Attachment 2 Schedule of Material Submittals.pdf

PDF 757 KB Posted

Attached to
Sampling, Testing, and Removal of Asbestos & Lead-Based Paint Federal contract opportunity
Solicitation number
FA5270-12-R-0011
Issued by
Department of the Air Force Pacific Air Forces

About this file

Attachment 2 Material Submittals

View the file

Other files for this federal contract opportunity

Other files attached to Sampling, Testing, and Removal of Asbestos & Lead-Based Paint, newest first.
File Type Posted
Amendment 0002.pdf PDF
FA5270-12-R-0011 Amendment 01.pdf PDF
Attachment 6 ACM LBP Past Performance Questionnaire.pdf PDF
Attachment 1 Specifications.pdf PDF
FA5270-12-R-0011 —
Exhibits A thru E.pdf PDF
Attachment 5 Seed Project.pdf PDF
Attachment 4 Asbestos Abatement Guideline EP1110-1-11 .pdf PDF
Attachment 3 Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 2 Page 1 of 10

PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

SECTION 01 56 00 - ENVIRONMENTAL PROTECTION

01 56 00 - 3.02A1.b.Chap.1 1 Applicable Regulations, 4

01 56 00 - 3.02A1.b.Chap.2 7 days after 2 4 NTP of each D.O 01 56 00 - 3.02A1.b.Chap.3 7 days after

3 Water Resources 4 NTP of (if applicable) each D O

LXEZ 12-2667

Air Emissions & Ozone Depleting Substances

Training Program & Env Representative

14 days before site work

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

(if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.4 7 days after

4 Hazardous Materials 4 NTP of (if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.5 7 days after

5 Hazardous Waste 4 NTP of (if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.6 7 days after

6 Solid Waste 4 NTP of each D.O

01 56 00 - 3.02A1.b.Chap.7 7 days after 7 Fuel Storage Tank 4 NTP of

(if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.8 7 days after

8 Natural Resources 4 NTP of (if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.9 7 days after

9 Polychlorinated Biphenyls (PCB) 4 NTP of (if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.10 7 days after

10 Asbestos 4 NTP of (if applicable) each D.O

AF Form 66, Sep 86 1 Nov 2011

FA5270-12-R-0011

ATTACHMENT 2 Page 2 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

01 56 00 - 3.02A1.b.Chap.11 7 days after 11 Radon 4 NTP of

(if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.12 7 days after

12 Lead-Based Paint 4 NTP of (if applicable) each D.O 01 56 00 - 3.02A1.b.Chap.13 7 days after

13 4 NTP of each D.O

01 56 00 - 3.02B1 14 Applicable Regulations, 4

Spill Preventionand Response

14 days before site workTraining Program & Env Representative 01 56 00 - 3.02B3

15 Hazardous Materials 4 (if applicable) 01 56 00 - 3.02B4

16 Hazardous Waste 4 (if applicable) 01 56 00 - 3.02B5

17 Solid Waste 4 (if applicable) 01 56 00 - 3.02B6

18 Fuel Storage Tank 4 (if applicable) 01 56 00 - 3.02B7

19 Histrical and Calutural Resources 4 (if applicable) 01 56 00 - 3.02B9

20 Polychlorinated Biphenyls (PCB) 4 (if applicable) 01 56 00 - 3.02B10

21 Asbestos 4 (if applicable)

During site work

During site work

During site work

During site work

During site work

During site work

During site work workTraining Program & Env Representative

ATTACHMENT 2 Page 3 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

01 56 00 - 3.02B11 22 Radon 4

(if applicable) 01 56 00 - 3.02B12

23 Lead-Based Paint 4 (if applicable) 01 56 00 - 3.02B13

24 4

01 56 00 - 3.02C4 25 Hazardous Waste 4

(if applicable)

3days after inspection

Spill Preventionand Response

During site work

During site work

During site work

(if applicable) 01 56 00 - 3.02C6

26 Fuel Storage Tank 4 (if applicable) 01 56 00 - 3.02C10

27 Asbestos 4

SECTION 02 41 00 - DEMOLITION AND REMOVAL

02 41 00 - 1.02 7 days after 28 Demolition and Removal 4 NTP of

Procedures each D.O.

SECTION 02 82 14.00 10 - ASBESTOS HAZARD CONTROL ACTIVITIES

02 82 14.00 10-1.03.A 29 4 30

02 82 14.00 10-1.03B 7 days after 30 4 NTP of each D.O.

3days after inspection

3days after inspection

Asbestos hazard Abatement Plan

Environmental Representative

ATTACHMENT 2 Page 4 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

02 82 14.00 10-1.03C 7 days after 31 4 NTP of each D.O.

02 82 14.00 10-1.03D

32 4 30

02 82 14.00 10-1.03E.1 7 days after 33 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.a 7 days after

34 HEPA Local Exhaust 4 NTP of Equipment each D O

Permit/ licenses/ notifications

Respitatory Protection Program

Shop Drawings

Equipment each D.O.

02 82 14.00 10-1.03E.2.b 7 days after

35 Vacuum Cleaning 4 NTP of Equipment each D.O.

02 82 14.00 10-1.03E.2.c 7 days after

36 Pressure Differential 4 NTP of Monitor each D.O.

02 82 14.00 10-1.03E.2.d 7 days after

37 Air Monitoring 4 NTP of Equipment each D.O.

02 82 14.00 10-1.03E.2.e 7 days after

38 Respirators 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.f 7 days after 39 Personal Protective 4 NTP of

Clothing & Equipment each D.O.

02 82 14.00 10-1.03E.2g 7 days after

40 Glovebags 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.h 7 days after 41 Duct Tape 4 NTP of each D.O.

ATTACHMENT 2 Page 5 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

02 82 14.00 10-1.03E.2.i 7 days after 42 Disposal Containers 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.j 7 days after

43 Sheet Plastic 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.k 7 days after 44 Wetting Agent 4 NTP of each D.O.

02 82 14.00 10-1.03E.2.l 7 days after

45 Strippable Coating 4 NTP of each D Oeach D.O.

02 82 14.00 10-1.03E.2.m 7 days after 46 Prefabricated 4 NTP of

Decontamination Unit each D.O.

02 82 14.00 10-1.03E.2.n 7 days after

47 Material Safety Data 4 NTP of Sheets each D.O.

02 82 14.00 10-1.03E.3 7 days after

48 4 NTP of each D.O.

02 82 14.00 10-1.03E.4 7 days after 49 4 NTP of each D.O.

02 82 14.00 10-1.03F.1 3 days after

50 Exposure Assessment 4 inspection and Air Monitoring 02 82 14.00 10-1.03.F.2 3 days after

51 Local Exhaust System 4 inspection

02 82 14.00 10-1.03.F.3 3 days after 52 4 inspectionRecords of all waste sampling and test data

Qualifications

Training Program

ATTACHMENT 2 Page 6 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

02 82 14.00 10- 1.03.G.1 7 days after 53 Vacuums 4 NTP of each D.O.

02 82 14.00 10-1.03.G.2 7 days after

54 Water Filtration 4 NTP of Equipment each D.O.

02 82 14.00 10-1.03.G.3 7 days after

55 Ventilation Equipment 4 NTP of each D.O.

02 82 14.00 10-1.03.G.4 7 days after 56 Other Equipment 4 NTP of

Required to Contain Airborne Asbestos Fibers each D ORequired to Contain Airborne Asbestos Fibers each D.O.

02 82 14.00 10- 1.03.H.1 within 60

57 4 days after issuance

02 82 14.00 10- 1.03.H.2 within 60 58 Waste Analysis 4 days after issuance 02 82 14.00 10- 1.03.H.3 within 60

59 4 days after issuance

02 82 14.00 10- 1.03.H.4 within 60 60 4 days after issuance 02 82 14.00 10- 1.24 Before each

61 4 DO const.

close

SECTION 02 82 33.13.20 - REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD

02 82 33.13.20- 1.04.A.1 7 days after 62 Vacuum Filters 4 NTP of each D.O.

Manifest/Asbestos Waste Shipment Records

Weight Bill and Delivery Ticket

Scale Weight Measurement

Asbestos Survey or Sampling reports

ATTACHMENT 2 Page 7 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

02 82 33.13.20- 1.04.A.2 7 days after 63 Respirators 4 NTP of each D.O.

02 82 33.13.20- 1.04.B.1 7 days after

64 Sampling Result 4 sampling

02 82 33.13.20- 1.04.B.2 7 days after 65 Occupational and Envi- 4 sampling ronmental Assessment 02 82 33.13.20- 1.04.B.3 7 days after

66 Toxicity Analysis (TCLP) 4 sampling

02 82 33.13.20- 1.04.C.1 7 days after 67 Qualifications of CP 4 NTP of each D.O.

02 82 33.13.20- 1.04.C.2 7 days after

68 4 NTP of each D.O.

02 82 33.13.20- 1.04.C.3 7 days after 69 Occupant Notification 4 NTP of each D.O.

02 82 33.13.20- 1.04.C.4 7 days after

70 Testing Certification of 4 NTP of Workers and Supervisors each D.O.

02 82 33.13.20- 1.04.C.5 7 days after

71 Notification of the 4 NTP of Commencement of LBP Hazard Abatement each D.O.

02 82 33.13.20- 1.04.C.6 7 days after

72 Third Party Consultant 4 NTP of Qualifications each D.O.

02 82 33.13.20- 1.04.C.7 7 days after

73 Lead-based Paint/ 4 NTP of Removal Control Plan Incl. CP approval each D.O.

Testing Laboratory Qualifications

ATTACHMENT 2 Page 8 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

02 82 33.13.20- 1.04.C.8 7 days after 74 Rental Equipment 4 NTP of

Notification each D.O.

02 82 33.13.20- 1.04.C.9 7 days after

75 Respoiratory Protection 4 NTP of Program each D.O.

02 82 33.13.20- 1.04.C.10 7 days after

76 Hazard Communication 4 NTP of Program each D.O.

02 82 33.13.20- 1.04.C.11 7 days after

77 Vacuum Filters 4 NTP of each D Oeach D.O.

02 82 33.13.20- 1.04.C.12 7 days after 78 Clearance Certification 4 NTP of each D.O.

02 82 33.13.20- 1.04.D.1 7 days after

79 Chemicals and 4 NTP of Equipment each D.O.

02 82 33.13.20- 1.04.D.2 7 days after

80 Materials 4 NTP of each D.O.

02 82 33.13.20- 1.04.D.3 7 days after 81 MSDS for all 4 NTP of

Chemicals each D.O.

02 82 33.13.20- 1.04.E.1 3 days

82 Drawings inducating locations for 4 after LBP abatement conducted inspection 02 82 33.13.20- 1.04.E.2 3 days

83 Drawings inducating sampling 4 after locations conducted inspection 02 82 33.13.20- 1.08 Before each

84 4 DO const.

close

Lead Base Paint Survey or Sampling reports

ATTACHMENT 2 Page 9 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

SECTION 09 65 00 - RESILIENT TILE FLOORING

09 65 00 - 1.02A.1 85 Resilient Flooring, Base 4 30 and Accessories 09 65 00 - 1.02A.2

86 Adhesives 4 30

09 65 00 - 1.02B 87 Resilient Flooring, Base 4 30 and Accessoriesand Accessories 09 65 00 - 1.02C

88 Manufactures' Instruction 4 30

SECTION 09 68 00 - CARPET

09 68 00- 1.02A 89 Shop drawing for insallation 4 30

09 68 00- 1.02B.1 90 carpet 4 30

09 68 00- 1.02B.2 91 Moldings 4 30

09 68 00- 1.02C.1 92 Carpet 4 30

09 68 00- 1.02C.2 93 Molding 4 30

ATTACHMENT 2 Page 10 of 10

(LOCAL MATERIAL)

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

DATE

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN CONTRACTOR

OF ITEM, CONTRACT SUB- RECEIVED CIVIL SUSPENSE FOLLOW-UP NOTIFIED CONTRACTOR FINAL REMARKS

REFERENCE, TYPE OF MISSION IN CON- ENGINEER- DATE RESUBMITTAL APPROVAL

SUBMITTAL DATE TRACTING ING

DIS-

APPROVED APPROVED

LXEZ 12-2667

R E

C O

R D

S

Remove Asbestos and Lead Base Paint, Various Bldgs, Various Locations, Okinawa, Japan

After NTP

SCHEDULE OF MATERIAL SUBMITTALS

09 68 00- 1.02D.

94 Moisture & Alkalinity 4 30

Tests 09 68 00- 1.02E

95 Carpet Certificates 4 30

09 68 00- 1.02F 96 Operation and 4 30

Maintenance Data