached single diagram.

To this busbar there are connected the following generators:

· Three diesel generators 1500 KW

· One group of motor-generator 2500 KW

· Group of Static Frequency Converters, 6 units 750 KW each.

1.2. Objectives of Work.

1.2.1 Protection Issues:

· It will be necessary to check the actual protection values set in the electromechanical and digital relays. Technical personal specialized in protection will test all the relays in order to confirm the actual values and the right operation of all the equipment.

· At the same time, a whole study for the selectivity of the devices and the calculation of the setting of trip values. Several general data from the installation will be needed, so at the right time a list of data will be required from the cables, devices, etc.

· Results of this study will be compared with the actual settings, this way, a solution of improvement for the new settings of the relays will be proposed and justified.

· All these actions will be developed with a test sets for testing all generations and types of protection relays. To complete the work, the contractor must use a test set and commissioning tool with all the protection functions as indicated in the following chart:

Quick CMC
Quick and easy PC controlled manual testing
State Sequencer
Determining operating times and logical timing relations by state-based sequences
Ramping
Determining magnitude, phase, and frequency thresholds by ramping definitions
TransPlay
Playback of COMTRADE files, recording of binary input status
Harmonics
Generation of signals with superimposed harmonics
Binary I/O Monitor
Status display of all binary inputs and outputs of the test setup
CB Simulation
Module for setting the CB simulation
Polarity Checker
Wiring check using the optional CPOL hardware
AuxDC Configuration
Setting of the auxiliary DC supply
Pulse Ramping
Determining magnitude, phase and frequency thresholds by pulse ramping definitions
Overcurrent
Automatic testing of positive/negative/zero sequence overcurrent characteristics
Overcurrent Char. Grabber
Extraction of overcurrent inverse-time characteristics and the inrush blocking of differential relays
Distance
Impedance element evaluations using automatic testing modes
Differential
Single-phase tests of the operating characteristics and inrush blocking of differential relays
Autoreclosure
Testing of the autoreclosure function with integral fault model
Advance Distance
Impedance element evaluations using automatic testing modes
VI Starting
Testing of the voltage dependent overcurrent starting function of distance relays
Advance Differential
Comprehensive three-phase differential relay testing
Annunciation Checker
Verification of the correct marshalling and wiring of protection devices
Synchronizer
Automatic testing of synchronizing devices and syncro-check relays
Transient Ground Fault
Simulation of steady state and transient ground-faults in isolated or compensated networks
Adavanced TransPlay
Playback and processing of COMTRADE, PL4 or CSV files
Meter
Testing of single and multifunction energy meters
Transducer
Testing of measurement transducers
Control Center Package
Automation tool, document-oriented test plan, template and report form. Including OMICROM Control Center (OCC), Pause Module, ExeCute, TextView, CM Engine

1.2.2 Review Faults Detection:

· Circuit breakers of feeders MV bays, receive a trip order without a confirmed origin of this control.

· This causes an open circuit undesirable.

· To avoid this situation, it must to be checked all the installation cabling in order to identify and locate the origin of this unexpected trip. In the first stage it has to be identify the conditions that force this operation, and afterwards, all the control circuits for control and protection must to be reviewed to verify if there is a short circuit, a wrong grounded contact, or another similar bad wiring.

1.2.3 Operation of Static Frequency Converters (SFC):

· Recently two new units of SFC, #5 and #6, has been installed, the extension of the two news SFC’s has involved several technical problems concerning the communication with existing ones. For this reason, the manufacturer has had to look over all the equipment, cabling, software settings till getting a successfully commissioning and setting up of all de converters together last 27th may 2016. These units are actually under warranty and the contractor can no modify the configuration of existing equipment without authorization in writing. The contractor can read relays configuration but they are not authorized to accomplish any modification.

· Nevertheless, it should be recommended confirm the right operation of all the converters without causing a wrong trip to the feeders.

1.3. Activities to be accomplished.

Phase 1:

· Getting actual protection values set in the protection relays.

· Study of protection selectivity including calculation of new protection values for the installed functions relays.

· Parameterization of protection relays with the result values

Phase 2:

· Two weeks tasks to find out the origin of the unexpected trips of feeders and repair the defect.

Phase 3:

· Test of the existing converters, checking the continuous working of all the systems.

1.4. Period of Performance. The period of performance for this contract is forty (40) days at the site. The contractor shall provide its execution time with your proposal.

2. SERVICES SUMMARY.

Performance Objective
SOW
Performance Threshold
N.A.
N.A.
N.A.

3. GOVERNMENT FURNISHED UTILITIES.

3.1. Use of Base Utilities: Base utilities are available to the Contactor at no additional expense to the Contractor. The following utilities shall be available from the existing Base utility connections in reasonable quantities:

a. Electricity 120/208 volts, 60 Hz.

b. Water.

All of the equipment, materials and labor required to accomplish the aforementioned items stipulated shall be supplied by the Contractor, as part of this contract.

3.2. Reference: Compliance with Air Force Instruction 32-1062 “Electrical Systems, Power Plants and Generators” is mandatory.

4. GENERAL INFORMATION.

4.1. Security Requirements. The contractor will request installation access through 496 ABS/CE

4.2. Physical Security. The contractor shall be responsible for safeguarding all government property provided for contractor use. At the close of each work period, government facilities, property, and materials shall be secured.

4.3. Hours of Operation.

4.3.1. Normal Hours of Operation. The contractor shall perform the services required under this contract during the following hours: Monday to Friday, 08:00-17:00. The contractor may work, with prior approval of the Contracting Officer, extended hours to ensure timely completion of work at no additional cost to the Government.

4.3.2. Recognized Holidays. The contractor is not required to provide service on the following days: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Days, Thanksgiving Day and Christmas Day. If the holiday falls on Saturday, it is observed on Friday. If the holiday falls on a Sunday, it is observed on Monday.

4.4. Conservation of Utilities. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions which prevent the waste of utilities which include the following:

4.4.1. Lights shall be used only in areas where and when work is actually being performed.

4.4.2. Mechanical equipment controls for heating, ventilation, and air conditioning systems shall not be adjusted by the contractor or by contractor employees unless authorized.

4.4.3. Water faucets or valves shall be turned off after the required use has been accomplished.

4.4.4. Government telephones shall be used only for official government business.

4.5. Records. The contractor shall be responsible for creating, maintaining, and disposing of only those government required records that are specifically cited in this SOW.

4.6. Environmental Controls:

4.6.1. Compliance with Laws and Regulations. The contractor shall be knowledgeable of and comply with all applicable Interstate, Federal, State, and Local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the Contracting Officer pursuant to notice requirements and negotiate a modification to the contract.

4.6.2. Notification of Environmental Spills. If the contractor spills or releases any substance contained in 40 CFR 302 into the environment, the contractor or its agent shall immediately report the incident to Moron AB Fire Dept at 117. The liability for the spill or release of such substances rests solely with the contractor and its agent.

4.6.3. Material Storage and Use. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness, and materials handling. This includes hazardous materials.

4.7. Government Observations. Government personnel, other than contracting officers (COs) and quality assurance personnel (QAPs), may from time-to-time, with CO coordination, observe contractor operations. However, these personnel may not interfere with contractor performance or make any changes to the contract.

4.8. Safety Requirements. In performing work under this contract, the contractor shall:

4.8.1. Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

4.8.2. Take such additional immediate precautions as the contracting officer may reasonably require for safety and mishap prevention purposes.

4.8.3. Develop and provide at the start of the orientation period or the start of the first operational performance period (if there is no orientation period) a safety plan for the protection of government facilities and property and to provide a safe work environment for contractor personnel.

4.8.4. Provide protection to government property to prevent damage during the period of time the property is under the control or in possession of the contractor.

4.8.5. Include a clause in all subcontracts to require subcontractors to comply with the safety provisions of this contract as applicable.

4.8.6. Record and report promptly (within one hour) to the contracting officer or designated government representative (GR), all available facts relating to each instance of damage to government property or injury to either contractor or government personnel.

4.8.7. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the contracting officer.

4.8.8. If the government elects to conduct an investigation of the accident/mishap, the contractor shall cooperate fully and assist government personnel in the conduct of investigation until the investigation is completed.

4.8.9. Include a clause in each applicable subcontract requiring the subcontractor's cooperation and assistance in accident reporting and investigation.

4.9. Special Qualifications. The company selected to accomplish this project must be certified by the manufacturer equipment. Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by the “Registro Oficial de Licitadores y Empresas Clasificadas del Estado,” covering the following groups, subgroups, and categories. The certificate holder must execute the activities related to the certificate.

Group
Subgroup
Category
I
4
E

4.10. Continuation of Essential DOD Contractor Services During Crisis IAW DoDI 3020.37. IAW AFI 63-124, para 2.7.1, and DODI 3020.37 this requirement is not considered mission essential.

4.11. Contract Restriction: In accordance with the Agreement of Defense and Cooperation between the Kingdom of Spain and the United States of America, any contract resulting from this notice/solicitation can only be entered into with companies authorized to carry out these activities in Spain under Spanish law. Companies must meet the requirements established by Spanish legislation for execution of Government works. In addition, in accordance with the Office of Defense Cooperation Policy Directive 400- 5 "(4) Spanish material, labor, and equipment must be used if permitted by the requirements of the contract specifications."

APPENDIXES

A. Power Plant Single Diagram.

APPENDIX A

POWER PLANT SINGLE DIAGRAM