Solicitation Number: FA5270-14-R-0020 13 June 2014
Contractor Question:
(Page 10 of 47/ Section C/ Paragraph (iv-v)) Do the past and present performance questionnaires need to be submitted in the English language?
Government Response:
On page 33 (hh) Correspondence in English (IAW DFARS 252.225-7041, Jun 1997) states: The Contractor shall ensure that all contract correspondence that is addressed to the United States Government is submitted in English or with an English translation.
(Page 1 of 47/ block 17a) Do we enter our DUNS number for CODE? Do we enter our CAGE CODE for
FACILITY CODE?
Government Response:
Offeror is not required to fill in “CODE” or “FACILITY CODE” in block 17a.
(Page 5 of 47/ CLIN DELIVERY/ TASK ORDER MINIMUM/ MAXIMUM QUANTITY
AND CLIN ORDER VALUE)
Is it possible for you to provide us with an example or description of what to enter for MINIMUM QUANTITY and MAXIMUM QUANTITY? If this is permitted could you please elaborate?
Government Response:
Offeror is not required to fill in the referenced portion of the 1449. Order minimums and maximums are addressed on page 21 of the Performance Work Statement.
(Attachment 3 Performance Work Statement page 8 of 30 (1.2)) Do we need to supply protection such as packing material and protective covering for a general cargo delivery? Will we be delivering cargo that is similar to our day to day operations?
Government Response:
Differences between a general cargo delivery and day to day delivery Are:
A day to day delivery is categorized by combination of classes (number of pieces) and zones. New and serviceable mattresses and box springs require protections (plastic bags) for both deliveries and pick up services. Plastic bags are already on the new/serviceable mattresses/box springs when they leave the warehouse(s). Contractors can re-use those plastic bags from the warehouse(s) when they pick up new/serviceable mattresses if plastic bags are still in good condition. If they are not in good condition, Contractor has to provide their own protection (plastic bags).
A general cargo delivery is not categorized by classes and zones. It is a per 4 ton truck load delivery/pick up between Kadena AB Dorms/warehouses and Camp Kinser DRMO/Kinser warehouse or between Camp Kinser DRMO/Kinser warehouse.
A general cargo delivery is either furniture going to DRMO (disposal or recycle) or furniture picked up From Chibana/Kinser warehouse and deliver to Kinser/Chibana warehouse. Both DRMO and warehouse to warehouse moves do not require plastic bags but protection (blankets) will be needed for warehouse to warehouse moves when items are wood furniture.
(Attachment 3 PWS page 7 part 1.1.4.4.2) Is the Identification and Condition Verifier the same individual as the COR?
Government Response:
Identification and Condition Verifiers are not the same as the COR. FMO warehouse has 8 Identification and condition Verifiers. 6 individuals are on Chibana, 2 are on Kinser. Their main responsibility is accountabilities of furnishings. They accompany contractors to on/off base quarters for every delivery and pickup. They talk to customers and inventory furniture and issue No Show letters and discrepancy reports.
(Attachment 3 Performance Work Statement page 11 of 30 (4.1.1)) Do we need to include our Quality Control Plan within our Technical Proposal?
Government Response:
Quality Control Plan is not required as part of your proposal. Your Technical Proposal should include your Staffing Plan.
(Attachment 1 Price Exhibit Page 3 of 8) What is the difference between a WAREHOUSE TO DRMO in A036 and a WAREHOUSE TO DRMO MOVES in A037?
A036 is between Chibana Warehouse and Kinser DRMO/warehouse; A037 is between Kinser warehouse (on Camp Kinser) and DRMO.
(Standard form 1449 page 1 blocks 23 and 24) In block 23 how many unit prices do we need to enter? In block 24 do we enter our total estimated price?
Government Response:
Only the blocks indicated in Addenda to 52.212-1 2(a) (at the top of page 9) need to be completed. For your price proposal you will complete attachment 1&2 Price Exhibits and list the total for each CLIN starting on page 3.
(Page 9 of 47 (Part III b)) May we include pictures?
Government Response:
Offerors may submit pictures but section (e)iv(D) on page 10 specifically states that elaborate formats, bindings, or color presentations are not desired or required.
General Questions:
Do we submit all 47 pages of the proposal?
Government Response:
Submit one original and one copy plus one copy on CD of your price proposal. This should include the full 47 pages of the solicitations and the price exhibits.
Our customers who have finished the past performance questionnaires are unable to send you a FAX. May they mail you these forms?
The may mail the forms, however, email would be preferred.
***Last Item***