FA524024Q3002 Amendment 0003 Questions and Answers.pdf
PDF 113 KB Posted
- Attached to
- 554 RHS ICF Debris Removal
- Solicitation number
- FA524024Q3002
About this file
This document contains Questions and Answers related to a federal contract opportunity for 554 RHS ICF Debris Removal services. The contract is a new requirement, not an incumbent contract. It is a 100% Small Business set-aside under NAICS 562119 with a $47M size standard. The contract will be awarded using Simplified Acquisition Procedures with a Period of Performance not to exceed 30 days. The contractor must provide all supplies, equipment, and services to perform debris removal at the Silver Flag Emergency Management facility on Andersen Air Force Base, Guam. The government estimates 250 tons of debris. Contractors are required to attend a pre-proposal site visit and submit quotes by 23 August 2024. The government will award a purchase order to the responsible offeror whose proposal is most advantageous. The Service Contract Act applies to this requirement.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA524024Q3002-0003: 554 RHS ICF Debris Removal Questions and Answers
LINE QUESTION / INQUIRY GOVERNMENT RESPONSE REFERENCE
1 We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services.
If not brand new, could you please provide the current / previous contract number?
This is a new contract requirement. N/A
2 Can roll off cans be used instead of dump trucks?
The contractor shall furnish all supplies, equipment, facilities, and services required to perform under this contract.
Attachment #1 – Performance Work Statement (PWS)
3 Will there be an Attachment 9 released regarding the scheduling procedures for a site visit?
Yes, Amendment 0002 was posted on 8-August-24 to provided pre-proposal site visit instructions.
Amendment 0002 Attachment 9 – Site Visit Instructions
4 Can we use CPAR’s instead of PPQ’s?
CPARs and PPQs are two different forms/sources of past performance information that may be submitted.
Attachment 5 – Evaluation Criteria Par. (a)(ii)
5 Will you be providing a 1449 for bidders to fill out?
No, the government will not provide a 1449 for bidders to fill out. Offerors are encouraged to review all solicitation requirements in Attachment 4.
Attachment 4 – Instructions to Offerors
6 Does the government require the ground to be leveled/resurfaced after work is completed?
No, restoration of the area to pre-construction condition is not being required.
Attachment #1 – Performance Work Statement (PWS)
7 Will the government take care of the separation or sorting of debris?
No, the government will not separate or sort the debris.
Attachment #1 – Performance Work Statement (PWS)
8 What is the volume or footprint of the area?
The government estimates 250 tons of debris. Contractors are encouraged to utilize best estimates in their proposal based on site visit.
The government anticipates the concrete slab (building’s foundation) to be demolished and included in total volume.
Attachment #1 – Performance Work Statement (PWS)
9 Is there documentation that can be provided to certify that the debris is free of hazards?
This information is not available at this time.
Attachment #1 – Performance Work Statement (PWS)
10 Are there any utilities such as power and water lines on site?
There are no active utilities on site. Attachment #1 – Performance Work Statement (PWS)
FA524024Q3002-0003: 554 RHS ICF Debris Removal Questions and Answers
11 What is the government’s timeline to complete the work?
Project completion is not to exceed 90 days.
Attachment #1 – Performance Work Statement (PWS)
12 Does the government require qualified personnel like a quality manager or SSHO?
The contractor shall ensure all employees possess the required training, certifications, and licenses for conducting debris removal services in the performance of this contract. The government will require at a minimum a “project manager” who will be responsible for the overall operations and contract completion.
Attachment #1 – Performance Work Statement (PWS)
13 How will damages to contractor’s equipment be addressed if they occur?
Contractors’ would be able to submit a claim IAW FAR part 33, in the event that contractor equipment is damaged as the result of government action under the performance of this requirement.
FAR part 33.206, Initiation of a Claim
14 Does the Service Contracts Act (SCA) apply to this requirement?
Yes Attachment 3 – SCA Wage Determination 2015-5693