Attachment_2_SOW_Safety_Loop_(3_June_2019).docx

DOCX document 21 KB Posted

Attached to
Active Barrier Safety Loop Federal contract opportunity
Solicitation number
FA557019QA011
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Active Barrier Safety Loop, newest first.
File Type Posted
RAFM_&_A_Safety_Loop_SOW_-_24_July_19.pdf PDF
RAFM_&_A_Safety_Loop_SOW_-_17_July_19.pdf PDF
Combo_Safety_Loop_revised_17_July_2019_.pdf PDF
Attachment_1_Site_Visit_Instructions.doc DOC document
Attachment_1_Site_Visit_Instructions.doc DOC document
Combo_Safety_Loop.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

RAF Molesworth and RAF Alconbury Active Vehicle Barrier Safety Loops 3 June 2019

1.0 BACKGROUND: RAF Molesworth and RAF Alconbury require the installation of Active Vehicle Barrier (AVB) Safety Loop Systems at the entry and exit points of the base.

1.1 SCOPE:

1.1.2 The contractor shall furnish AVB safety loop systems at RAF Molesworth and RAF Alconbury in accordance with the specifications listed below. The barrier systems shall only deploy at the correct instances of use. The safety loop shall prevent unauthorized deployment while a vehicle is within the prescribed distances listed below.

1.1.3 The contractor shall provide all labor, supervision, tools, materials, equipment, transportation and disposal necessary to provide and install the systems. All materials used must match existing installations to maintain a professional appearance. The Contractor shall be an authorized distributor and service provider of the equipment listed above or authorized substitution items.

1.1.4 The government shall provide the contractor with utilities necessary to accomplish the objectives described in this SOW.

2.0 GENERAL INFORMATION

Hours of Operation. Normal hours of operation are Monday through Friday, 0730 to 1630, excluding federal holidays. The following federal holidays are observed.

New Year’s DayJanuary 1
Birthday of Martin Luther KingThird Monday in January
Washington’s BirthdayThird Monday in February
Memorial DayLast Monday in May
Independence DayJuly 4
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
Veteran’s DayNovember 11
Thanksgiving DayFourth Thursday in November
Christmas DayDecember 25

a. Security Requirements. The contractor shall comply with all applicable Department of Defense security and safety regulations and procedures during the performance of this contract. The contractor shall not disclose and must safeguard procurement sensitive information, computer systems and data, Privacy Act data, and government personnel work products which are obtained or generated in the performance of this contract. This includes dissemination of protocols and papers not generally available to the public.

b. Installation Passes. A Government representative will coordinate the issuance of required installation passes to contractor personnel. The contractor personnel shall wear an identifiable outer garment i.e. company uniform or badge which clearly identifies them as a contractor employee at all times. The contractor shall be responsible for safeguarding all government equipment, information, and property provided for contractor use. At the end of each work period, the contractor shall ensure that the place of performance is clean and government facilities, equipment and materials secured.

c. The contractor shall be responsible for coordinating with the 423 CES for the dig permit approval. The dig permit shall be approved prior to the commencement of work.

3.0 DESCRIPTION OF REQUIREMENT:

3.1 RAF Molesworth

3.1.1 The contractor shall provide all labor, supervision, tools, materials, equipment, transportation and disposal necessary to provide and install a complete AVB Safety Loop System at RAF Molesworth.

3.1.2 The contractor will supply & install four (4) safety loop sensors. The four sensors or “safety loops” will be positioned at the front and the back of each barrier on RAF Molesworth. One sensor shall be positioned at each entry and exit point of the barrier “Inner Safety Loop” and Outer “Safety Loop” at each AVB system. The safety sensors shall be placed approximately 20ft from the Inner Safety Loop and 5ft from the Outer Safety Loop.

3.1.3 The contractor shall provide and install a single control panel at the main entry point which allows for both barriers to be controlled independently. The control panel shall include push-buttons allowing the operator to raise and lower each barrier as well as include a feedback display indicating if the barrier is in the “deployed” or “static” position. Once the push-button has been depressed, the system shall automatically deploy until the barrier is fully raised or lowered.

3.1.4 The system shall be fully integrated with the existing traffic lights located at the active barrier. The green light must be active when the barrier is in the “static” position and red light must be active when the barrier is in the “deployed” position.

3.2 RAF Alconbury

3.2.1 The contractor shall provide all labor, supervision, tools, materials, equipment, transportation and disposal necessary to provide and install a complete AVB Safety Loop System at RAF Alconbury.

3.2.2 The contractor will supply & install two (2) safety loop sensors. The two sensors or “safety loops” will be positioned at the front and the back of the barrier on RAF Alconbury. One sensor shall be positioned at the entry and exit point of the barrier “Inner Safety Loop” and Outer “Safety Loop” at the AVB system. The safety sensors shall be placed approximately 20ft from the Inner Safety Loop and 5ft from the Outer Safety Loop.

3.2.3 The contractor shall provide and install a single control panel at the main entry point which allows the operator to control the active barrier. The control panel shall include push-buttons allowing the operator to raise and lower the barrier as well as include a “feedback” display indicating if the barrier is in the “deployed” or “static” position. Once the push-button has been depressed, the system shall automatically deploy until the barrier is fully raised or lowered.

3.2.4 The system shall be fully integrated with the existing traffic lights located at the active barrier. The green light must be active when the barrier is in the “static” position and red light must be active when the barrier is in the “deployed” position.

4.0 DELIVERY, RECEIVING, STORAGE, HANDLING, AND PROTECTION OF MATERIAL

4.1 The contractor is responsible for the storage and safekeeping of all material to be used in the work including materials and installation of equipment.

4.2 The contractor will make every attempt to protect all government and non-government property and personnel on base from inconvenience, damage, or injury.

4.3 The contractor shall be responsible for directing traffic if at any point there is a disruption of traffic flow or a temporary lane closure.

4.4 The contractor shall instruct employees in utilities conservation practices and shall be responsible for operating under conditions that preclude the waste of utilities, which shall include: Lights shall be used only in areas where and when work is actually being performed, doors will be kept closed when air-conditioning or heating systems are running except when opened to move materials or enter or exit the work area. The contractor shall not adjust mechanical equipment controls for heating, ventilation, and air conditioning systems. Water faucets or valves shall be turned off after the required usage has been accomplished.

5.0 CLEANING, PROTECTION, AND ACCEPTANCE

5.1 After installation and prior to final acceptance, the worksite shall be thoroughly cleaned using materials and procedures recommended by the manufacturer.

5.2 Remove all equipment, containers, and all other material upon completion of the contract.

5.3 The job is considered complete once a final walkthrough has been conducted by a contracting and civil engineering representative. A quality assurance inspection shall be documented and signed by all parties for final acceptance.